Home / Browse projects / Bengaluru Urban, Karnataka / KUMAR PROSPERA
KUMAR PROSPERA
RG-KA-20097 · RERA PRM/KA/RERA/1251/446/PR/210302/003980 · Last updated on RERA Karnataka portal: 9 Jul 2026
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 60 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
KUMAR PROSPERA is a Residential/Group Housing project by Kumar Properties Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/210302/003980 on 2 Mar 2021. Possession is promised by 30 Jun 2030. The completion date has moved by 60 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameKUMAR PROSPERA
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/210302/003980
- ReraGenie IDRG-KA-20097
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on2 Mar 2021
- Promised completion30 Jun 2030
- Revised completionRevised to 30 Jun 2030 (originally 30 Jun 2025)
- Buildings2 building records
- Documents filed111 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A | - | - | - | 73 | 0 | 73 |
| Block B | - | - | - | 127 | 0 | 127 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Munawar Burhan | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | C B Vivek Uthaiah |
| Engineer | Sunil Mutalik & Associates |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterForce Majeure
No reason recorded in the filing
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00460/2026 | - | Kumar Properties Pvt Ltd | 04/05/2026 |
Documents filed111
As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/210302/003980 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Application for modificationFile: Application for modification.pdf | 9 Jul 2026 |
| Consent Letter 01File: Consent Letter 01.pdf | 9 Jul 2026 |
| Consent LetterFile: Consent Letter.pdf | 9 Jul 2026 |
| Consent Letter 02File: Consent Letter 02.pdf | 9 Jul 2026 |
| Query answersFile: Query answer.pdf | 9 Jul 2026 |
| Anual Audit 2021-22 ACK- Annexure - 1File: Anual Audit 2021-22 ACK.pdf | 7 Jul 2025 |
| Form 7 CA Certificate FY 2021-22File: Form 7 CA Certificate FY 2021-22.pdf | 7 Jul 2025 |
| FR No 18531of 2025 kumar prop vs State of Kar Annexure - 2File: FR No 18531of 2025 kumar prop vs State of Kar.pdf | 7 Jul 2025 |
| Query ReplyFile: Query Reply.pdf | 7 Jul 2025 |
| Bescom NOCFile: Bescom NOC.pdf | 7 Jul 2025 |
| BWSSBFile: BWSSB.pdf | 7 Jul 2025 |
| Anual Audit 2021-22 ACKFile: Anual Audit 2021-22 ACK.pdf | 4 Jun 2025 |
| RERA Query reply letterFile: RERA Query reply letter.pdf | 4 Jun 2025 |
| 2020 Balance SheetFile: BS 2020.pdf | 18 Feb 2021 |
| 2020 PLFile: PL 2020.pdf | 18 Feb 2021 |
| 2020 ITRFile: ITR 2020.pdf | 18 Feb 2021 |
| 2020 Director ReportFile: Dir Report 2020.pdf | 18 Feb 2021 |
| 2020 Audit ReportFile: Aud Report 2020.pdf | 18 Feb 2021 |
| 2019 Balance SheetFile: BALANCE SHEET 2019.pdf | 18 Feb 2021 |
| 2019 PLFile: PROFIT and LOSS 2019.pdf | 18 Feb 2021 |
| 2019 ITRFile: IT RETURN 2019.pdf | 18 Feb 2021 |
| 2019 Audit ReportFile: AUDITOR REPORT 2019.pdf | 18 Feb 2021 |
| Cash flow 2019File: CASH FLOW STATEMENT 2019.pdf | 18 Feb 2021 |
| BANK ACCOUNT DETAILSFile: BANK .pdf | 12 Feb 2021 |
| BBMP SANCTION ORDERFile: Kino BBMP Sanction order.pdf | 12 Feb 2021 |
| ALL PLANS MERGEDFile: ALL PLANS.pdf | 12 Feb 2021 |
| ECFile: EC.pdf | 12 Feb 2021 |
| RECTIFICATION DEEDFile: RECTIFICATION DEED.pdf | 12 Feb 2021 |
| AUDITOR REPORT 17-18, 18-19, 19-20File: AUDITOR REPORT 17-18, 18-19, 19-20.pdf | 12 Feb 2021 |
| BALANCE SHEET 17-18, 18-19, 19-20File: BALANCE SHEET- 17-18, 18-19, 19-20.pdf | 12 Feb 2021 |
| CASH FLOW 17-18, 18-19, 19-20File: CASH FLOW STATEMENT 17-18, 18-19, 19-20.pdf | 12 Feb 2021 |
| IT RETURN 17-18, 18-19, 19-20File: IT RETURN 17-18, 18-19, 19-20.pdf | 12 Feb 2021 |
| PROFIT & LOSS 17-18, 18-19, 19-20File: PROFIT & LOSS 17-18, 18-19, 19-20.pdf | 12 Feb 2021 |
| CertificateFile: incorporation certificate.pdf | - |
