ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / Jeet Residency-3BHK

Valid until 12 Jun 2026 Mixed Development project

Jeet Residency-3BHK

By Ghanshyam Bihola

RG-GJ-69216 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA03424/140918 · Last updated on GujRERA portal: 22 Jun 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
32 of 32Construction stages doneacross 4 buildings; every applicable stage filed complete
18 of 100Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Jeet Residency-3BHK is a Mixed Development project by Ghanshyam Bihola in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA03424/140918 on 14 Sep 2018. Possession is promised by 12 Jun 2026. 82 of the 100 units on this registration are recorded sold or booked, and 32 of 32 construction stages are filed complete.

At a glance

Project

  • NameJeet Residency-3BHK
  • TypeMixed Development
  • Location
    • Survey No. 383/2
    • Nr. Jeet Bunglow
    • Opp. IIT Gandhinagar
    • Palaj
    • Palaj
    • Gandhinagar
    • 382355
  • Pincode382355
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA03424/140918
  • ReraGenie IDRG-GJ-69216

Builder

  • NameGhanshyam Bihola
  • Entity typeIndividual/Propritorship
  • Other registrations1 more →
  • Past their filed date2

Key dates

this monthRegisteredSep 2018PromisedJun 2026

Key facts

Registration and timeline

  • StatusValid until 12 Jun 2026
  • Registered on14 Sep 2018
  • Promised completion12 Jun 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed41 files

Current status

82%82 of 100 units booked
100.0%Of the estimated cost spent so far

Figures as on 22 Jun 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block-B---20020
Block-C---20020
Block-D---25025
Block-A---251035

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 22 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

32 of 32 construction stages are filed complete across 4 buildings.

Block-B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block-C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block-D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block-A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 22 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,978 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.89 cr
Cost incurredRs 7.89 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Block-ANARs 1.97 crRs 1.97 cr
Block-BNARs 1.97 crRs 1.97 cr
Block-CNARs 1.97 crRs 1.97 cr
Block-DNARs 1.97 crRs 1.97 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHemant Mehta
EngineerNarendrabhai Patel

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA03424/140918 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)22 Jun 2022
Engineer's certificate (Form 2)22 Jun 2022
Engineer's certificate annexure22 Jun 2022
Accountant's certificate (Form 3)22 Jun 2022
Site photograph, Block-B22 Jun 2022
Site photograph, Block-C22 Jun 2022
Site photograph, Block-D22 Jun 2022
Site photograph, Block-A22 Jun 2022
RERA registration certificate14 Sep 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

82%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Jeet Residency-3BHK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Palaj1,600+ in Gandhinagar

2 kmJeet Residency-3BHKOther 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: Ghanshyam Bihola

Ghanshyam Bihola has 2 registrations on GujRERA, including Jeet Residency-3BHK and Jeet Residency. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Jeet Residency-3BHK is delayed beyond 12 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Jeet Residency-3BHK?

The registered promoter entity is Ghanshyam Bihola, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Jeet Residency-3BHK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Jeet Residency-3BHK?

The professionals named in the filing: Architect: Hemant Mehta; Engineer: Narendrabhai Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jeet Residency-3BHK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jeet Residency-3BHK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jeet Residency-3BHK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.