Home / Browse projects / Mumbai Suburban, Maharashtra / INTEGRATED ARCADE
INTEGRATED ARCADE
RG-MH-11965 · RERA P51800003983 · Last updated on MahaRERA portal: 2 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Completion date moved by 84 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
INTEGRATED ARCADE is a Others project by Sadgurukrupa Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003983 on 7 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 84 months from the original filing. 19 of the 21 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameINTEGRATED ARCADE
- TypeOthers
- Location
- R B Mehta Marg
- Patel Chowk
- Near Railway Station
- Ghatkopar East
- Kurla
- Mumbai Suburban
- 400077
- Pincode400077
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003983
- ReraGenie IDRG-MH-11965
Builder
- NameSadgurukrupa Developers
- Entity typePartnership
- PartnerKanti Savla
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Aug 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2019)
- Buildings1 building record
- Documents filed154 files
Current status
Figures as on 2 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INTEGRATED ARCADE | NA | 14 | 13 | 1 | 20 | 21 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
INTEGRATED ARCADE: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed27
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| INTEGRATED ARCADE | NA | Rs 5.47 cr | Rs 9.28 cr |
| - | NA | Rs 44.00 lakh | Rs 50.00 lakh |
Certifying professionals and partners10
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shri Uttam Ranadive |
| Engineer | Dayanand Salunke |
| Engineer | Prashant Patere |
| Engineer | PRASHANT ANANT PATERE |
| Chartered Accountant | Varun A. Tiwari |
| Chartered Accountant | Vijay Kumar Jain |
| Chartered Accountant | Divya P. Sabadra |
| Chartered Accountant | Ashish Shukla |
| Chartered Accountant | NEHALI DHAVAL DOSHI |
| Chartered Accountant | vinay bhushan&associates |
| Partner | Role in project |
|---|---|
| Sadgurukrupa Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReasons of the Extension as per Self declaration as attached. Consent taken put as 59 as all the 59 tenements are allotted to slum dwellers in SRA project for which Occupancy Certificate already applied with Competent Authority. There is no sale in the Sale Component. Zero is not acceptable in the column "Total Consent Taken". Hence, number put as "59"
Reason as filed by the promoter“Government by an notification has differed to implement D P 2034, as such further approval for additional floor has been delayed. However, we have not sold any free sale area to third party.”
Reason as filed by the promoterDue to COVID-19 and shortage of materials and labour we are not able to complete project on time. We request you to please grant us extension until 31/03/2026.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed154
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 154 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Arcade Dec 25.pdf | 2 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Arcade Dec 25.pdf | 2 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Arcade Dec 25.pdf | 2 Feb 2026 |
| Form 5 (FY 2024-2025)File: 251114_RERA_Form-5_SKD_24-25 (1).pdf | 15 Dec 2025 |
| Withdrawal Update Form 1File: Arcade Form 1 Sept 25.pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: Arcade Form 1 Sept 25.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Arcade (1).pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Arcade (1).pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate Integrated Arcade Sept 25.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate Integrated Arcade Sept 25.pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: Arcade Form 1 Sept 25.pdf | 28 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - Arcade (1).pdf | 28 Oct 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate Integrated Arcade Sept 25.pdf | 28 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1.pdf | 3 Oct 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 3 Oct 2025 |
| Withdrawal Update Form 3File: form 3.pdf | 3 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Arcade.pdf | 3 Oct 2025 |
| Certificates of CA (Form 3)File: Form 3 Integrated Arcade Mar 25.pdf | 5 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SKD.pdf | 5 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30_form 1 (arcade).pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30_form 1 (arcade).pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 28 Jan 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 27 Jan 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 21 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 21 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 21 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arcade.pdf | 9 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arcade.pdf | 9 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 12 Aug 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 12 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SKD - Form 5_FY 23-24.pdf | 23 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 22 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Arcade form 2A.pdf | 5 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Arcade.pdf | 14 May 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 14 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arcade.pdf | 5 Apr 2024 |
