Home / Browse projects / Thane, Maharashtra / JVMs Hive

Registered No litigation declared Commercial project

JVMs Hive

By Mehta Realtors

RG-MH-19481 · RERA P51700077770 · Last updated on MahaRERA portal: 19 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
8 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
122 of 143Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

JVMs Hive is a Commercial project by Mehta Realtors in Thane, Maharashtra, registered with MahaRERA as P51700077770 on 29 Oct 2024. Possession is promised by 31 Dec 2027. 21 of the 143 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameJVMs Hive
  • TypeCommercial
  • Location
    • Wagle Estate Industrial Area
    • THANE
    • Thane (M Corp.)
    • 400604
  • Pincode400604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700077770
  • ReraGenie IDRG-MH-19481

Builder

  • NameMehta Realtors
  • Entity typePartnership
  • Abcabc xyz
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredOct 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Oct 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed56 files

Current status

15%21 of 143 units booked
20.8%Work done, per cost certificate

Figures as on 19 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 1NA7706868
Building No 2NA7707575

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

Building No 146%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises14%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 248%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises33%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes13%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed86

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots86
Closed/Covered86
BuildingClosed/CoveredTotal
Building No 14343
Building No 24343

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,035 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jul 2025

Approvals and building plan

Sanctioning authorityMaharashtra Industrial Development Corporation
Permissible FSI7326.0
Proposed, not sanctioned6,225 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD ACKRUTI SMC NEAR MSRTC BUS DEPOT POKHRAN ROAD NO1 KHOPAT THANE MAHARASHTRA 400606
Estimated costRs 31.94 cr
Cost incurredRs 6.66 cr
Work done20.84%
BuildingWingEstimatedIncurred
Building No 1NARs 15.65 crRs 3.33 cr
Building No 2NARs 15.65 crRs 3.33 cr
-NARs 63.87 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPB Associates
ArchitectAlphine Architects Pvt Ltd
EngineerSK Consultants & Engineers
Chartered AccountantNB Sayed & Associates
PartnerRole in project
Mehta Realtors-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600017Bhakti AchrekarMehta Realtors07/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 26-03-30 FORM-1.pdf19 Apr 2026
Withdrawal Update Form 2File: Form 2 JVSM Hive.pdf19 Apr 2026
Withdrawal Update Form 3File: Form 3 - Hive as on 31-03-2026.pdf19 Apr 2026
Withdrawal Update Form 1File: Form 1 - Hive as on Dec 2025.pdf26 Mar 2026
Withdrawal Update Form 2File: Form 2 - Hive as on Dec 2025 (SIGNED).pdf26 Mar 2026
Withdrawal Update Form 3File: Form 3 - Hive as on Dec 2025.pdf26 Mar 2026
Withdrawal Update Form 1File: Form 1 - Hive as on Sep 2025.pdf4 Dec 2025
Withdrawal Update Form 2File: Form 2 - Hive as on Sep 2025.pdf4 Dec 2025
Withdrawal Update Form 3File: Form 3 - Hive as on 30-09-2025.pdf4 Dec 2025
Withdrawal Update Form 1File: Form 1 - Hive as on June 2025.pdf4 Nov 2025
Withdrawal Update Form 2File: Form 2 - Hive as on June 2025.pdf4 Nov 2025
Withdrawal Update Form 3File: Form 3 - Hive as on June 2025.pdf4 Nov 2025
Details of encumbrances concerned to FinanceFile: JVM HIVE.pdf26 Jun 2025
Details of encumbrances concerned to LegalFile: JVM HIVE.pdf26 Jun 2025
Proforma of Agreement for saleFile: AFS - Hive.pdf25 Jun 2025
Proforma of Agreement for saleFile: AFS - Hive.pdf25 Jun 2025
Layout approvalFile: Plan 1.pdf4 Mar 2025
Building plan approvalFile: Plan 2.pdf4 Mar 2025
Building plan approvalFile: Plan 3.pdf4 Mar 2025
Building plan approvalFile: Plan 4.pdf4 Mar 2025
Building plan approvalFile: Plan 5.pdf4 Mar 2025
Copy of Layout Approval (in case of layout)File: Plan 1.pdf4 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan 3.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan 4.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan 5.pdf4 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Hive as on Dec 2024.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Hive as on Dec 2024.pdf21 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Hive as on Dec 2024.pdf21 Feb 2025
Building plan approvalFile: 11zon_merged-PDF.pdf23 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 11zon_merged-PDF.pdf23 Oct 2024
Other - TechnicalFile: mail copy.pdf23 Oct 2024
Copy of the legal title reportFile: Final Mehta Realtors Title_compressed.pdf22 Oct 2024
Proforma of Allotment letterFile: AL_Hive_ Mehta Realtors_21102024.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mehta Realtors_11zon (1).pdf22 Oct 2024
Other - LegalFile: 2 Other - Legal.pdf22 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A) (34).pdf22 Oct 2024
Deviation Report with respect to Allotment letterFile: deviation report Mehta Realtors.pdf22 Oct 2024
Other - TechnicalFile: Order 50 (1).pdf22 Oct 2024
Proforma of Agreement for saleFile: Final AFS-Hive.pdf22 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Mehta Realtors.pdf22 Oct 2024
Layout approvalFile: Appoval Drawings p1-output.pdf21 Oct 2024
PAN CardFile: Mehta Realtors NEW PAN CARD.pdf21 Oct 2024
Details of encumbrances concerned to FinanceFile: encumbrances Finance.pdf21 Oct 2024
Details of encumbrances concerned to FinanceFile: encumbrances legal.pdf21 Oct 2024
Copy of Layout Approval (in case of layout)File: Appoval Drawings p1-output.pdf21 Oct 2024
Declaration in FORM BFile: Form B Notary Affidavit.pdf21 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: B 21 and B 24 CC letter (1).pdf21 Oct 2024
Declaration about Commencement CertificateFile: Format D MEHTA REALTORS.pdf21 Oct 2024
CERSAI detailsFile: Cersai Declaration Maharera.pdf21 Oct 2024
Details of encumbrances concerned to LegalFile: encumbrances Finance.pdf21 Oct 2024
Details of encumbrances concerned to LegalFile: encumbrances legal.pdf21 Oct 2024
Deviation Report with respect to model copy of AgreementFile: deviation report Jitendra Mehta (1).pdf21 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged (17).pdf21 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secure _Unsecured finace availed for the project (1).pdf21 Oct 2024

How this compares with Thane

15%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JVMs Hive on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THANE7,600+ in Thane

2 kmJVMs HiveCompleted 97Lapsed / revoked 63Other 130Dot size: filed unitsN

Filed coordinates, straight-line distance. 290 registered projects within 2 km.

Builder: Mehta Realtors

MEHTA REALTORS has 2 registrations on MahaRERA, including ORCHID and JVMs Hive. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if JVMs Hive is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JVMs Hive?

The registered promoter entity is Mehta Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JVMs Hive?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against JVMs Hive?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for JVMs Hive?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JVMs Hive?

The professionals named in the filing: Architect: PB Associates; Architect: Alphine Architects Pvt Ltd; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JVMs Hive?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JVMs Hive. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JVMs Hive to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.