ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / JEEVANADI SAMPOORNA

Registration approved Residential/Group Housing project

JEEVANADI SAMPOORNA

By JEEVANADI ESTATES PRIVATE LIMITED

RG-KA-01743 · RERA PRM/KA/RERA/1251/309/PR/180507/001654

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 6 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2020Possession promisedmoved 6 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 69 documents Report an error

JEEVANADI SAMPOORNA is a Residential/Group Housing project by JEEVANADI ESTATES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180507/001654 on 7 May 2018. Possession is promised by 31 Dec 2020. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameJEEVANADI SAMPOORNA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/180507/001654
  • ReraGenie IDRG-KA-01743

Builder

  • NameJEEVANADI ESTATES PRIVATE LIMITED
  • Entity typeCompany
  • CINU07010KA2003PTC032396
  • Authorized SignatoryKANNAYAN MOHANRAJ
  • DirectorM KRISHNAVENI

Key dates

this monthRegisteredMay 2018First promiseJun 2020Revised toDec 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 May 2018
  • Promised completion31 Dec 2020
  • Revised completionRevised to 31 Dec 2020 (originally 30 Jun 2020)
  • Buildings2 building records
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BLOCK---84084
B BLOCK---44044

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,548 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 38.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHARADWAJ N
EngineerBHARADWAJ N

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2020 → Sep 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/200303/001654Sep 2021 → Dec 2020

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed69

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180507/001654 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed - 1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed - 1.pdf-
CA Certificate for Funds UtilizationFile: Funds Utilized.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending - 2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending - 2.pdf-
CA Certificate for Funds required for Project CompletionFile: Funds required.pdf-
AffidavitFile: Affidavit.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Consent letter from 2/3rd of AllotteesFile: NOC From Client.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold and unsold units.pdf-
Document 1File: Affidavit (2).pdf-
Document 2File: Funds required.pdf-
Document 3File: Funds Utilized.pdf-
Document 4File: Bank Statement.pdf-
Document 5File: Affidavit.pdf-
Document 6File: Affidavit (2).pdf-
Document 7File: CC.pdf-
Document 8File: Sold and unsold units.pdf-
Document 9File: NOC From Client.pdf-
Document 11File: Sold and unsold units.pdf-
Document 12File: Consent from allottees.pdf-
Document 13File: Affidavit for compensation.pdf-
Document 14File: Affidavit for seeking extension of registered project.pdf-
Document 15File: Affidavit for seeking extension of registered project.pdf-
Commencement Certificate-
2 of 4-
1 of 4-
Sale deed draft final-
Sale Agreement - draft _KODIGEHALLI_ final-
Sale Deed & RTC-
Scan-
Scan-
Flat Allotment Letter-
PROJECT SPECIFICATION JEEVANADI SAMPOORNA-
EC 2004-2018-
Khata Extract 205-16-
Joint Development Agreement-
Conversion Order-
1 of 4-
1 of 4-
Joint Development Agreement-
Balance Sheet 2016 - 2017File: Balance sheet 2017-2018.pdf-
Balance Sheet 2015 - 2016File: Balance sheet 2016-2017.pdf-
Balance Sheet 2014 - 2015File: balance sheet 2015-2016.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit and Loss statement 2017-2018.pdf-
Audited Profit and Loss Statement 2015 - 2016File: profit and loss statement 2016-2017.pdf-
Audited Profit and Loss Statement 2014 - 2015File: profit anf loss statement 2015-2016.pdf-
Director's Report 2016 - 2017File: Notice and Directors Report Jeevanadi - 16 -17(Directors Report).pdf-
Director's Report 2015 - 2016File: Notice, Board's Report and Financials 15-16 (Directors Report).pdf-
Director's Report 2014 - 2015File: Financials, Board's Report 14-15 (Directors Report).pdf-
Cash Flow Statement 2016 - 2017File: cash flow statement 2017-2018.pdf-
Cash Flow Statement 2015 - 2016File: cash flow statement 2016-2017.pdf-
Auditor's Report 2016 - 2017File: Auditors Report 2017-2018.pdf-
Auditor's Report 2015 - 2016File: Audit report 16-17.pdf-
Auditor's Report 2014 - 2015File: Auditors Report 2015-2016.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Income tax return acknowledgement 2017-2018.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Income tax return acknowledgement 2016-2017.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Income tax return acknowledgement 2015-2016.pdf-
Form_B-
Prospectus/BrochureFile: Revised_Brochure.pdf-
Advertisement Copy 1File: Jeevanadi sampoorna_33x25_Final.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180507_001654.xls-
Loan raised documentFile: Tata Capital Sanction letter_compressed.pdf-
Occupancy CertificateFile: Occupancy Certificate.pdf-
Architect certificate for having completed the work(in format no 5)File: Form-5, Architect Certificate 31-12-2021.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Jeevanadi_K RERA Form 4CC for Project Sampoorna CA Signed.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit Jeevanadi.pdf-
Engineer CertificateFile: Form -6, Engineer Certificate 31-12-2021.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 6 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep JEEVANADI SAMPOORNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: JEEVANADI ESTATES PRIVATE LIMITED

JEEVANADI ESTATES PRIVATE LIMITED has 1 registration on RERA Karnataka, including JEEVANADI SAMPOORNA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if JEEVANADI SAMPOORNA is delayed beyond 31 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JEEVANADI SAMPOORNA?

The registered promoter entity is JEEVANADI ESTATES PRIVATE LIMITED, a company as per the filing. Its CIN U07010KA2003PTC032396 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JEEVANADI SAMPOORNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JEEVANADI SAMPOORNA?

The professionals named in the filing: Architect: BHARADWAJ N; Engineer: BHARADWAJ N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JEEVANADI SAMPOORNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JEEVANADI SAMPOORNA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JEEVANADI SAMPOORNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.