Registration approved No litigation declared Residential/Group Housing project

HM Scottsville

By HM Infratech Private Limited

RG-KA-49198 · RERA PRM/KA/RERA/1251/446/PR/181224/007307 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Jun 2027Possession promisedmoved 12 months from the original
5 of 18Construction stages donefurthest along: RCC or MS Framed structure, 98%
101 of 154Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 188 documents Report an error

HM Scottsville is a Residential/Group Housing project by HM Infratech Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/181224/007307 on 18 Dec 2024. Possession is promised by 30 Jun 2027. The completion date has moved by 12 months from the original filing. 53 of the 154 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.

At a glance

Project

  • NameHM Scottsville
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/181224/007307
  • ReraGenie IDRG-KA-49198

Builder

  • NameHM Infratech Private Limited
  • Entity typeCompany
  • GSTIN29AACCH0523J1ZQ
  • Authorized SignatoryMr.HJ Siwani and Mr.MJ Siwani
  • DirectorsMr.HJ Siwani & Mr.MJ Siwani
  • DirectorsMr.HJ Siwani, Mr. MJ Siwani
  • Project HeadMr.Kodanda Rama
  • Declared earlier projects2 →

Key dates

this monthRegisteredDec 2024First promiseJun 2026Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Dec 2024
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2026)
  • Buildings2 building records
  • Documents filed188 files

Current status

34%53 of 154 units booked
9.3%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---76076
Tower B---78078

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 98%.

Building: 88% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure98%
Masonry Construction97%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc78%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)85%
Railing and Grill fixing85%
Electrification, Water supply and Sanitary Finishing80%
Painting80%
Fire prevention and fire fighting fitting and fixture with network82%
Weather Proof work(tile,concrete)95%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work91%
Internal and External work including landscapes as per sanctioned drawings40%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes77%
Sewage and Drainage SystemYes85%
Water conservation/rain water harvesting/recharge of ground waterYes82%
Energy managementYes20%
Fire protection and fire safety requirementsYes88%
Solid waste management and disposalYes74%
Emergency Evacuation servicesYes79%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes75%
Storm water drainsYes75%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes85%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes85%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes40%
Club HouseYes95%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes75%
GymNoNot applicable
ParksNoNot applicable
Power BackupYes85%
Piped GasNoNot applicable
Water and SanitationYes84%
Air ConditioningNoNot applicable
StaircasesYes92%
LiftsYes85%
Corridor/LobbiesYes89%
Fire escapesYes87%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes87%
TerraceYes88%
Outer WallNoNot applicable
Open parking areasYes44%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesYes55%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Smt. A R Mangala--
Smt. N R Sowmya Sathyan--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 87.34 cr
Cost incurredRs 8.10 cr
Spent of the estimate9.28%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 86.10 crRs 7.37 cr
On-site expenditure-Consultants FeesRs 76.08 lakhRs 2.47 lakh
On-site expenditure-Site OverheadRs 48.09 lakhRs 9.17 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 61.24 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRB Associates
EngineerMr.Suhas Sabins
Chartered AccountantMr.Vijay Bhatia

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/260718/007307Jun 2026 → Jun 2027

