Home / Browse projects / Bengaluru Urban, Karnataka / HMT SRI GAYATHRI SERENITY

Registration approved No litigation declared Residential/Group Housing project

HMT SRI GAYATHRI SERENITY

By sdr constructions

RG-KA-25998 · RERA PRM/KA/RERA/1251/446/PR/070426/008573 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
5 of 16Construction stages donefurthest along: Masonry Construction, 80%
48 of 48Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 126 documents Report an error

HMT SRI GAYATHRI SERENITY is a Residential/Group Housing project by sdr constructions in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/070426/008573 on 7 Apr 2026. Possession is promised by 31 Dec 2029. 0 of the 48 units on this registration are recorded sold or booked, and 5 of 16 construction stages are filed complete.

At a glance

Project

  • NameHMT SRI GAYATHRI SERENITY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560016
  • Pincode560016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/070426/008573
  • ReraGenie IDRG-KA-25998

Builder

  • Namesdr constructions
  • Entity typePartnership Firm
  • GSTIN29ADPFS5689B1ZE
  • Authorized SignatoryDorasla Srinivas Reddy
  • Other registrations3 more →

Key dates

this monthRegisteredApr 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Apr 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed126 files

Current status

0%0 of 48 units booked
48.9%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HMT SRI GAYATHRI SERENITY---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 16 construction stages are filed complete. The stage furthest along is Masonry Construction, at 80%.

Building: 36% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction80%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities30

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes40%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes10%
LiftsYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,922 sq m
Named landowners1
LandownerVillageDistrict
Muniyamma--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 16.10 cr
Cost incurredRs 7.87 cr
Spent of the estimate48.89%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 16.10 crRs 7.87 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTata Vittala Srinivas
EngineerMandhadi Venkataramana Reddy
Chartered AccountantBogala Prasad

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed126

As listed on the registration, under the names the promoter filed them with; the newest 80 of 126 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/070426/008573 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form4.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4 q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: form 5.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
BANK ACCOUNT CONFIRMATIONFile: Bank account confirmation.pdf31 Mar 2026
CA CERTIFICATEFile: CA certificate.pdf31 Mar 2026
BANK AFFIDAVITFile: SGS Bank Affidavit.pdf31 Mar 2026
BANK ACCOUNT CONFIRMATIONFile: Bank account confirmation.pdf23 Mar 2026
CA CERTIFICATE FORM 1File: CA certificate.pdf23 Mar 2026
FIRM REGISTRATION CERTIFICATEFile: SDR reg certificate.pdf23 Mar 2026
BANK AFFIDAVITFile: SGS Bank Affidavit.pdf23 Mar 2026
SOURCE OF FUNDFile: Source of fund clarification.pdf23 Mar 2026
FINANCIAL STATEMENTFile: SDR CONSTRUCTIONS 2024.pdf23 Mar 2026
FINANCIAL STATEMENTFile: Total Set FY 2024 25.pdf23 Mar 2026
ECFile: EC latest.pdf23 Mar 2026
JD CUM AFFIDAVITFile: JD cum affidavit.pdf23 Mar 2026
FORM B AFFIDAVITFile: SGS Form B.pdf23 Mar 2026
MRFile: MR merger.pdf23 Mar 2026
BUILDING LICENSEFile: SG SERENITY BUILDING LICENS.pdf23 Mar 2026
BUILDING PLANFile: SG SERENITY BUILDING PLAN.pdf23 Mar 2026
KSPCB NOCFile: SG Serenity PCB NOC.pdf23 Mar 2026
SINGLE LAYOUT PLAN ORDERFile: SGS Single Plot Layout Order.pdf23 Mar 2026
SINGLE LAYOUT PLANFile: SGS Single plot Layout plan.pdf23 Mar 2026
SURVEY SKETCHFile: Survey Sketch.pdf23 Mar 2026
PLINTH CERTIFICATEFile: Plinth certificate.pdf23 Mar 2026
VILLAGE MAPFile: SGS Village map.pdf23 Mar 2026
MASTER PLANFile: CDP map.pdf23 Mar 2026
STRUCTURAL STABILITY CERTIFICATEFile: SGS Structural Stability Certificate.pdf23 Mar 2026
STP DRAWINGFile: SGS STP.pdf23 Mar 2026
STRUCTURAL ENGINEER SELF ATTESTED LICENSEFile: Structural engineer self attested license.pdf23 Mar 2026
SECTION 3 VIOLATION AFFIDAVITFile: SGS sec 3 Notarized Affidavit.pdf23 Mar 2026
PROJECT ESTIMATED COSTFile: SGS COST Estimation SNS.pdf23 Mar 2026
AREA STATEMENTFile: Area statement.pdf23 Mar 2026
LAND VALUE CALCULATIONFile: land value.pdf23 Mar 2026
PROFORMA OF AGREEMENT OF SALEFile: Agreement of Sale Proforma.pdf23 Mar 2026
MODEL FORM OF ALLOTMENT LETTERFile: MODEL FORM OF ALLOTMENT LETTER.pdf23 Mar 2026
BANK ACCOUNT CONFIRMATIONFile: Bank account confirmation.pdf12 Mar 2026
CA CERTIFICATE FORM 1File: CA certificate.pdf12 Mar 2026
BANK AFFIDAVITFile: SGS Bank Affidavit.pdf12 Mar 2026
SOURCE OF FUND CLARIFICATIONFile: Source of fund clarification.pdf12 Mar 2026
FIRM REGISTRATION CERTIFICATEFile: SDR reg certificate.pdf12 Mar 2026
BUILDING LICENSEFile: SG SERENITY BUILDING LICENSE.pdf12 Mar 2026
BUILDING PLANFile: SG SERENITY BUILDING PLAN.pdf12 Mar 2026
KSPCB NOCFile: SG Serenity PCB NOC.pdf12 Mar 2026
PLINTH CERTIFICATEFile: Plinth certificate.pdf12 Mar 2026
SINGLE PLOT LAYOUT ORDERFile: SGS Single Plot Layout Order.pdf12 Mar 2026
SINGLE PLOT LAYOUT PLANFile: SGS Single plot Layout plan.pdf12 Mar 2026
VILLAGE MAPFile: SGS Village map.pdf12 Mar 2026
SURVEY SKETCHFile: Survey Sketch.pdf12 Mar 2026
JD CUM AFFIDAVITFile: JD cum affidavit.pdf12 Mar 2026
////////////// MRFile: MR Serenity Endorsement.pdf12 Mar 2026
FORM BFile: SGS Form B.pdf12 Mar 2026
ECFile: EC latest.pdf12 Mar 2026
JD CUM AFFIDAVITFile: JD cum affidavit.pdf12 Mar 2026
PROJECT BRIEF ESTIAMATED COSTFile: SGS COST Estimation SNS.pdf12 Mar 2026
SECTION 3 NOTARIZED AFFIDAVITFile: SGS sec 3 Notarized Affidavit.pdf12 Mar 2026
STP DRAWINGFile: SGS STP.pdf12 Mar 2026
GUIDANCE VALUE CERTIFICATEFile: Guidance value certifi.pdf12 Mar 2026
STRUCTURAL STABILITY CERTIFICATEFile: SGS Structural Stability Certificate.pdf12 Mar 2026
LAND VALUE CALCULATIONFile: Land value calculation.pdf12 Mar 2026
RTC, survey 380/6-
Mutation, survey 380/6-
Encumbrance Certificate, survey 380/6-
Conversion/Alienation Order, survey 380/6-
Sale/Title/Gift Deed, survey 380/6-
JDA, survey 380/6-
Khatha, survey 380/6-
Registration CertificateFile: SDR Partnership Deed.pdf-
GST CertificateFile: SDR SERENITY GST.pdf-
Partnership DeedFile: SDR Partnership Deed.pdf-
Partner Details-
Partner Details-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep HMT SRI GAYATHRI SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmHMT SRI GAYATHRI SERENITOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: sdr constructions

SDR CONSTRUCTIONS has 4 registrations on RERA Karnataka, including Sri Gayathri Prime and HMT SRI GAYATHRI SERENITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HMT SRI GAYATHRI SERENITY is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HMT SRI GAYATHRI SERENITY?

The registered promoter entity is sdr constructions, a partnership firm as per the filing. Its GSTIN 29ADPFS5689B1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HMT SRI GAYATHRI SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HMT SRI GAYATHRI SERENITY?

The professionals named in the filing: Architect: Tata Vittala Srinivas; Engineer: Mandhadi Venkataramana Reddy; Chartered Accountant: Bogala Prasad. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HMT SRI GAYATHRI SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HMT SRI GAYATHRI SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HMT SRI GAYATHRI SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.