IMPERIAL ATRIA TOWER 2
By MERIDIAN
RG-MH-50750 · RERA P52100016407 · Last updated on MahaRERA portal: 28 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 50 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
IMPERIAL ATRIA TOWER 2 is a Residential / Group Housing project by MERIDIAN in Pune, Maharashtra, registered with MahaRERA as P52100016407 on 10 May 2018. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 50 months from the original filing. 23 of the 29 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameIMPERIAL ATRIA TOWER 2
- TypeResidential / Group Housing
- Location
- S NO 37 H NO 1 PART
- BANER
- Haveli
- Pune
- 411008
- Pincode411008
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100016407
- ReraGenie IDRG-MH-50750
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 May 2018
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Apr 2022)
- Buildings1 building record
- Documents filed158 files
Current status
Figures as on 28 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| IMPERIAL ATRIA TOWER 2 | NA | 23 | 20 | 29 | 0 | 29 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 83%.
IMPERIAL ATRIA TOWER 2: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 74% |
| Sanitary Fittings within the flats / premises | 23% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 83% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 68% |
Progress on shared amenities15
As on 28 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SUDARSHAN BAFNA | Shrirampur (M Cl) | Ahmednagar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| IMPERIAL ATRIA TOWER 2 | NA | Rs 31.44 cr | Rs 31.44 cr |
| - | NA | Rs 3.11 cr | Rs 3.11 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | vishal deshpande |
| Architect | Jagadish Deshpande |
| Architect | GA DESIGN |
| Engineer | Strudcom Consultants Pvt Ltd JAYANT INAMDAR NIKHIL INAMDAR |
| Chartered Accountant | Supriya Mundada |
| Partner | Role in project |
|---|---|
| MERIDIAN | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe impact of Covid-19 on the real estate market development project in City of Pune had drastically changed thereafter a) due to the threat to the lives of residents and the impossibility of free movement of the residents, b) since Pune being IT & ITes Centric City, work from home mode introduced post onset of COVID-19 continued for most of the said Companies till September, 2022 in the IT Hub of Pune Viz Hindjewadi, Wakad, Baner, Aundh, Pashan etc. which are in close vicinity of the project, coupled with the continuous increase in interest rates by the RBI from time to time commencing May, 2
Reason as filed by the promoterThe development of the said Project commenced and continued in accordance with the timelines committed at the time of its registration with MAHARERA (i.e., April 30, 2021), except for interruptions due to force majeure events including COVID-19. In view of the pandemic, MAHARERA had granted two extensions, followed by a further extension dated February 8, 2023, valid until June 30, 2025. Construction progressed thereafter based on projected sales and internal accruals; however, due to lower-than-expected sales-especially impacted by the pandemic’s effect on the IT sector in Hinjewadi and the d
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12603601 | Sunil Multanmal Palrecha | MERIDIAN | 11/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 May 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 May 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Nov 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed158
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 158 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form 1.pdf | 28 Jul 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 28 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Jul 2026 |
| Form 2A (FY 2025-2026)File: form 2A.pdf | 28 Jul 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 16 Jul 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 16 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 16 Jul 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: form1.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 30 Oct 2025 |
| Withdrawal Update Form 1File: form 1.pdf | 30 Oct 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 30 Oct 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 30 Oct 2025 |
| Withdrawal Update Form 3File: form 3.pdf | 30 Oct 2025 |
| Withdrawal Update Form 3File: form 3.pdf | 30 Oct 2025 |
| Commencement certificateFile: CC 26092023.pdf | 18 Jul 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A IAT2.pdf | 18 Jul 2025 |
| OtherFile: letter to rera_signed.pdf | 12 Jun 2025 |
| OtherFile: letter_signed new.pdf | 12 Jun 2025 |
| Certificates of CA (Form 3)File: FORM 3 IAT2.pdf | 8 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IAT2.pdf | 8 May 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD IAT2.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A IAT2.pdf | 8 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IAT2.pdf | 21 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 MERIDIAN.pdf | 13 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Meridian.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold meridian.pdf | 2 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 MERIDIAN.pdf | 2 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 Imperial Atria.pdf | 24 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3 Imperial atria T2.pdf | 24 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold imperial atria T2.pdf | 23 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Imperial Atria.pdf | 22 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3 Imperial Atria.pdf | 22 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Imperial Atria.pdf | 22 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 15 May 2024 |
| Disclosure of sold/ booked inventoryFile: sold inventory.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 15 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 22 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a.pdf | 22 Apr 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 17 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sold inventory.pdf | 16 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 12 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 12 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 IA T2.pdf | 20 Nov 2023 |
| Building plan approvalFile: Scan281901.pdf | 2 Nov 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Scan281901.pdf | 2 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 148721.pdf | 2 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 26092023.pdf | 2 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: sold inventory.pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: form 3 IA T2.pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 IA T2.pdf | 19 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 16 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 13 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 13 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC0367 18052022.pdf | 13 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 20230805165132.pdf | 13 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC0367 18052022.pdf | 13 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 20230805165132.pdf | 13 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold inventory.pdf | 28 Jul 2023 |
| Certificates of CA (Form 3)File: form 3.pdf | 28 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 27 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 27 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (March 2023).pdf | 19 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (March 2023).pdf | 18 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 12 Apr 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 12 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 6 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2a.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: booked inventory.pdf | 6 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: may 2021 form 1.pdf | 21 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 22 form 1.pdf | 21 Jan 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| IMPERIAL ATRIA TOWER 1 | BANER PUNE 411 008 | 78 | Completed | Jul 2016 | Late, Feb 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 158 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep IMPERIAL ATRIA TOWER 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BANER13,700+ in Pune
Filed coordinates, straight-line distance. 328 registered projects within 2 km.
LIVIENCE ALEENTA
LIVIENCE LIFESPACE PRIVATE LIMITED
VRAJA VILAS TOWER
SUPRA HOME PRIVATE LIMITED
AMAR LANDMARK
PRITAM CONSTRUCTIONS PVT LTD
ARENA CONSTRUCTIONS
ARENA CONSTRUCTIONS
IMPERIAL COMMERCIAL SPACES
MERIDIAN
Nilaya
Four Seasons Holdings
Builder: MERIDIAN
MERIDIAN has 2 registrations on MahaRERA, including IMPERIAL COMMERCIAL SPACES and IMPERIAL ATRIA TOWER 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that IMPERIAL ATRIA TOWER 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if IMPERIAL ATRIA TOWER 2 is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of IMPERIAL ATRIA TOWER 2?
The registered promoter entity is MERIDIAN, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in IMPERIAL ATRIA TOWER 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against IMPERIAL ATRIA TOWER 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for IMPERIAL ATRIA TOWER 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at IMPERIAL ATRIA TOWER 2?
The professionals named in the filing: Architect: vishal deshpande; Architect: Jagadish Deshpande; Architect: GA DESIGN; Engineer: Strudcom Consultants Pvt Ltd JAYANT INAMDAR NIKHIL INAMDAR; Chartered Accountant: Supriya Mundada. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in IMPERIAL ATRIA TOWER 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback