Home / Browse projects / Bengaluru Urban, Karnataka / Iconica Nitesh Knightsbridge

Registration approved No litigation declared Residential/Group Housing project

Iconica Nitesh Knightsbridge

By GARDENCITY REALTY PVT LTD

RG-KA-91649 · RERA TOR/PRM/KA/RERA/1251/309/PR/210807/000942 · Last updated on RERA Karnataka portal: 30 Mar 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 60 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Dec 2025Possession promisedmoved 60 months from the original
5 of 18Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 80%
9 of 11Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 100 documents Report an error

Iconica Nitesh Knightsbridge is a Residential/Group Housing project by GARDENCITY REALTY PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as TOR/PRM/KA/RERA/1251/309/PR/210807/000942 on 7 Aug 2021. Possession is promised by 31 Dec 2025. The completion date has moved by 60 months from the original filing. 2 of the 11 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameIconica Nitesh Knightsbridge
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.TOR/PRM/KA/RERA/1251/309/PR/210807/000942
  • ReraGenie IDRG-KA-91649

Builder

  • NameGARDENCITY REALTY PVT LTD
  • Entity typeCompany
  • CINU70200KA2004PTC033885
  • Authorized SignatoryKOTTU MURALIKRISHNA
  • OthersJyotirmoy Tripathi
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2021First promiseDec 2020Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Aug 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2020)
  • Buildings1 building record
  • Documents filed100 files

Current status

18%2 of 11 units booked
43.0%Of the estimated cost spent so far

Figures as on 30 Mar 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-1---11011

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 30 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 80%.

Building: 45% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)80%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc42%
Plastering inside , outside & Ceiling42%
Joinery: Doors, Windows, Ventilators etc42%
Basic work of Water supply, Sanitary and Electrification35%
Dadoing, Skirting, Flooring, Tiles work (All types)30%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network8%
Weather Proof work(tile,concrete)30%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings5%

Progress on shared amenities41

As on 30 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes30%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes35%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes20%
ParksNoNot applicable
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionYes0%
StaircasesYes40%
LiftsYes40%
Staircases and Lift lobbies, corridor,lobbies, corridorYes40%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes90%
TerraceYes35%
Outer WallYes0%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,285 sq m
Named landowners2
LandownerVillageDistrict
Shantesh S Gureddi--
Jyothi S Gureddi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 40.50 cr
Cost incurredRs 17.43 cr
Spent of the estimate43.03%
Cost lineEstimatedIncurred
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 18.00 crRs 4.05 cr
Estimated Cost of Construction as certified by EngineerRs 17.40 crRs 13.38 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 3.00 cr-
On-site expenditure-Salaries of workersRs 1.00 cr-
On-site expenditure-Site OverheadRs 1.00 cr-
On-site expenditure-Consultants FeesRs 10.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG Murugan
EngineerHP Yogesh

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/309/PR/220908/000942Dec 2020 → Dec 2021

Reason as filed by the promoterothers; Company in Loss

ExtensionDec 2021 → Dec 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00421/2026-GARDENCITY REALTY PVT LTD21/04/2026

Documents filed100

As listed on the registration, under the names the promoter filed them with; the newest 80 of 100 are shown. The files themselves are available at source: search the registration number TOR/PRM/KA/RERA/1251/309/PR/210807/000942 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-04.pdf30 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: IKB -form 5.pdf30 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: IKB -form 6.pdf30 Mar 2026
Q3 2025-26 Water supply and sewage board30 Mar 2026
Q3 2025-26 KPTCL- BESCOM30 Mar 2026
Q3 2025-26 Fire and Safety30 Mar 2026
Q3 2025-26 Airport Authority of India30 Mar 2026
Q3 2025-26 BSNL/Telecommunication Department30 Mar 2026
EX-7File: Form Ex-7 INKB.pdf21 Mar 2022
Registration CertificateFile: Knightsbridge RERA Regn-TORPRMKARERA1251309PR210807000942.pdf21 Mar 2022
Proforma of AgreementFile: Gundami Shankar - Sale Agreement.pdf21 Mar 2022
NOC-AAIFile: NOC - AAI.pdf21 Mar 2022
NOC-BWSSBFile: NOC - BWSSB.pdf21 Mar 2022
NOC-KSPCBFile: KSPCB.pdf21 Mar 2022
NOC-BESCOMFile: NOC - BESCOM.pdf21 Mar 2022
NOC-FireFile: NOC - Fire.pdf21 Mar 2022
NOC-SEIAAFile: SEIAA.pdf21 Mar 2022
Building PlanFile: Building plan.pdf21 Mar 2022
Revised JDAFile: JDA- Shantesh Gureddi & Anotr to GRPL-Knightsbridge-compressed.pdf21 Mar 2022
DeclarationFile: Declaration Reason for Delay.pdf21 Mar 2022
Project Bank Account as per RERA CircularFile: RERA Designate Project Bank Account-KB 70% ESC.pdf19 Jun 2021
Previous Project RERA Registration CertificateFile: TORPRMKARERA1251309PR210528001913.pdf19 Jun 2021
DeclarationFile: Knightsbridge Declaration.pdf26 May 2021
Challan for the payment of feesFile: Challan Knightsbridge.pdf26 May 2021
Audit report wherein UDIN number is mentioned on the last pageFile: GRPL AuditReport 201920.pdf26 May 2021
Affidavit from Outgoing PromoterFile: Affidavit from Outgoing Promoter-Knights Bridge.pdf15 Apr 2021
Affidavit from Incoming PromoterFile: Affidavit from Incoming Promoter-Knights Bridge.pdf15 Apr 2021
Joint Affidavit and Declaration of Land Owner and PromoterFile: Joint Affidavit and Declaration-Knights Bridge.pdf15 Apr 2021
Khata CertificateFile: Amalgamated Khata Certificate and Extract-compressed.pdf15 Apr 2021
Attested PANFile: Attested PAN Copy of Gardencity.pdf15 Apr 2021
Directors Report 201920File: Directors Report FY 201920-compressed.pdf15 Apr 2021
GPA from Land Owners to PromoterFile: GPA- Shantesh Gureddi & Anotr to GRPL-Knightsbridge-compressed.pdf15 Apr 2021
Audit Report 201920File: GRPL AuditReport 201920-compressed.pdf15 Apr 2021
Financials 201920File: GRPL FinancialsFY 201920-compressed.pdf15 Apr 2021
ITR 201920File: GRPLITR6ACKFY201920.pdf15 Apr 2021
JDA from Land Owners to PromoterFile: JDA- Shantesh Gureddi & Anotr to GRPL-Knightsbridge-compressed.pdf15 Apr 2021
RERA Fee Paid ChallanFile: RERA Fee Paid Challan.pdf15 Apr 2021
Sale Deed of Land OwnerFile: Sale Deed dated 11.11.2003-compressed.pdf15 Apr 2021
Sale Deed of Land Owner 2File: Sale Deed dated 24.5.2010-compressed.pdf15 Apr 2021
EC from 01.04.2004 to 2021File: EC from 01.04.2004 to 20.03.2021-Knights Bridge.pdf15 Apr 2021
RERA order for Transfer of ProjectFile: Final Order RERA-Transfer of Project.pdf15 Apr 2021
Declaration of PromoterFile: Declaration.pdf15 Apr 2021
CertificateFile: GRPLIncorporation.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Architect's Certificate Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer's Certificate Ex-5.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex3-CA Funds Utilization Certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect's Certificate Ex2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer's Certificate Ex6.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4-CA Certificate for funds required.pdf-
AffidavitFile: Form B Affidavit-Project Extention-KB.pdf-
Latest Encumbrance CertificateFile: E C Knights Bridge.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter-G Shankar.pdf-
Details Of Sold/ Un-sold UnitsFile: Deatils of sold & unsold units.pdf-
Document 1File: Consent of Customers.pdf-
Document 2File: JDA- Shantesh Gureddi & Anotr to GRPL-Knightsbridge-compressed.pdf-
Document 3File: GPA- Shantesh Gureddi & Anotr to GRPL-Knightsbridge-compressed.pdf-
NKB Sanction letter-
Building plan-
Site plan-
JDA & Location map-
Section plan-
RERA - NKB - Services-
KnightsbridgeLetterofallotmentformat-
KnightsbridgeProspectus-
Specs_R1-RERA-NKB-
NOCAAI-
Form B affidavit for RERA Reg-Knights Bridge Project_compressed-
Form B affidavit for RERA Reg-Knights Bridge Project_compressed-
JDAKnightsbridge-
Legal opinion- Lokesh-
NA - Conv, MR, RTC-
NA - Conv, MR, RTC-
Sale Deed between Prashanth in favor of Shantesh S Gureddi and Jyothi S Gureddi compressed-
NOC - Fire-
NOC - AAI-
NOC - BESCOM-
NOC - BWSSB-
KSPCB-
SEIAA-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Iconica Nitesh Park Avenue-OngoingJan 2023Not delivered

How this compares with Bengaluru Urban

18%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 60 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Iconica Nitesh Knightsbridge on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmIconica Nitesh KnightsbrOther 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: GARDENCITY REALTY PVT LTD

GARDENCITY REALTY PVT LTD has 1 registration on RERA Karnataka, including Iconica Nitesh Knightsbridge. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Iconica Nitesh Knightsbridge is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Iconica Nitesh Knightsbridge?

The registered promoter entity is GARDENCITY REALTY PVT LTD, a company as per the filing. Its CIN U70200KA2004PTC033885 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Iconica Nitesh Knightsbridge?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Iconica Nitesh Knightsbridge?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Iconica Nitesh Knightsbridge?

The professionals named in the filing: Architect: G Murugan; Engineer: HP Yogesh. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Iconica Nitesh Knightsbridge?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Iconica Nitesh Knightsbridge. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Iconica Nitesh Knightsbridge to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.