Registration approved Plotted Development project

JR URBANIA PHASE5

By JR Housing Developers Pvt Ltd

RG-KA-86369 · RERA PRM/KA/RERA/1251/308/PR/171123/000428

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2019Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 63 documents Report an error

JR URBANIA PHASE5 is a Plotted Development project by JR Housing Developers Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/171123/000428 on 23 Nov 2017. Possession is promised by 30 Mar 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameJR URBANIA PHASE5
  • TypePlotted Development
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/171123/000428
  • ReraGenie IDRG-KA-86369

Builder

  • NameJR Housing Developers Pvt Ltd
  • Entity typeCompany
  • CINU07010KA2004PTC035108
  • Authorized SignatoryS Jagadeeswara Reddy
  • Other registrations13 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredNov 2017First promiseMar 2018Revised toMar 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Nov 2017
  • Promised completion30 Mar 2019
  • Revised completionRevised to 30 Mar 2019 (originally 30 Mar 2018)
  • BuildingsNot stated in filing
  • Documents filed63 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area49,574 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.87 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/200218/000428Mar 2018 → Mar 2019

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed63

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/171123/000428 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Registration.jpg-
Architect Certificate for Work Completion Schedule till DateFile: JR Urbania Phase 5 Architect Certificate.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate JR Urbania Phase-5_lowres.pdf-
CA Certificate for Funds UtilizationFile: JR Urbania Phase-5 CA Certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: JR Urbania Phase 5 Architect Certificate.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate JR Urbania Phase-5_lowres.pdf-
CA Certificate for Funds required for Project CompletionFile: JR Urbania Phase-5 CA Certificate.pdf-
AffidavitFile: Form-B JRUrbania 5.pdf-
Latest Encumbrance Certificate-
Details Of Sold/ Un-sold UnitsFile: Sold and Un sold Units details of Project.xlsx-
Document 1File: RevisedApprovalLetter.pdf-
Document 2File: RevisedLayoutPlan_LowRes.pdf-
Document 3File: JR Urbania Phase-5 Chartered Accountant Form1.pdf-
Document 4File: Affidavit Form-8.pdf-
Document 5File: CA Certificate for Funds Utilization Phase 5.pdf-
Document 6File: CA Certificate for Funds Required Phase 5.pdf-
Document 7File: Affidavit Phase 5.pdf-
Document 8File: Bank Statement Phase 5.txt-
Document 9File: JR Urbania 5th Phase final release order.pdf-
Document 10File: RERA Affidavit (JR Urbania Phase-5).pdf-
Document 11File: Application_APA_JRURB5.pdf-
Document 12-
JR Urbania 5th Phase (Approval Letter)-
JR Urbania 5th Phase (Approved Layout Plan)-
LayoutPlan_5thPhase-
Proforma_Sale_Deed_JR Urbania Phase 6-
Proforma Sale Agreement JR Urbania Phase-6-
Saledeed_Location-
JR Urbania 5th Phase (Approved Layout Plan)-
Area_Development_Plan-
Allotment_Form-
ebrochure_JRUrbania-
JR Urbania th Phase (KSPCB)-
Project Specification of JR Urbania Phase-
EC (JR Urbania 5th Phase)-
Conversion_Orders_5thPhase-
JR Urbania Phase 5 Sale Deeds-
conversion orders-
JR Urbania 5th Phase Relinquishment deed-ilovepdf-compressed-
JR Urbania_5Phase_KSPCB-
Balance Sheet 2015 - 2016File: BalanceSheet_1617.jpg-
Balance Sheet 2014 - 2015File: BalanceSheet_1516.jpg-
Balance Sheet 2013 - 2014File: BalanceSheet_1415.jpg-
Audited Profit and Loss Statement 2015 - 2016File: P&L_1617.jpg-
Audited Profit and Loss Statement 2014 - 2015File: P&L_1516.jpg-
Audited Profit and Loss Statement 2013 - 2014File: P&L_1415.jpg-
Director's Report 2015 - 2016File: DirReport_1617.pdf-
Director's Report 2014 - 2015File: DirReport_1516.jpg-
Director's Report 2013 - 2014File: DirReport_1415.jpg-
Cash Flow Statement 2015 - 2016File: DirReport_1617.pdf-
Cash Flow Statement 2014 - 2015File: DirReport_1516.jpg-
Auditor's Report 2015 - 2016File: AudReport_1617.pdf-
Auditor's Report 2014 - 2015File: AudReport_1516.pdf-
Auditor's Report 2013 - 2014File: AudReport_1415.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR_1617.jpg-
Income Tax Return Acknowledgement 2014 - 2015File: ITR_1516.jpg-
Income Tax Return Acknowledgement 2013 - 2014File: ITR_1415.jpg-
Affidavit (JR Urbania Phase-5) (1)-
Prospectus/BrochureFile: JRURBANIA_eBrochure_highres.pdf-
Advertisement Copy 1File: JRURBANIA_TOI_CLASSIFIED.jpg-
Plot Excel SheetFile: PRM_KA_RERA_1251_308_PR_171123_000428.xls-
Occupancy CertificateFile: Urbania Phase 5 Final Release order.pdf-
Completion certificateFile: Urbania Phase 5 Final Release order.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep JR URBANIA PHASE5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmJR URBANIA PHASE5Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: JR Housing Developers Pvt Ltd

JR Housing Developers Pvt Ltd has 14 registrations on RERA Karnataka, including JR STRR ENCLAVE and JR ONE EAST. Its filings declare 5 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if JR URBANIA PHASE5 is delayed beyond 30 Mar 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JR URBANIA PHASE5?

The registered promoter entity is JR Housing Developers Pvt Ltd, a company as per the filing. Its CIN U07010KA2004PTC035108 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JR URBANIA PHASE5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in JR URBANIA PHASE5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JR URBANIA PHASE5. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JR URBANIA PHASE5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.