Home / Browse projects / Bengaluru Urban, Karnataka / Jain Heights East Parade Phase II

Registration approved Residential/Group Housing project

Jain Heights East Parade Phase II

By Metrik Infraprojects Pvt Ltd

RG-KA-63980 · RERA PRM/KA/RERA/1251/446/PR/171015/000396

Source: official RERA Karnataka filing

Red flags

  • 18 complaints at RERA Karnataka
  • Completion date moved by 10 months
  • 1 extension taken

Clear

  • Separate project account declared
Nov 2019Possession promisedmoved 10 months from the original
18Complaints at RERA Karnatakaon this registration
Jump to the 76 documents Report an error

Jain Heights East Parade Phase II is a Residential/Group Housing project by Metrik Infraprojects Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/171015/000396 on 15 Oct 2017. Possession is promised by 15 Nov 2019. The completion date has moved by 10 months from the original filing. 18 complaints are on record with the regulator.

At a glance

Project

  • NameJain Heights East Parade Phase II
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/171015/000396
  • ReraGenie IDRG-KA-63980

Builder

  • NameMetrik Infraprojects Pvt Ltd
  • Entity typeCompany
  • CINU45202KA2010PTC055953
  • Authorized SignatoryGururaj K
  • OthersPrakash H N
  • Declared earlier projects5 →

Key dates

this monthRegisteredOct 2017First promiseJan 2019Revised toNov 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Oct 2017
  • Promised completion15 Nov 2019
  • Revised completionRevised to 15 Nov 2019 (originally 31 Jan 2019)
  • Buildings1 building record
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block G---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,548 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.56 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThilak Thomas
EngineerShradha Designtech Pvt Ltd

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/220712/000396Jan 2019 → Nov 2019

Reason as filed by the promoterFinancial crunch

Complaints filed with RERA Karnataka18

Case no.ComplainantRespondentFiled
CMP/200315/0005726-Metrik Infraprojects Pvt Ltd15/03/2020
CMP/200624/0006053-Metrik Infraprojects Pvt Ltd24/06/2020
CMP/200701/0006071-Metrik Infraprojects Pvt Ltd01/07/2020
CMP/201225/0007076-Metrik Infraprojects Pvt Ltd25/12/2020
CMP/201225/0007322-Metrik Infraprojects Pvt Ltd25/12/2020
CMP/201225/0007323-Metrik Infraprojects Pvt Ltd25/12/2020
CMP/201225/0007324-Metrik Infraprojects Pvt Ltd25/12/2020
CMP/201225/0007325-Metrik Infraprojects Pvt Ltd25/12/2020
CMP/201225/0007326-Metrik Infraprojects Pvt Ltd25/12/2020
CMP/201227/0007331-Metrik Infraprojects Pvt Ltd27/12/2020
CMP/201228/0007335-Metrik Infraprojects Pvt Ltd28/12/2020
CMP/201229/0007337-Metrik Infraprojects Pvt Ltd29/12/2020
CMP/210114/0007367-Metrik Infraprojects Pvt Ltd14/01/2021
CMP/210114/0007356-Metrik Infraprojects Pvt Ltd14/01/2021
CMP/210126/0007355-Metrik Infraprojects Pvt Ltd26/01/2021
CMP/210126/0007350-Metrik Infraprojects Pvt Ltd26/01/2021
CMP/210127/0007352-Metrik Infraprojects Pvt Ltd27/01/2021
CMP/210129/0007521-Metrik Infraprojects Pvt Ltd29/01/2021