| Project Details | - |
| Already registered project ongoing detailsFile: Quarterly Update Details March 26.pdf | - |
| Modified plan details site plan, floor plans, Plan Licence LetterFile: BUILDING LICENCE (2).pdf | - |
| Elevation, Sections, Specifications ( If changes are there )File: Plan Approval A Block (3).pdf | - |
| List Of AllotteesFile: Sold and Unsold units.pdf | - |
| List Of ComplaintsFile: Complaint details.pdf | - |
| Consent LetterFile: Consent Letters.pdf | - |
| Chartered Accountant CertificateFile: Form 4 CA certificate.pdf | - |
| Notarized AffidavitFile: Affidavit cum declaration.pdf | - |
| Engineer CertificateFile: Form 6 Engineer Certificate for Modifiction of plan.pdf | - |
| Architect CertificateFile: Form 5 Architect certificate for Modification.pdf | - |
| Structural Engineer Certificate for stability of structureFile: Stability Certificate with Lisence copy.pdf | - |
| Modification of Plan DetailsFile: KP Site Plan.pdf | - |
| Modification of Plan DetailsFile: Plan Approval A Block.PDF | - |
| Modification of Plan DetailsFile: BUILDING LICENCE (2).pdf | - |
| Modification of Plan DetailsFile: Sold and unsold units.xlsx | - |
| Modification of Plan DetailsFile: Sold and unsold units.xlsx | - |
| Document 1File: KSPCB NOC 23-7-2020.pdf | - |
| Affidavit NOCFile: Affidavit NOC.pdf | - |
| Stability Certificate with Lisence copyFile: Stability Certificate with Lisence copy.pdf | - |
| Sold and Unsold unitsFile: Sold and Unsold units.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate for Work Completion.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate for Work Completion.pdf | - |
| CA Certificate for Funds UtilizationFile: 5 CA Certificate for Funds Utilization.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate for Pending Work Completion.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for Pending Work Completion.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: 8 CA Certificate for Funds required for Project Completion.pdf | - |
| AffidavitFile: Extension Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: ECC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: sold and unsold units.xlsx | - |
| Document 1File: HDFC Bank April 2025 statement.pdf | - |
| Document 2File: HDFC BANK April 2024 to March 2025.pdf | - |
| Document 3File: HDFC BANK Nov 23 to March 2024.pdf | - |
| KP Site Plan | - |
| RERA AGREEMENT FOR SALE-kumar | - |
| SALE DEED AND GIFT DEED | - |
| KP Site Plan | - |
| CDP PLAN | - |
| proforma of allotment letter | - |
| Project Specification | - |
| EC-FINAL2000-2020 | - |
| Affidavit | - |
| JDA AFFIDAVIT | - |
| KP Khata 18-19 | - |
| JDA 2 | - |
| RTC,MUTATION,PANI | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Princetown Royale | - | Completed | - | No date filed |
| Princetown | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep KUMAR PROSPERA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Kumar Properties Pvt Ltd
Kumar Properties Pvt Ltd has 2 registrations on RERA Karnataka, including Kumar Kino Platinum and KUMAR PROSPERA. Its filings declare 3 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if KUMAR PROSPERA is delayed beyond 30 Jun 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of KUMAR PROSPERA?
The registered promoter entity is Kumar Properties Pvt Ltd, a company as per the filing. Its CIN U70101MH2000PTC216236 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in KUMAR PROSPERA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KUMAR PROSPERA?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at KUMAR PROSPERA?
The professionals named in the filing: Architect: C B Vivek Uthaiah; Engineer: Sunil Mutalik & Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KUMAR PROSPERA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.