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed188

As listed on the registration, under the names the promoter filed them with; the newest 80 of 188 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/181224/007307 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Chartered Accountant Certificate_compressed.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate_compressed.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer's Certificate_compressed.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Labour and Education Department13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Chartered Accountant Certificate_compressed.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate_compressed.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineering Certificate_compressed (1).pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Labour and Education Department13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
BWSSB NocFile: Affidavit_Renewal BWSSB NOC.pdf29 May 2026
Engineer CertificateFile: Attested_Engineering_License.jpeg29 May 2026
BESCOM NOCFile: BESCOM NOC.pdf29 May 2026
Fire NOCFile: Fire force department NOCcompressed.pdf29 May 2026
KSPCBFile: KSPCB NOC.pdf29 May 2026
BWSSB NocFile: Letter to BWSSB_ Renewal of NOC.pdf29 May 2026
SEIAA NocFile: SEIAA NOC.pdf29 May 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Chartered Accountant Certificate_compressed.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate_compressed.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer's Certificate_compressed.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Labour and Education Department13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Chartered Accountant Certificate_compressed.pdf17 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate_compressed.pdf17 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate_compressed.pdf17 Jan 2026
Q3 2025-26 Water supply and sewage board17 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)17 Jan 2026
Q3 2025-26 KPTCL- BESCOM17 Jan 2026
Q3 2025-26 Fire and Safety17 Jan 2026
Q3 2025-26 Labour and Education Department17 Jan 2026
Q3 2025-26 Airport Authority of India17 Jan 2026
Quarterly Report - Chartered Accountant's CertificateFile: Chartered Accountant Certificate_compressed.pdf22 Oct 2024
Quarterly Report - Architect's CertificateFile: Architect Certificate_compressed.pdf22 Oct 2024
Quarterly Report - Engineer's CertificateFile: Engineer Certificate_compressed.pdf22 Oct 2024
Balance Sheet 2021 with schedulesFile: Balance Sheet 2021.pdf22 Oct 2024
Balance Sheet 2022 with schedulesFile: Balance Sheet 2022.pdf22 Oct 2024
Balance Sheet 2023 with schedulesFile: Balance Sheet 2023.pdf22 Oct 2024
Building License from Local Authority Original CopyFile: building license_compressed.pdf19 Sep 2024
EC from 2004- 2024File: EC from 2004- 2024.pdf19 Sep 2024
Notarised JD cum declaration affidavitFile: Notarised JD cum declaration affidavit.pdf19 Sep 2024
Clarification in regard to Commencement CertificateFile: Clarification in regard to Commencement Certificate.pdf19 Sep 2024
Pass sheet 100%File: Pass Book for 100%.pdf10 Sep 2024
Pass sheet 70%File: Pass Book for 70%.pdf10 Sep 2024
Pass sheet 30%File: Pass Book for 30%.pdf10 Sep 2024
Chartered Accountant KYC and membership certificate with self-attestedFile: Chartered Accountant KYC with membership certificate.pdf10 Sep 2024
GST CertificateFile: HM Infratech- GST.pdf10 Sep 2024
Self Attested Directors KYCFile: Directors KYC with self-attested.pdf10 Sep 2024
Sources of funds to complete the projectFile: Sources of fund_compressed.pdf10 Sep 2024
Borrowing detailsFile: No Borrowing Letter.pdf10 Sep 2024
Chartered Accountant CertificateFile: Chartered Accountant Certificate.pdf10 Sep 2024
Profit & Loss 2021-2022File: Statement of Profit & Loss 2021.pdf10 Sep 2024
Profit & Loss 2022-2023File: Statement of profit & loss 2022.pdf10 Sep 2024
Profit & Loss 2023-2024File: statement of profit & loss 2023.pdf10 Sep 2024
Balance Sheet 2021-2022File: Balance Sheet 2021.pdf10 Sep 2024
Balance Sheet 2022-2023File: Balance Sheet 2022.pdf10 Sep 2024
Balance Sheet 2023-2024File: Balance Sheet 2023-24.pdf10 Sep 2024
Income Tax Returns 2021-2022File: Income Tax Returns 2021.pdf10 Sep 2024
Income Tax Returns 2022-2023File: Income Tax Returns 2022.pdf10 Sep 2024
Income Tax Returns 2023-2024File: Income Tax Returns 2023.pdf10 Sep 2024
Cash Flow Statement 2021-2022File: Cash Flow Statement 2021.pdf10 Sep 2024
Cash Flow Statement 2022-2023File: Cash Flow Statement 2022.pdf10 Sep 2024
Cash Flow Statement 2023-2024File: Cash Flow Statement 2023.pdf10 Sep 2024
Current year RTCFile: RTC.pdf10 Sep 2024
ECFile: Encumbrance Certificate.pdf10 Sep 2024
Relinquishment DeedFile: Release Deed Ranganyakamma.pdf10 Sep 2024
Form BFile: FORM B - Notarized.pdf10 Sep 2024
JD cum AffidavitFile: JD_Affidavit_cum_Declaration.pdf10 Sep 2024
Building License from Local Authority Original CopyFile: Building license from local authority original copy.pdf10 Sep 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
PRM/KA/RERA/1251/310/PR/180516/001711 LitigationSurvey no.28, Jaraganahalli Village, Uttrahalli HobliOngoingDec 2025Not delivered
HM Tropical Tree4th Main Road, 15th Cross, R T Nagar,Completed-No date filed

How this compares with Bengaluru Urban

34%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep HM Scottsville on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: HM Infratech Private Limited

HM Infratech Private Limited has 1 registration on RERA Karnataka, including HM Scottsville. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HM Scottsville is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HM Scottsville?

The registered promoter entity is HM Infratech Private Limited, a company as per the filing. Its GSTIN 29AACCH0523J1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HM Scottsville?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HM Scottsville?

The professionals named in the filing: Architect: RB Associates; Engineer: Mr.Suhas Sabins; Chartered Accountant: Mr.Vijay Bhatia. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HM Scottsville?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HM Scottsville. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HM Scottsville to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.