Home / Browse projects / Bengaluru Urban, Karnataka / J V PARADISE
J V PARADISE
RG-KA-64080 · RERA PRM/KA/RERA/1251/446/PR/250924/007064 · Last updated on RERA Karnataka portal: 15 Jul 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
J V PARADISE is a Residential/Group Housing project by J V CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/250924/007064 on 25 Sep 2024. Possession is promised by 31 Dec 2026. 33 of the 33 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.
At a glance
Project
- NameJ V PARADISE
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/250924/007064
- ReraGenie IDRG-KA-64080
Builder
- NameJ V CONSTRUCTIONS
- Entity typePartnership Firm
- GSTIN29AATFJ5642E1ZY
- Authorized SignatoryCHENNUR JANARDHAN REDDY
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on25 Sep 2024
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed155 files
Current status
Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JV Paradise | - | - | - | 33 | 0 | 33 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 17 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities40
As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 100% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 100% |
| Parks | No | Not applicable |
| Power Backup | Yes | 100% |
| Piped Gas | Yes | 0% |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | No | Not applicable |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | Yes | 100% |
| Provision for lodging of management staff and security staff | Yes | 100% |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | Yes | 100% |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| J.V. Constructions | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 11.50 cr | Rs 1.04 cr |
| Payment of taxes | Rs 2.50 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 1.00 cr | - |
| On-site expenditure-Site Overhead | Rs 50.00 lakh | Rs 46,294 |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 50.00 lakh | - |
| On-site expenditure-Salaries of workers | Rs 35.00 lakh | Rs 1.72 lakh |
| On-site expenditure-Consultants Fees | Rs 15.00 lakh | Rs 50,000 |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | G Bhanumathy |
| Engineer | Maddikunta Mallikarjuna Rao |
| Chartered Accountant | Seshachalapathi J |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed155
As listed on the registration, under the names the promoter filed them with; the newest 80 of 155 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/250924/007064 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q1 26-27 JV Paradise.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 J V Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 JV Q4 25-26.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: JV FORM-5 Q4 25-26.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: JV Form-6 Engr Q4 25-26.pdf | 13 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 13 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 13 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 13 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: From-4 CA Cert JV Q3 2025-26.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Cert Q3 25-26.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate (Q3)-25-26F.pdf | 14 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 14 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 14 Jan 2026 |
| Khatha CertificateFile: Khatha JV.jpeg | 9 Jul 2024 |
| Change of Land Use ClarificationFile: CLU Clarification.pdf | 9 Jul 2024 |
| Commencement ClarificationFile: CC Clarification.pdf | 9 Jul 2024 |
| Commencement acknowledgementFile: CC AcknowledgememntJV.jpeg | 9 Jul 2024 |
| Architect Certificate with COA No.File: COA Certificate.pdf | 9 Jul 2024 |
| Water NOCFile: WATER NOCSelf attested.pdf | 9 Jul 2024 |
| Nakshe Manjurathi Pathra issued by BDAFile: NAKSHA MANJURATHI PATRA.pdf | 12 Jun 2024 |
| Khatha and ExtractFile: KHATHA AND EXTRACT.pdf | 12 Jun 2024 |
| Advocate search reportFile: LEGAL REPORT.pdf | 12 Jun 2024 |
| CDP MapFile: CDP marked JV project.jpeg | 12 Jun 2024 |
| Commencement certificateFile: CC.pdf | 12 Jun 2024 |
| Construction permissionFile: Construction Permission.pdf | 12 Jun 2024 |
| Relinquishment clarificationFile: Relinquishmentdeed Clarification.pdf | 12 Jun 2024 |
| Sanction drawing 1File: PLAN1_11zon.pdf | 12 Jun 2024 |
| sanction drawing 2File: PLAN2_11zon.pdf | 12 Jun 2024 |
| Architect Certificate with COA No.File: ARCHITECT CERTIFICATE.jpeg | 12 Jun 2024 |
| Area Calculations by engineerFile: Engineer certified area calculations J V PARADISE.pdf | 12 Jun 2024 |
| Common area calculations by engineerFile: Engineer certified area calculations J V PARADISE.pdf | 12 Jun 2024 |
| Self attested Engineer CertificateFile: Engineer Certificate Sign n seal.pdf | 12 Jun 2024 |
| Form-6 Engineer CertificateFile: Form6CertJVParadise.pdf | 12 Jun 2024 |
| BESCOM NOC Self attested copyFile: BESCOM TEMP POWER APPROVAL.pdf | 12 Jun 2024 |
| Water NOC (grama panchayat)File: WATER NOCSelf attested.pdf | 12 Jun 2024 |
| Water clarificationFile: BWSSB Clarification.pdf | 12 Jun 2024 |
| Conversion copyFile: 1CONVERSION COPY.pdf | 12 Jun 2024 |
| Conversion fee paidFile: 2CONVERSION FEE PAID.pdf | 12 Jun 2024 |
| Conversion sketchFile: 3&4CONVERSIONSKETCH.pdf | 12 Jun 2024 |
| Commencement certificateFile: CC.pdf | 12 Jun 2024 |
| Construction permissionFile: Construction Permission.pdf | 12 Jun 2024 |
| PCB Area clarificationFile: PCB AREA Difference clarification.pdf | 12 Jun 2024 |
| Relinquishment deed clarificationFile: Relinquishmentdeed Clarification.pdf | 12 Jun 2024 |
| JV Paradise Bank Account 100%File: JV PARADISE Bank statements-100.pdf | 14 May 2024 |
| JV Paradise Bank Account 70%File: JV PARADISE Bank statements-70.pdf | 14 May 2024 |
| JV Paradise Bank Account 30%File: JV PARADISE Bank statements-30.pdf | 14 May 2024 |
| Duration of partners in partnership firm clarificationFile: FIRM DISSOLUTION clarification.pdf | 14 May 2024 |
| Chartered Accountant certificateFile: Form-1 CA Certificate.pdf | 14 May 2024 |
| Partner Ch. Janardhan Reddy Financial Statements for the F.Y. 2022-23File: CJR ITR 2023com.pdf | 14 May 2024 |
| Partner N. Venkateswarlu Financial Statements for the F.Y. 2022-23File: N Venkateswarlu 2223com.pdf | 14 May 2024 |
| Partner K.Sai Kumar Reddy Financial Statements for the F.Y. 2022-23File: Sai Reddy K ITR 2023COM.pdf | 14 May 2024 |
| Partner K.Yugandar Sagar Financial Statements for the F.Y. 2022-23File: Plbs-2022-23.pdf | 14 May 2024 |
| Partner K.Yugandar Sagar Financial Statements for the F.Y. 2022-23File: Book1-2023-24.pdf | 14 May 2024 |
| Sources of funds for Project completion certificate from CAFile: Sources of fund Certificatenew.pdf | 14 May 2024 |
| RTC latest SY.No.85.1 2023-24File: 851RTC JV PARADISE.pdf | 14 May 2024 |
| RTC latest SY.No.85.3 2023-24File: 853RTC jv paradise.pdf | 14 May 2024 |
| HISSA 85.1 JV ParadiseFile: Hissa 851.pdf | 14 May 2024 |
| HISSA 85.3 JV ParadiseFile: hissa 853.pdf | 14 May 2024 |
| EC JV ParadiseFile: 47 EC 2004 TO 2023.pdf | 14 May 2024 |
| Sy.No. 85/1& 85/3 J V Paradise Latest KhathaFile: JV Paradise Latest Khatha.pdf | 14 May 2024 |
| List of Units BHK Wise and Area calculationsFile: Engineer certified area calculations J V PARADISE.pdf | 14 May 2024 |
| Single plan layout clarificationFile: Single Plot layout clarification.pdf | 14 May 2024 |
| Certified carpet area calculationFile: Engineer certified area calculations J V PARADISE.pdf | 14 May 2024 |
| CDP Drawing the project locationFile: CDP marked JV project.jpeg | 14 May 2024 |
| Village MapFile: 40 VILLAGE MAP.pdf | 14 May 2024 |
| Commencement CertificateFile: Construction Permission.pdf | 14 May 2024 |
| KSPCB permission letterFile: PCB.pdf | 14 May 2024 |
| LicenseFile: License letter.pdf | 14 May 2024 |
| Plan sanction licenseFile: PLAN License.pdf | 14 May 2024 |
| Plan sanction 1File: PLAN1_11zon.pdf | 14 May 2024 |
| Plan sanction2File: PLAN2_11zon.pdf | 14 May 2024 |
| Area calculations by EngineerFile: Engineer certified area calculations J V PARADISE.pdf | 14 May 2024 |
| Architect Certificate of LicenseFile: Mythili Architect cert.jpeg | 14 May 2024 |
| Architect certified FormFile: ARCHITCT CERTIFICATE FORM 2 mythili new.pdf | 14 May 2024 |
| Engineer Certificate of LicenseFile: Engineer lisence.jpeg | 14 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep J V PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: J V CONSTRUCTIONS
J V CONSTRUCTIONS has 1 registration on RERA Karnataka, including J V PARADISE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if J V PARADISE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of J V PARADISE?
The registered promoter entity is J V CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29AATFJ5642E1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in J V PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at J V PARADISE?
The professionals named in the filing: Architect: G Bhanumathy; Engineer: Maddikunta Mallikarjuna Rao; Chartered Accountant: Seshachalapathi J. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in J V PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback