Home / Browse projects / Bengaluru Urban, Karnataka / Kumar Kino Platinum
Kumar Kino Platinum
RG-KA-67027 · RERA PRM/KA/RERA/1251/309/PR/170915/000222 · Last updated on RERA Karnataka portal: 28 Jan 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Kumar Kino Platinum is a Residential/Group Housing project by Kumar Properties Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/170915/000222 on 15 Sep 2017. Possession is promised by 30 Sep 2022. The completion date has moved by 21 months from the original filing.
At a glance
Project
- NameKumar Kino Platinum
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/170915/000222
- ReraGenie IDRG-KA-67027
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Sep 2017
- Promised completion30 Sep 2022
- Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2020)
- Buildings1 building record
- Documents filed73 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kumar Kino Platinum | - | - | - | 38 | 0 | 38 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 28 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 28 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | InFORM Architects |
| Engineer | Mr. Sunil Mutalik |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc; Shortage of Labour; Awaiting Approvals; Awaiting OC
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed73
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/170915/000222 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| NOC BESCOM - UPLOADEDFile: Bescom.pdf | 28 Jan 2022 |
| NOC BWSSB - UPLOADEDFile: BWSSB.pdf | 28 Jan 2022 |
| EXPLANATION FOR BANK ACCOUNTFile: 1 Explanation for bank account.pdf | 12 Nov 2021 |
| STP WORKORDERFile: 2 STP workorder.pdf | 12 Nov 2021 |
| STP LOCATION PLANFile: 3 STP LOCATION PLAN.pdf | 12 Nov 2021 |
| RELINQUISHMENT DEEDFile: 4 RELINQUISHMENT DEED KINO.pdf | 12 Nov 2021 |
| ALLOTEE LISTFile: 6 ALLOTTEE LIST.xls | 12 Nov 2021 |
| STABILITY CERTIFICATEFile: 7 Stability Certificate.PDF | 12 Nov 2021 |
| REASOM FOR DELAY IN PROJECTFile: 8 REASON FOR DELAY IN PROJECT.pdf | 12 Nov 2021 |
| AFFIDAVIT IN LIEU OF CONSENTFile: 9 Affidavit in lieu of consent LETTER.pdf | 12 Nov 2021 |
| FUND REQURIED VERTIFICATEFile: 10 Fund Required Certificate.pdf | 12 Nov 2021 |
| FUND UTILZATION CERTIFICATEFile: 11 funds Utilzation certificate.pdf | 12 Nov 2021 |
| BANK STATEMENT FROM 2018 TO TILL DATEFile: 12 BANK STATEMENT FROM 2018 TILL DATE.pdf | 12 Nov 2021 |
| CertificateFile: ROC.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate WORK COMPLETED.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: ENG CERT WORK COMPLETED KUMAR KINO.pdf | - |
| CA Certificate for Funds UtilizationFile: 11 funds Utilzation certificate.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate WORK Pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: ENG CERT WORK PENDING KINO.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: 10 Fund Required Certificate.pdf | - |
| AffidavitFile: Affidavit for seeking Extension of Registration of Project.pdf | - |
| Latest Encumbrance CertificateFile: EC 2004 2021.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: 4 SOLD & UNSOLD.xlsx | - |
| Document 1File: Form-B Affidavit cum Declaration.pdf | - |
| Document 2File: Affidavit in lieu of consent LETTER.pdf | - |
| Document 3File: Affidavit Project Extension.pdf | - |
| Document 4File: Bank statement.pdf | - |
| Document 5File: 6 KPPL Authorised Signatory Board Resolution.pdf | - |
| CC - KINO | - |
| consolidated-10 | - |
| consolidated-10 | - |
| Kino Deed | - |
| consolidated-10 | - |
| Area-Kino | - |
| 18NOC | - |
| 19Specifications-Kino | - |
| Kino EC-2 | - |
| Khatha Kino FY 17-18 | - |
| Balance Sheet 2015 - 2016File: BS 16.pdf | - |
| Balance Sheet 2014 - 2015File: BS 15.pdf | - |
| Balance Sheet 2013 - 2014File: BS-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PL16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: PL15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: PL14.pdf | - |
| Cash Flow Statement 2015 - 2016File: cas.pdf | - |
| Auditor's Report 2015 - 2016File: AD 16.pdf | - |
| Auditor's Report 2014 - 2015File: AD 15.pdf | - |
| Auditor's Report 2013 - 2014File: AD 14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR 16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR 15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR 14.pdf | - |
| 23Form B Kino | - |
| Prospectus/BrochureFile: Kumar Kino Platinum E-Brochure.pdf | - |
| Advertisement Copy 1File: kino ad.jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_170915_000222.xlsx | - |
| Loan raised documentFile: Release deed.pdf | - |
| Stability CertificateFile: Stability Certificate.PDF | - |
| Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: road cutting permission.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: Fire NOC (2).pdf | - |
| Occupancy CertificateFile: OC Kino Project.pdf | - |
| Consent for operation issued by KSPCBFile: KPPL KSPCB.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift licence kino project.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Bescom (1).pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB.pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: BWSSB.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form5 Architect Certificate kino.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC CA Certificate.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit for completion.pdf | - |
| Airport IndiaFile: Airport India.jpg | - |
| BOCWWBFile: BOCWWB.pdf | - |
| BSNLFile: BSNL.pdf | - |
| CEIG approvalFile: CEIG approval.pdf | - |
| Kino BBMP Sanction PlanFile: Kino BBMP Sanction Plan.pdf | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Kumar Panchsheel | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Kumar Kino Platinum on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 18 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Kumar Properties Pvt Ltd
Kumar Properties Pvt Ltd has 2 registrations on RERA Karnataka, including Kumar Kino Platinum and KUMAR PROSPERA. Its filings declare 3 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Kumar Kino Platinum is delayed beyond 30 Sep 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Kumar Kino Platinum?
The registered promoter entity is Kumar Properties Pvt Ltd, a company as per the filing. Its CIN U70101MH2000PTC216236 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Kumar Kino Platinum?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Kumar Kino Platinum?
The professionals named in the filing: Architect: InFORM Architects; Engineer: Mr. Sunil Mutalik. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kumar Kino Platinum?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.