Home / Browse projects / Mumbai Suburban, Maharashtra / INTEGRATED ARCADE

Registration lapsed No litigation declared Others project

INTEGRATED ARCADE

By Sadgurukrupa Developers

RG-MH-11965 · RERA P51800003983 · Last updated on MahaRERA portal: 2 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 84 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
2 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 154 documents Report an error

INTEGRATED ARCADE is a Others project by Sadgurukrupa Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003983 on 7 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 84 months from the original filing. 19 of the 21 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameINTEGRATED ARCADE
  • TypeOthers
  • Location
    • R B Mehta Marg
    • Patel Chowk
    • Near Railway Station
    • Ghatkopar East
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003983
  • ReraGenie IDRG-MH-11965

Builder

  • NameSadgurukrupa Developers
  • Entity typePartnership
  • PartnerKanti Savla

Key dates

7 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2017
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed154 files

Current status

90%19 of 21 units booked
165.5%Work done, per cost certificate

Figures as on 2 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INTEGRATED ARCADENA141312021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

INTEGRATED ARCADE: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 2 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area789 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI3805.0
Proposed, not sanctioned2,696 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKarma Sankalp Building Road No 7 Rajawadi Opp Somaiya College Mumbai 400077
Estimated costRs 5.91 cr
Cost incurredRs 9.78 cr
Work done165.48%
BuildingWingEstimatedIncurred
INTEGRATED ARCADENARs 5.47 crRs 9.28 cr
-NARs 44.00 lakhRs 50.00 lakh

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShri Uttam Ranadive
EngineerDayanand Salunke
EngineerPrashant Patere
EngineerPRASHANT ANANT PATERE
Chartered AccountantVarun A. Tiwari
Chartered AccountantVijay Kumar Jain
Chartered AccountantDivya P. Sabadra
Chartered AccountantAshish Shukla
Chartered AccountantNEHALI DHAVAL DOSHI
Chartered Accountantvinay bhushan&associates
PartnerRole in project
Sadgurukrupa Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010051Mar 2019 → Mar 2023

Reason as filed by the promoterReasons of the Extension as per Self declaration as attached. Consent taken put as 59 as all the 59 tenements are allotted to slum dwellers in SRA project for which Occupancy Certificate already applied with Competent Authority. There is no sale in the Sale Component. Zero is not acceptable in the column "Total Consent Taken". Hence, number put as "59"

EXT51800000663Mar 2019 → Mar 2020

Reason as filed by the promoter“Government by an notification has differed to implement D P 2034, as such further approval for additional floor has been delayed. However, we have not sold any free sale area to third party.”

EXT51800019161Mar 2019 → Mar 2026

Reason as filed by the promoterDue to COVID-19 and shortage of materials and labour we are not able to complete project on time. We request you to please grant us extension until 31/03/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed154