Documents filed76

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/171015/000396 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Registration Certificate- MIPL.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Work Completed-EP.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: EP-EX-% COMP.pdf-
CA Certificate for Funds UtilizationFile: East Parade fund utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Work Pending-EP.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: EP-EX-% PEN.pdf-
CA Certificate for Funds required for Project CompletionFile: Work Pending-EP.pdf-
AffidavitFile: FORM B.pdf-
Latest Encumbrance Certificate-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails (2).xlsx-
Document 1File: Bank Statement - EP -- 1.pdf-
Document 2File: Bank Statement - EP -- 2.pdf-
Document 3File: East Parade DP_compressed (1).pdf-
Document 4File: Affidavit - EP.pdf-
Document 5File: 2-3rd Consent Letter .pdf-
Document 6File: Doc-1.pdf-
Document 7File: CA-Certificate - Funds Utilised.pdf-
Document 8File: CA-Certificate - Funds Required.pdf-
EP- Commencement Certificate-
EP - Approved building- plotting Plan-
EP - Approved Layout Plan-
EP- Proforma of Sale Deed-
EP- Proform Agreement of Sale-
Sale deed & RTC-
EP - Approved Section of building-Infrastructure Plan of Plotting-
EP - Area Development Plan of the project area-
EP - Proforma of Allotment Letter-
EP Phase II -Brochure-
EP- All NOC's from all the authorities-
EP- Project specifications-
EC-
Khatha Certificate and Tax Paid receipt-
Joint Development Agreement-
Other Title Document-
Conversion order (1 MB)-
Section 14 of KTCP Act-
Utilization Certificate-
TDR Certificate-
Relinquishment Deed EP-
Fire NOC-
NOC Airport-
Revised BESCOM NOC-
NOC BWSSB-
KSPCB NOC-
SEIAA NOC-
BSNL-
NOC from abutting lands-
Unnamed document-
Urban Land Ceiling-
BMRCL-
Urban Arts Commission-
Inspector of factories-
District Magistrate-
Coastal regulation-
Structural Stability Certificate-
Sectional Drawing-
Balance Sheet 2015 - 2016File: MIPL Balance Sheet 15-16.pdf-
Balance Sheet 2014 - 2015File: MIPL Balance Sheet 14-15.pdf-
Balance Sheet 2013 - 2014File: MIPL Balance Sheet 13-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: MIPL Profit & Loss 15-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: MIPL Profit & loss 14-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: MIPL Profit & Loss 13-14.pdf-
Director's Report 2015 - 2016File: MIPL Director Report 15-16.pdf-
Director's Report 2014 - 2015File: MIPL Director Report 14-15.pdf-
Director's Report 2013 - 2014File: MIPL Directors Report 13-14.pdf-
Cash Flow Statement 2015 - 2016File: MIPL Cash Flow 15-16.pdf-
Cash Flow Statement 2014 - 2015File: MIPL Cash Flow 14-15.pdf-
Auditor's Report 2015 - 2016File: MIPL Auditor Report 15-16.pdf-
Auditor's Report 2014 - 2015File: MIPL Auditor Report 14-15.pdf-
Auditor's Report 2013 - 2014File: MIPL Auditor Report 13-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR MIPL 15-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR MIPL 14-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR MIPL 13-14.pdf-
EP- Declaration in Form 'B'-
Prospectus/BrochureFile: East Parade Floor plan & Brochure-1.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_171015_000396.xlsx-

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Solus2 Phase I-OngoingJul 2017Not delivered
Solus-CompletedJul 2017No date filed
Jain Heights Grand West Phase I-OngoingJul 2017Not delivered
Jain Heights East Parade Phase I-CompletedJul 2017No date filed
Jain Heights Corona-CompletedJul 2017No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 10 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Jain Heights East Parade Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Metrik Infraprojects Pvt Ltd

Metrik Infraprojects Pvt Ltd has 1 registration on RERA Karnataka, including Jain Heights East Parade Phase II. Its filings declare 5 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Jain Heights East Parade Phase II is delayed beyond 15 Nov 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Jain Heights East Parade Phase II?

The registered promoter entity is Metrik Infraprojects Pvt Ltd, a company as per the filing. Its CIN U45202KA2010PTC055953 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Jain Heights East Parade Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Jain Heights East Parade Phase II?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Jain Heights East Parade Phase II?

The professionals named in the filing: Architect: Thilak Thomas; Engineer: Shradha Designtech Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jain Heights East Parade Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jain Heights East Parade Phase II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jain Heights East Parade Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.