ICON MICASA
By ICON INFRA SHELTERS INDIA PRIVATE LIMITED
RG-KA-59490 · RERA PRM/KA/RERA/1251/310/PR/110422/004823 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
ICON MICASA is a Residential/Group Housing project by ICON INFRA SHELTERS INDIA PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/110422/004823 on 11 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 168 of the 170 units on this registration are recorded sold or booked, and 7 of 17 construction stages are filed complete.
At a glance
Project
- NameICON MICASA
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560105
- Pincode560105
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/110422/004823
- ReraGenie IDRG-KA-59490
Builder
- NameICON INFRA SHELTERS INDIA PRIVATE LIMITED
- Entity typeCompany
- CINU45202KA2012PTC064358
- GSTIN29AACCI9710Q1ZW
- Authorized SignatoryMR.RAJASEKHAR GOWRINENI
- Managing DirectorMR.RAJASEKHAR GOWRINENI
- DirectorsDR.P.MANMOHAN REDDY, DEVIREDDY CHAITANYA KUMAR REDDY
- Project HeadDR.P.MANMOHAN REDDY
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on11 Apr 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
- Buildings1 building record
- Documents filed145 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ICONEST 7 | - | - | - | 170 | 0 | 170 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 17 construction stages are filed complete. The stage furthest along is Joinery: Doors, at 95%.
Building: 93% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 95% |
| Basic work of Water supply, Sanitary and Electrification | 90% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 95% |
| Railing and Grill fixing | 90% |
| Electrification, Water supply and Sanitary Finishing | 85% |
| Painting | 80% |
| Fire prevention and fire fighting fitting and fixture with network | 85% |
| Weather Proof work(tile,concrete) | 90% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 95% |
| Internal and External work including landscapes as per sanctioned drawings | 75% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 80% |
| Sewage and Drainage System | Yes | 80% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 50% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Solid waste management and disposal | Yes | 60% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 50% |
| Electricity supply transformer and substation | Yes | 55% |
| Storm water drains | Yes | 45% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 50% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 50% |
| Club House | No | Not applicable |
| Community Hall | Yes | 80% |
| Outdoor Sports facility | Yes | 50% |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 75% |
| Gym | Yes | 50% |
| Parks | No | Not applicable |
| Power Backup | Yes | 60% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 60% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 95% |
| Lifts | Yes | 90% |
| Corridor/Lobbies | Yes | 90% |
| Fire escapes | Yes | 90% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 75% |
| Basement | No | Not applicable |
| Terrace | Yes | 85% |
| Outer Wall | Yes | 75% |
| Open parking areas | Yes | 70% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Doddakrishna Reddy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 63.55 cr | Rs 7.37 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MIDHULA J |
| Engineer | Munish Sharma |
| Chartered Accountant | Raghavendra M |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed145
As listed on the registration, under the names the promoter filed them with; the newest 80 of 145 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/110422/004823 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Icon_Micasa_Q2_FY2026-27 Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate_Icon Micasa Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate_Icon Micasa Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Certificate_Icon Micasa Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate_Icon Micasa Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-5 Engineer Certificate_Icon Micasa Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Icon Micasa_ Q4_2025-26.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architecture Certificates ICON MICASA.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Enginees Certificate-ICON MICASA.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 15 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Icon Micasa_ Q3_2025-26_Signed.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: From-5, Architect (QU) Micasa.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: From-6, Engineer (QU) Micasa.pdf | 15 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 15 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 15 Jan 2026 |
| Q3 2025-26 Fire and Safety | 15 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 15 Jan 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 15 Jan 2026 |
| Annual Audit reportFile: RERA - Micasa Annual return 23-24 Signed (1).pdf | 28 Nov 2024 |
| Affidavit ExFile: Affidavit - Form EX7.pdf | 28 Nov 2024 |
| Commencement CertificateFile: Commencement Certificate.pdf | 28 Nov 2024 |
| Icon Sanctuary RERA Registration CertificateFile: RERA certificate - Sanctuary.pdf | 18 Mar 2022 |
| First Site Release OrderFile: Initial Release order.pdf | 18 Mar 2022 |
| Second Site Release OrderFile: Second Release Order.pdf | 18 Mar 2022 |
| Final Release orderFile: Final release order.pdf | 18 Mar 2022 |
| Explanation statement - Icon Sanctuary, Iconest 4, Iconest 5 projectFile: Iconest 4 & 5 - Explanation for Excess withdrawals of money.pdf | 18 Mar 2022 |
| Guideline ValueFile: ICONEST-4 - Guideline value.pdf | 18 Mar 2022 |
| Audit Profit and loss accountFile: IIS P&L.PDF | 13 Jan 2022 |
| Balance SheetFile: IIS BS.PDF | 13 Jan 2022 |
| Partition deedFile: Partition deed.pdf | 13 Jan 2022 |
| Common area allotted to AssociationFile: ICONEST 7 - Details of Common area allotted to Association.pdf | 13 Jan 2022 |
| Provision for STPFile: STP PLAN.pdf | 13 Jan 2022 |
| STP ReportFile: STP Report.pdf | 13 Jan 2022 |
| Authorized signed copy of project specificationFile: Iconest - 7 - Specifications.pdf | 13 Jan 2022 |
| Section 3(1) Notarized AffidavitFile: Affidavit Under Sec 3(1).pdf | 13 Jan 2022 |
| Query No.2 - GPAFile: GPA.pdf | 13 Jan 2022 |
| Query No.3 - Approved building Plans from 1st to 8th FloorFile: TYPICAL 2 4 6 8 FLOOR.pdf | 13 Jan 2022 |
| Query No.3 - Approved building Plans from 1st to 8th FloorFile: TYPICAL 3 5 7 AND TERRACE.pdf | 13 Jan 2022 |
| Query No.3 - Approved building Plans from 1st to 8th FloorFile: GROUND FLOOR PLAN.pdf | 13 Jan 2022 |
| Query No.4 - Cost detailsFile: cost details i7.pdf | 13 Jan 2022 |
| LRF Order under WPFile: WP order.pdf | 13 Jan 2022 |
| Endorsement for Receipt paymentFile: Endorsement - Non availability of receipt.jpg | 13 Jan 2022 |
| RTC, survey 11 | - |
| Mutation, survey 11 | - |
| Encumbrance Certificate, survey 11 | - |
| Conversion/Alienation Order, survey 11 | - |
| JDA, survey 11 | - |
| Khatha, survey 11 | - |
| Registration CertificateFile: IISIPL-GST Certificate.pdf | - |
| Organization StructureFile: Organisation Structure.pdf | - |
| Certificate issued by CA Form 1 | - |
| Certificate issued by Architect Form 2 | - |
| Certificate issued by Engineer Form 3 | - |
| Project Details | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: AFFIDAVIT - No mortgages and litigation.pdf | - |
| Certificate from Chartered Account | - |
| Balance Sheet 2020 - 2021File: 2020-21.pdf | - |
| Balance Sheet 2019 - 2020File: Balance Sheet.pdf | - |
| Balance Sheet 2018 - 2019File: bl 18-19_20200327113127.pdf | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| ICONEST 5 | Survey Nos.128/2 and 128/3, Kudlu Village, Sarjapura Hobli, Anekal Taluk | Ongoing | Mar 2023 | Not delivered |
| ICONEST 4 | Survey Nos.64/2 and 62/1, Thindlu Village, Sarjapur Hobli, Anekal Taluk | Ongoing | Jul 2022 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ICON MICASA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 8 registered projects within 2 km.
DS MAX SKY SANMAN
DS Max Properties Private Limited
M5 ECHELON
Mahendra Homes Private Limited
BREN PARK CITY
BREN CORPORATION PRIVATE LIMITED
DS MAX SKY STANZA
DS MAX PROPERTIES PRIVATE LIMITED
SATTVA AMRITYA
Sattva Resi Private Limited
HABULUS TRANQUIL
HABULUS BUILDERS AND DEVELOPERS PRIVATE LI
See every Bengaluru Urban project, with the district possession charts
Builder: ICON INFRA SHELTERS INDIA PRIVATE LIMITED
ICON INFRA SHELTERS INDIA PRIVATE LIMITED has 1 registration on RERA Karnataka, including ICON MICASA. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ICON MICASA is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ICON MICASA?
The registered promoter entity is ICON INFRA SHELTERS INDIA PRIVATE LIMITED, a company as per the filing. Its CIN U45202KA2012PTC064358 and GSTIN 29AACCI9710Q1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ICON MICASA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at ICON MICASA?
The professionals named in the filing: Architect: MIDHULA J; Engineer: Munish Sharma; Chartered Accountant: Raghavendra M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ICON MICASA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.