ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / KBR NAVARATHNA RESIDENCY

Registration approved Residential/Group Housing project

KBR NAVARATHNA RESIDENCY

By KBR Homes India Private Limited

RG-KA-01592 · RERA PRM/KA/RERA/1251/309/PR/220104/004621 · Last updated on RERA Karnataka portal: 29 Dec 2021

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 61 documents Report an error

KBR NAVARATHNA RESIDENCY is a Residential/Group Housing project by KBR Homes India Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/220104/004621 on 4 Jan 2022. Possession is promised by 25 Dec 2023.

At a glance

Project

  • NameKBR NAVARATHNA RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/220104/004621
  • ReraGenie IDRG-KA-01592

Builder

  • NameKBR Homes India Private Limited
  • Entity typeCompany
  • CINU70102KA2012PTC064637
  • Authorized SignatoryK.BABU RAJU
  • DirectorK.BABU RAJU
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJan 2022PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Jan 2022
  • Promised completion25 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KBR NAVARATHNA RESIDENCY---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 29 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,558 sq m
Named landowners3
LandownerVillageDistrict
K.BABU RAJU--
K.KUMAR--
K.S VENKATESHAIAH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.24 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMBIANT ASSOCIATES Mr. Srinivas
EngineerGirish M Swamy Consultants

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed61

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/220104/004621 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
1. UPDATED PAYMENT PLAN AND UPLOAD THE AOS - UPLOADEDFile: KBR N R Draft Sale agreement.pdf29 Dec 2021
1.PROFORMA SALE DEED WITH PROJECT SPECIFICATION - UPLOADEDFile: Proforma Sale Deed.pdf21 Dec 2021
2.PROFORMA OF AGREEMENT OF SALE - UPLOADEDFile: Proforma Agreement to Sell.pdf21 Dec 2021
KSPCB NOCFile: NOC KSPCB.pdf22 Nov 2021
UNAUDITED FINANCIALS STATEMENTFile: UNAUDITED FINACIALS.PDF2 Nov 2021
IT DUE DATE DECLARATIONFile: IT DUE DATE DECLARATION.pdf13 Oct 2021
KSPCBFile: KSPCB FEE RECEIPT.jpg13 Oct 2021
STP DRAWINGSFile: STP DRAWINGS.pdf13 Oct 2021
FINACIALS 2019-2020File: FINACIALS 2019-2020.pdf22 Sep 2021
FINACIALS 2020-2021File: Finacials 2020-2021.pdf22 Sep 2021
BESCOM NOCFile: BESCOM Noc.pdf22 Sep 2021
BWSSB NOCFile: BWSSB Noc.pdf22 Sep 2021
KSPCB NOC APPLICATIONFile: KBR NR - KSPCB NOC UNDER PROCESS.pdf22 Sep 2021
KATHAFile: KATHA.pdf22 Sep 2021
CertificateFile: Incorporation certificate.PDF-
Approval letter-
Sanction plan-
Approval letter & Sanction Plan-
Performa of Sale deed-
Performa of sale agreement-
Sale deed-
Sanction plan-
Sanction plan-
Performa of allotment letter-
BROCHURE-
Project specification-
EC 2021-
SECTION(3) AFFIDAVIT-
JD AFFIDAIVT-
Katha-
JDA-
Title deed-
Bescom NOC Affidavit-
BWSSB Noc-
Unnamed document-
Approval letter & Sanction Plan-
Sanction plan-
Project Specification & Plan-
Approval letter-
LEGAL REPORTS-
Balance Sheet 2019 - 2020File: Balance sheet 2019.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 2018.pdf-
Balance Sheet 2017 - 2018File: Auditor report 2017-2018.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit & loss 2019.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and loss 2018.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit & Loss 2017.pdf-
Director's Report 2019 - 2020File: Directors Report.pdf-
Director's Report 2018 - 2019File: Directors Report 2018.pdf-
Director's Report 2017 - 2018File: Director Report 2017.pdf-
Cash Flow Statement 2019 - 2020File: Cash flow 2019.pdf-
Cash Flow Statement 2018 - 2019File: cash flow 2018.pdf-
Auditor's Report 2019 - 2020File: Auditor Report 2019.PDF-
Auditor's Report 2018 - 2019File: Audit Report 2018.PDF-
Auditor's Report 2017 - 2018File: Auditor report 2017.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR 2019.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR 2018-19.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 2017-2018.pdf-
FORM-B-
Tower Excel SheetFile: PRMKARERA1251309PR220104004621.xlsx-
Occupancy CertificateFile: KBR NR OC DATED 14-08-2023.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: KBR NR AFFIDAVIT COMPLETION.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
KBR PEARL-Completed-No date filed
KBR ELITE-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep KBR NAVARATHNA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: KBR Homes India Private Limited

KBR HOMES INDIA PRIVATE LIMITED has 2 registrations on RERA Karnataka, including KBR PRIME and KBR NAVARATHNA RESIDENCY. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if KBR NAVARATHNA RESIDENCY is delayed beyond 25 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of KBR NAVARATHNA RESIDENCY?

The registered promoter entity is KBR Homes India Private Limited, a company as per the filing. Its CIN U70102KA2012PTC064637 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in KBR NAVARATHNA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KBR NAVARATHNA RESIDENCY?

The professionals named in the filing: Architect: AMBIANT ASSOCIATES Mr. Srinivas; Engineer: Girish M Swamy Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KBR NAVARATHNA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KBR NAVARATHNA RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KBR NAVARATHNA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.