Home / Browse projects / Bengaluru Urban, Karnataka / ISR ASHRITA

Registration revoked Residential/Group Housing project

ISR ASHRITA

By ISR CONSTRUCTIONS PRIVATE LIMITED

RG-KA-39601 · RERA PRM/KA/RERA/1251/446/PR/180601/001828

Source: official RERA Karnataka filing

Red flags

  • Registration revoked
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jump to the 59 documents Report an error

ISR ASHRITA is a Residential/Group Housing project by ISR CONSTRUCTIONS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180601/001828 on 1 Jun 2018. Possession is promised by 24 Aug 2022. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameISR ASHRITA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/180601/001828
  • ReraGenie IDRG-KA-39601

Builder

  • NameISR CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45209AP2013PTC089980
  • Authorized SignatoryK INDRASENA REDDY
  • Board MembersR NARSIMHA REDDY, S.KRISHNA REDDY, K PRASAHANTHI
  • DirectorsRAM MOHAN REDDY G, RAMMAOHAN REDDY, K INDRASENA REDDY
  • Other registrations1 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2018First promiseNov 2020Revised toAug 2022

Key facts

Registration and timeline

  • StatusRegistration revoked
  • Registered on1 Jun 2018
  • Promised completion24 Aug 2022
  • Revised completionRevised to 24 Aug 2022 (originally 24 Nov 2020)
  • Buildings4 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---48048
B---48048
C---48048
D---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,105 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 38.66 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionNov 2020 → Aug 2021

No reason recorded in the filing

ExtensionAug 2021 → Aug 2022

Reason as filed by the promoterothers

Documents filed59

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180601/001828 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CERTIFICATE.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1-Architect Certificate for status of work as on date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5-Engineer Certificate for status of work as on date.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex3-CA-For Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2-Architect Certificate for pending work as on date.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6-Engineer Certificate for pending work as on date.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4-CA For Fund Required.pdf-
AffidavitFile: Form Ex7- Affidavit for extension-ISR Ashrita_compressed.pdf-
Latest Encumbrance CertificateFile: Latest EC Copy.pdf-
Consent letter from 2/3rd of AllotteesFile: 2-3rd consent letters from the customers_compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Environmental Certificate.pdf-
Document 2File: RERA A1 39005073838.pdf-
Document 3File: Quarterly Update Details-Q-2_18-19.pdf-
Document 4File: Quarterly Update Details-Q-3_18-19.pdf-
Document 5File: Quarterly Update Details-Q-4_18-19.pdf-
Document 6File: Quarterly Update Details-Q-1_19-20.pdf-
Document 7File: Quarterly Update Details-Q-2_19-20.pdf-
Document 8File: Quarterly Update Details-Q-3_19-20.pdf-
Document 9File: Quarterly Update Details-Q-4_19-20.pdf-
Document 10File: Quarterly Update Details-Q-1_20-21.pdf-
Document 11File: Quarterly Update Details-Q-2_20-21.pdf-
Document 12File: Quarterly Update Details-Q-3-20-21.pdf-
Document 13File: Quarterly Update Details-Q-4-20-21.pdf-
Document 14File: Quarterly Update Details-Q-1_21-22.pdf-
Document 15File: FORM-B- for Extension of Project ISR Ashrita.pdf-
I UPDATE LATER-
trace floor plan-
stlit floor plan-
SALE DEED-
SALE DEED-
trace floor plan-
trace floor plan-
allotment_letter-
EC latest-
katha-
jda-
conversion order-
Balance Sheet 2016 - 2017File: balance sheet ay-16-17.pdf-
Balance Sheet 2015 - 2016File: balance sheet -15-16.pdf-
Balance Sheet 2014 - 2015File: Bl 2014.pdf-
Audited Profit and Loss Statement 2016 - 2017File: p&L 2016.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&l 2015.pdf-
Director's Report 2016 - 2017File: direcoters report-2016.pdf-
Director's Report 2015 - 2016File: Directors report-2015.pdf-
Director's Report 2014 - 2015File: Directors report-2014.pdf-
Auditor's Report 2016 - 2017File: auditer report-2016.pdf-
Auditor's Report 2015 - 2016File: audit report-2015.pdf-
Auditor's Report 2014 - 2015File: audit report-2014.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: AK AY-16-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ISR ITR V AY -15-16 PDF.pdf-
form B-ilovepdf-
Prospectus/BrochureFile: e-brochure_ISR_Ashrita FINAL.pdf-
Advertisement Copy 1File: e-brochure_ISR_Ashrita FINAL.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_180601_001828.xlsx-
Occupancy CertificateFile: occupancy sertificate ISR ASHRITA.pdf-
Consent for operation issued by KSPCBFile: PCB.pdf-
Architect certificate for having completed the work(in format no 5)File: ARCHTECT CERTIFICATE completion.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT RERA.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is among them

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ISR ASHRITA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ISR CONSTRUCTIONS PRIVATE LIMITED

ISR CONSTRUCTIONS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including ISR INDRAPRASTHA and ISR ASHRITA. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What does it mean that ISR ASHRITA shows as registration revoked on RERA Karnataka?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the RERA Karnataka portal, and take legal advice before paying any further instalment.

What are my rights if ISR ASHRITA is delayed beyond 24 Aug 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ISR ASHRITA?

The registered promoter entity is ISR CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Its CIN U45209AP2013PTC089980 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ISR ASHRITA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in ISR ASHRITA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ISR ASHRITA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ISR ASHRITA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.