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 154 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Arcade Dec 25.pdf2 Feb 2026
Withdrawal Update Form 2File: Form 2 Arcade Dec 25.pdf2 Feb 2026
Withdrawal Update Form 3File: Form 3 Arcade Dec 25.pdf2 Feb 2026
Form 5 (FY 2024-2025)File: 251114_RERA_Form-5_SKD_24-25 (1).pdf15 Dec 2025
Withdrawal Update Form 1File: Arcade Form 1 Sept 25.pdf6 Nov 2025
Withdrawal Update Form 1File: Arcade Form 1 Sept 25.pdf6 Nov 2025
Withdrawal Update Form 2File: Form 2 - Arcade (1).pdf6 Nov 2025
Withdrawal Update Form 2File: Form 2 - Arcade (1).pdf6 Nov 2025
Withdrawal Update Form 3File: Signed CA Certificate Integrated Arcade Sept 25.pdf6 Nov 2025
Withdrawal Update Form 3File: Signed CA Certificate Integrated Arcade Sept 25.pdf6 Nov 2025
Withdrawal Update Form 1File: Arcade Form 1 Sept 25.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 - Arcade (1).pdf28 Oct 2025
Withdrawal Update Form 3File: Signed CA Certificate Integrated Arcade Sept 25.pdf28 Oct 2025
Withdrawal Update Form 1File: FORM 1.pdf3 Oct 2025
Withdrawal Update Form 2File: form 2.pdf3 Oct 2025
Withdrawal Update Form 3File: form 3.pdf3 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A - Arcade.pdf3 Oct 2025
Certificates of CA (Form 3)File: Form 3 Integrated Arcade Mar 25.pdf5 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SKD.pdf5 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30_form 1 (arcade).pdf29 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30_form 1 (arcade).pdf29 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf28 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf27 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf21 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf21 Nov 2024
Certificates of CA (Form 3)File: form 3.pdf21 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arcade.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arcade.pdf9 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf12 Aug 2024
Certificates of CA (Form 3)File: form 3.pdf12 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SKD - Form 5_FY 23-24.pdf23 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Arcade form 2A.pdf5 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Arcade.pdf14 May 2024
Certificates of CA (Form 3)File: form 3.pdf14 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arcade.pdf5 Apr 2024
Declaration in FORM BFile: F Form B.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: F Disclosure of inventory.pdf23 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 23.pdf5 Feb 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate Dec 23.pdf5 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 25_form 1 (arcade).pdf11 Jan 2024
Certificates of CA (Form 3)File: Form 3 SKD_July-Sep 2023_Signed.pdf8 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_SKD_July-Sep 2023.pdf7 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Sadguru Devel_signed.pdf17 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (arcade)_Signed.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-FY22-23-Integrated Arcade.pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Integrated Arcade-Q1-FY 23-24.pdf17 Aug 2023
Certificates of CA (Form 3)File: Form 3-Integrated Arcade-Q1-FY 23-24.pdf17 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate - Integrated Arcade- June-23.pdf8 Jul 2023
Details of encumbrancesFile: Encumbrance Arcade.pdf16 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - Integrated Aracde- Form 2.pdf19 May 2023
Certificates of CA (Form 3)File: CA Certificate Integrated Arcade Mar'23 - Final Signed.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate - Integrated Aracde.pdf18 Apr 2023
CERSAI detailsFile: CERSAI ARCADE.pdf2 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf28 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf28 Feb 2023
Certificates of CA (Form 3)File: CA form 3.pdf28 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A Arcade FY 21-22.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Arcade_FY21-22.pdf25 Jan 2023
Certificates of CA (Form 3)File: Form 3_CA Certificate-Arcade_signed.pdf19 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Arcade_31 12 22.pdf18 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_ARCADE_EC_Mar'22 Signed.pdf18 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sign Form Sadgurukrupa Developers.pdf10 Oct 2022
Certificates of CA (Form 3)File: Form 3_Q4_Arcade_FY20-21.pdf16 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19_form 1 (arcade)_compressed.pdf17 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FOrm 1 31122021.pdf8 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - 30062021.pdf16 Aug 2021
Disclosure of sold/ booked inventoryFile: Arcade declaration sold unsold inventory.pdf14 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 RERA FY 2018-19.pdf3 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 RERA FY 2019-20.pdf3 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Form 2A dt 31032020 sign 30062021.pdf2 Jul 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate 01072021 signed.pdf1 Jul 2021
Form 2AFile: Engineer Certificate Form 2A dt 31122020 sign 30062021.pdf1 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Form 2A dt 31122020 sign 30062021.pdf1 Jul 2021
Disclosure of sold/ booked inventoryFile: Diclosure of Sold_Booked Inventory 01072021 signed.pdf1 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect Certificate - Arcade.pdf22 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer Certificate - Arcade.pdf22 Jun 2021
Certificates of CA (Form 3)File: Final Form 3 Arcade Jan 2020 to December 2020 v1.pdf22 Jun 2021

How this compares with Mumbai Suburban

90%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 84 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep INTEGRATED ARCADE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Patel Chowk, Near Railway Station, Ghatkopar East6,700+ in Mumbai Suburban

2 kmINTEGRATED ARCADECompleted 131Lapsed / revoked 88Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 341 registered projects within 2 km.

Builder: Sadgurukrupa Developers

Sadgurukrupa Developers has 1 registration on MahaRERA, including INTEGRATED ARCADE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that INTEGRATED ARCADE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if INTEGRATED ARCADE is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INTEGRATED ARCADE?

The registered promoter entity is Sadgurukrupa Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INTEGRATED ARCADE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INTEGRATED ARCADE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INTEGRATED ARCADE?

The professionals named in the filing: Architect: Shri Uttam Ranadive; Engineer: Dayanand Salunke; Engineer: Prashant Patere; Engineer: PRASHANT ANANT PATERE; Chartered Accountant: Varun A. Tiwari; Chartered Accountant: Vijay Kumar Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INTEGRATED ARCADE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INTEGRATED ARCADE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INTEGRATED ARCADE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.