JAI GARDENIA

By JAI CONSTRUCTIONS

RG-KA-01973 · RERA PRM/KA/RERA/1251/446/PR/211130/004565 · Last updated on RERA Karnataka portal: 22 Nov 2021

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 69 documents Report an error

JAI GARDENIA is a Residential/Group Housing project by JAI CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/211130/004565 on 30 Nov 2021. Possession is promised by 15 Jun 2023.

At a glance

Project

  • NameJAI GARDENIA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/211130/004565
  • ReraGenie IDRG-KA-01973

Builder

  • NameJAI CONSTRUCTIONS
  • Entity typePartnership Firm
  • Authorized SignatoryM. SOMASEHKAR
  • OthersM. PRADEEP, P.YUGANDHAR REDDY, M. SOMASEHKAR, T.SRINADH, VIKAS PODILI

Key dates

this monthRegisteredNov 2021PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 Nov 2021
  • Promised completion15 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JAI GARDENIA---1300130

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 22 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 22 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,175 sq m
Named landowners9
LandownerVillageDistrict
T.SRINADH--
V.R.LAKSHMI PURNIMA--
E. DEVARAJULU NAIDU--
V.R.L. OMKAR--
M. BALAJI MADHAVA MURTHY--
VINODH PODHILI--
M. ARJUN--
M. PRADEEP--
P.ESWARA REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 32.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesh S
EngineerRamesh S

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed69

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/211130/004565 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Sharing agreementFile: Sharing agreement.pdf22 Nov 2021
specificationFile: specification.pdf22 Nov 2021
JD affidavitFile: JDA Affidavit.pdf22 Nov 2021
JD agreementFile: JDA Agreement_compressed.pdf22 Nov 2021
brochuerFile: brochuer_compressed.pdf22 Nov 2021
draft agreement of saleFile: agreement of sal draft.pdf22 Nov 2021
approved planFile: Approved plan_compressed.pdf22 Nov 2021
planFile: Approved plan.pdf22 Nov 2021
license letterFile: BUILDING LICENCE LETTER.pdf22 Nov 2021
deedFile: Sale deed_compressed.pdf22 Nov 2021
Balance sheet 2019-20 with CA UDINFile: balance sheet 2019-20 with CA UDIN.pdf11 Oct 2021
P & L 2019-20 with CA UDINFile: P & L 2019-20 with CA UDIN.pdf11 Oct 2021
Balance sheet and P & L accountFile: P & L and Balance sheet.pdf11 Oct 2021
CertificateFile: GST certificate.pdf-
CC demand notice_compressed-
Approved plan_compressed-
Approved plan_compressed-
Sale deed_compressed-
BUILDING LICENCE LETTER-
RTC-
Sale deed_compressed-
Approved plan_compressed-
BUILDING LICENCE LETTER-
Specifications_compressed-
Specifications_compressed-
EC up to date-
Section 3(1) Affidavit-
JDA Affidavit-
Katha-
JDA Agreement-
GPA-
CONVERSION ORDER-
CC demand notice_compressed-
CONVERSION ORDER-
PARTNERSHIP DEED-
RELINQUISHMENT DEED-
PARTNERSHIP DEED-
BESCOM NOC-
BWSSB NOC-
KSPCB NOC-
KSPCB NOC-
BESCOM NOC-
Unnamed document-
MR-
2019-20 BBMP TAXT-
Approved plan-
JDA Agreement-
CONVERSION ORDER-
RTC-
Balance Sheet 2020 - 2021File: Financial statement Declaration.pdf-
Balance Sheet 2019 - 2020File: Financial statement Declaration.pdf-
Balance Sheet 2018 - 2019File: 2019-20 BBMP TAXT.pdf-
Audited Profit and Loss Statement 2020 - 2021File: FIRM REGISTRATION CERTIFICATE.pdf-
Audited Profit and Loss Statement 2019 - 2020File: GST certificate.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Financial statement Declaration.pdf-
Director's Report 2020 - 2021File: Financial statement Declaration.pdf-
Director's Report 2019 - 2020File: Financial statement Declaration.pdf-
Director's Report 2018 - 2019File: Financial statement Declaration.pdf-
Cash Flow Statement 2020 - 2021File: Financial statement Declaration.pdf-
Cash Flow Statement 2019 - 2020File: Financial statement Declaration.pdf-
Auditor's Report 2020 - 2021File: Financial statement Declaration.pdf-
Auditor's Report 2019 - 2020File: Financial statement Declaration.pdf-
Auditor's Report 2018 - 2019File: Financial statement Declaration.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Financial statement Declaration.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: Financial statement Declaration.pdf-
Form B Affidavit_compressed-
Prospectus/BrochureFile: Specifications_compressed.pdf-
Advertisement Copy 1File: Specifications_compressed.pdf-
Tower Excel SheetFile: PRMKARERA1251446PR211130004565 (1).xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep JAI GARDENIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: JAI CONSTRUCTIONS

JAI CONSTRUCTIONS has 1 registration on RERA Karnataka, including JAI GARDENIA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if JAI GARDENIA is delayed beyond 15 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JAI GARDENIA?

The registered promoter entity is JAI CONSTRUCTIONS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JAI GARDENIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JAI GARDENIA?

The professionals named in the filing: Architect: Ramesh S; Engineer: Ramesh S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAI GARDENIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAI GARDENIA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAI GARDENIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.