| Declaration in FORM BFile: F Form B.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: F Disclosure of inventory.pdf | 23 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 23.pdf | 5 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Dec 23.pdf | 5 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 25_form 1 (arcade).pdf | 11 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 SKD_July-Sep 2023_Signed.pdf | 8 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_SKD_July-Sep 2023.pdf | 7 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Sadguru Devel_signed.pdf | 17 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (arcade)_Signed.pdf | 13 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-FY22-23-Integrated Arcade.pdf | 18 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Integrated Arcade-Q1-FY 23-24.pdf | 17 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3-Integrated Arcade-Q1-FY 23-24.pdf | 17 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate - Integrated Arcade- June-23.pdf | 8 Jul 2023 |
| Details of encumbrancesFile: Encumbrance Arcade.pdf | 16 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - Integrated Aracde- Form 2.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: CA Certificate Integrated Arcade Mar'23 - Final Signed.pdf | 19 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate - Integrated Aracde.pdf | 18 Apr 2023 |
| CERSAI detailsFile: CERSAI ARCADE.pdf | 2 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf | 28 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf | 28 Feb 2023 |
| Certificates of CA (Form 3)File: CA form 3.pdf | 28 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A Arcade FY 21-22.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Arcade_FY21-22.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3_CA Certificate-Arcade_signed.pdf | 19 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Arcade_31 12 22.pdf | 18 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_ARCADE_EC_Mar'22 Signed.pdf | 18 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sign Form Sadgurukrupa Developers.pdf | 10 Oct 2022 |
| Certificates of CA (Form 3)File: Form 3_Q4_Arcade_FY20-21.pdf | 16 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19_form 1 (arcade)_compressed.pdf | 17 Aug 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FOrm 1 31122021.pdf | 8 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - 30062021.pdf | 16 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Arcade declaration sold unsold inventory.pdf | 14 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 RERA FY 2018-19.pdf | 3 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 RERA FY 2019-20.pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Form 2A dt 31032020 sign 30062021.pdf | 2 Jul 2021 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate 01072021 signed.pdf | 1 Jul 2021 |
| Form 2AFile: Engineer Certificate Form 2A dt 31122020 sign 30062021.pdf | 1 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Form 2A dt 31122020 sign 30062021.pdf | 1 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Diclosure of Sold_Booked Inventory 01072021 signed.pdf | 1 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect Certificate - Arcade.pdf | 22 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer Certificate - Arcade.pdf | 22 Jun 2021 |
| Certificates of CA (Form 3)File: Final Form 3 Arcade Jan 2020 to December 2020 v1.pdf | 22 Jun 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 154 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep INTEGRATED ARCADE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Patel Chowk, Near Railway Station, Ghatkopar East6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 341 registered projects within 2 km.
Mahindra Rainforest Phase 1
Anthurium Developers Limited
Mahindra Rainforest Phase 2
Anthurium Developers Limited
CRYSTAL PRIME MERIDIAN
ARYAMAAN DEVELOPERS PRIVATE LIMITED
AARADHYA ONEPARK
MICL CREATORS LLP
CENTRONA ZEN-A
ELEVATED AVENUE REALTY LLP
CENTRONA ZEN-B
ELEVATED AVENUE REALTY LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Sadgurukrupa Developers
Sadgurukrupa Developers has 1 registration on MahaRERA, including INTEGRATED ARCADE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that INTEGRATED ARCADE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if INTEGRATED ARCADE is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of INTEGRATED ARCADE?
The registered promoter entity is Sadgurukrupa Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in INTEGRATED ARCADE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for INTEGRATED ARCADE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at INTEGRATED ARCADE?
The professionals named in the filing: Architect: Shri Uttam Ranadive; Engineer: Dayanand Salunke; Engineer: Prashant Patere; Engineer: PRASHANT ANANT PATERE; Chartered Accountant: Varun A. Tiwari; Chartered Accountant: Vijay Kumar Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in INTEGRATED ARCADE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback