Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
ICONEST4 is a Residential/Group Housing project by Icon Infra Shelters India Pvt. Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/200117/003186 on 17 Jan 2020. Possession is promised by 30 Apr 2023. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameICONEST4
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/308/PR/200117/003186
- ReraGenie IDRG-KA-35498
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on17 Jan 2020
- Promised completion30 Apr 2023
- Revised completionRevised to 30 Apr 2023 (originally 30 Jul 2022)
- Buildings1 building record
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | 60 | 0 | 60 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 30 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 30 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed68
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/200117/003186 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| lONGITUDE AND LATITUDE DETAILSFile: Longitude & Lattitude.pdf | 30 Dec 2019 |
| ARCHITECT AND STRUCTURAL ENGINEER DETAILSFile: Architect & Structural Engineer details.pdf | 30 Dec 2019 |
| CONRACTOR DETAILSFile: Contractor Details.pdf | 30 Dec 2019 |
| Longitude & LatitudeFile: Longitude & Lattitude.pdf | 24 Dec 2019 |
| Associated Vendor DetailsFile: Associated Vendor Details.pdf | 24 Dec 2019 |
| AFFIDAVIT CUM DECLRATIONFile: Affidavit cum declaration.pdf | 20 Dec 2019 |
| AFFIDAVITFile: Affidavit.pdf | 20 Dec 2019 |
| Water NOCFile: Water letter.pdf | 20 Dec 2019 |
| Affidavit cum DeclarationFile: Affidavit cum declaration.pdf | 16 Dec 2019 |
| ECFile: EC.pdf | 16 Dec 2019 |
| Amalgamation planFile: 1 & 64-2 - Amalga - khata.pdf | 16 Dec 2019 |
| AffadavitFile: Affidavit.pdf | 16 Dec 2019 |
| Company ResolutionFile: Company Resolution.pdf | 16 Dec 2019 |
| Conversion of rectified ordersFile: Conversion of Rectified Orders.pdf | 16 Dec 2019 |
| Conversion orderFile: Conversion Order Krishnappa.pdf | 16 Dec 2019 |
| Final Release orderFile: Final release order.pdf | 16 Dec 2019 |
| Initial Release orderFile: Initial Release order.pdf | 16 Dec 2019 |
| KhataFile: Khata - Form 9.pdf | 16 Dec 2019 |
| Plan - AmalgamationFile: Plan - Amalgamated.PDF | 16 Dec 2019 |
| Sale Deed Pot 1File: Sale Deed - 1892-2013-14.pdf | 16 Dec 2019 |
| Sale Deed KrishnappaFile: Sale Deed - Krishnappa.pdf | 16 Dec 2019 |
| Layout PlanFile: Sancturay original layout plan.pdf | 16 Dec 2019 |
| Second Release orderFile: Second Release Order.pdf | 16 Dec 2019 |
| Water LetterFile: Water letter.pdf | 16 Dec 2019 |
| Khata Form 11File: Khata - Form 11.pdf | 16 Dec 2019 |
| CertificateFile: Infra Incorporation Certificate.pdf | - |
| commencment | - |
| Floor Pan | - |
| site pan | - |
| Sale Deed convert final | - |
| elevation | - |
| site pan | - |
| Specification iconest 4 | - |
| EC - 2004-15 | - |
| E-Khata - Form 9 | - |
| Sale Deed final - Krishnappa (2) | - |
| RTC - 2000-2018 | - |
| Conversion Order final | - |
| CFE-Icon Infra | - |
| site pan | - |
| elevation | - |
| Conversion Order final | - |
| Balance Sheet 2018 - 2019File: BS.pdf | - |
| Balance Sheet 2017 - 2018File: BS.pdf | - |
| Balance Sheet 2016 - 2017File: BS.jpg | - |
| Audited Profit and Loss Statement 2018 - 2019File: P&L.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P&L.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&L.jpg | - |
| Director's Report 2018 - 2019File: Director Report.pdf | - |
| Director's Report 2017 - 2018File: Director Report.pdf | - |
| Director's Report 2016 - 2017File: Icon Infra Board's Report FY 2015-16.pdf | - |
| Cash Flow Statement 2018 - 2019File: C&F.pdf | - |
| Cash Flow Statement 2017 - 2018File: CF.pdf | - |
| Auditor's Report 2018 - 2019File: Audit Report.pdf | - |
| Auditor's Report 2017 - 2018File: Audit Report.pdf | - |
| Auditor's Report 2016 - 2017File: audit report .pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: ITR.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR.jpg | - |
| Prospectus/BrochureFile: Brochure - Iconest 4.pdf | - |
| Advertisement Copy 1File: Brochure - Iconest 4.pdf | - |
| Tower Excel SheetFile: IN4 unit detais of PRM_KA_RERA_1251_308_PR_200117_003186.xlsx | - |
| Loan raised documentFile: Sanction letter - Bajaj.pdf | - |
| Stability CertificateFile: Stability Certificate.pdf | - |
| Occupancy CertificateFile: Project completion certificate Iconest-4.pdf | - |
| Consent for operation issued by KSPCBFile: Icon CFO.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: I4 BESCOM service certificate.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: affidavit cum declaration.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ICONEST4 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Icon Infra Shelters India Pvt. Ltd
ICON INFRA SHELTERS INDIA PVT. LTD. has 4 registrations on RERA Karnataka, including Icon Sanctuary and ICONEST4. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ICONEST4 is delayed beyond 30 Apr 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ICONEST4?
The registered promoter entity is Icon Infra Shelters India Pvt. Ltd, a company as per the filing. Its CIN U45202KA2012PTC064358 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ICONEST4?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in ICONEST4?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback