Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Mar 2027Possession promisedmoved 21 months from the original
9 of 16Construction stages donefurthest along: Elevation work, 95%
71 of 138Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 83 documents Report an error

HINDUJA EL JARDIN is a Residential/Group Housing project by Hinduja Projects in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/190222/002444 on 22 Feb 2019. Possession is promised by 30 Mar 2027. The completion date has moved by 21 months from the original filing. 67 of the 138 units on this registration are recorded sold or booked, and 9 of 16 construction stages are filed complete.

At a glance

Project

  • NameHINDUJA EL JARDIN
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/472/PR/190222/002444
  • ReraGenie IDRG-KA-00683

Builder

  • NameHinduja Projects
  • Entity typePartnership Firm
  • Authorized SignatorySUNIL HINDUJA

Key dates

this monthRegisteredFeb 2019First promiseJun 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Feb 2019
  • Promised completion30 Mar 2027
  • Revised completionRevised to 30 Mar 2027 (originally 30 Jun 2025)
  • Buildings13 building records
  • Documents filed83 files

Current status

49%67 of 138 units booked
148.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
IRIS---12012
JASMINE---12012
LOTUS---12012
DAISY---12012
CARNATION---12012
ORCHID---12012
SUNFLOWER---12012
LAVENDER---12012
LILLY---12012
MAGNOLIA---12012
DAFFODIL---909
ROSE---606
TULIP---303

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 16 construction stages are filed complete. The stage furthest along is Elevation work, at 95%.

Building: 94% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification90%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing90%
Electrification, Water supply and Sanitary Finishing80%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Painting70%
Elevation work95%
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes85%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes85%
Parks & Tree plantingYes65%
Street LightingYes65%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes85%
Solid waste management and disposalYes85%
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes60%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes85%
Use of renewable energyYes50%
Water conservation/rain water harvesting/recharge of ground waterYes75%
ElectricityYes60%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes70%
Club HouseYes70%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes80%
Swimming PoolYes70%
GymYes60%
ParksYes55%
Power BackupYes0%
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes95%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes90%
BasementYes95%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes80%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,059 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 68.00 cr
Cost incurredRs 101.24 cr
Spent of the estimate148.88%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 66.00 crRs 76.04 cr
On-site expenditure-Consultants FeesRs 2.00 crRs 64.54 lakh
On-site expenditure-Salaries of workers-Rs 17.46 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 7.09 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTeam 2 Architects
EngineerTeam 2 Architects

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2025 → Mar 2026

No reason recorded in the filing

EX/PRM/KA/RERA/1251/472/PR/260219/002444Mar 2026 → Mar 2027

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed83

As listed on the registration, under the names the promoter filed them with; the newest 80 of 83 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/190222/002444 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate FORM-4 26-27 Q-2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect_s_Certi_for_Q-2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers_Certi_for_Q-2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate FORM-4 26-27 Q-1_compressed.pdf5 Aug 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect_s_Certi_for_Q-1 26-27.pdf5 Aug 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers_Certi_for_Q-1 26-27.pdf5 Aug 2026
Q1 2026-27 Water supply and sewage board5 Aug 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)5 Aug 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)5 Aug 2026
Q1 2026-27 KPTCL- BESCOM5 Aug 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA- CA Certificate Q-4 25-26.pdf19 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect_s_Certi_for_Q-4 25-26.pdf19 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers_Certi_for_Q-4 25-26.pdf19 May 2026
Q4 2025-26 Water supply and sewage board19 May 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)19 May 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)19 May 2026
Q4 2025-26 KPTCL- BESCOM19 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA- CA Certificate Q-3 25-26.pdf23 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect_s_Certi_for_Q-3 25-26.pdf23 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eingineer's Certi for Q-3 25-26.pdf23 Jan 2026
Q3 2025-26 Water supply and sewage board23 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)23 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)23 Jan 2026
Q3 2025-26 KPTCL- BESCOM23 Jan 2026
CertificateFile: FORM C Partnership Firm.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex-1 certificate of Architect_compressed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form-5.pdf-
CA Certificate for Funds UtilizationFile: Form-4 CA certificate for Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex-2 certificate of Architect_compressed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form-6.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-4 CA certificate for Fund Requied.pdf-
AffidavitFile: Ex 7_compressed.pdf-
Building Licence copy-
ilovepdf_merged (1)-
Final Plan-
Final Sale Deed-
final agmt_for_rera_after_schedules (1)-
title Deed-
ilovepdf_merged (1)-
Plan 1-ilovepdf-compressed (1)-
final agmt_for_rera_after_schedules (1)-
NOT YET PREPARED AFTER OBTAINING KRERA PERMANENT NUMBER WE HAVE PREPARE BROCHURE-
Specification-
EC final final-
katha and tax paid receipt-
JOint development agreement-
RTC-
conversion_order (1)-ilovepdf-compressed (1)-
conversion_order (1)-ilovepdf-compressed (1)-
relinquishment_deed_regd (1) (2)-
BESCOM Letter-
letter_for_bwssb_noc (1)-
kspcb_noc-
moef_noc (5)-
Unnamed document-
WE WILL OBTAIN AFTER COMPLETION OF STRUCTURAL WORK-
ilovepdf_merged (1)-
Final Plan-
Final Plan-
conversion_order (1)-ilovepdf-compressed (1)-
opinion final-
Balance Sheet 2017 - 2018File: itr_2018_19_itr_pal_bs (1)-ilovepdf-compressed (1).pdf-
Balance Sheet 2016 - 2017File: hinduja_projects_2017_18_itr_and_financials (1)-ilovepdf-compressed (1).pdf-
Balance Sheet 2015 - 2016File: 2016_17_itr_bs_pal (3)-ilovepdf-compressed (1).pdf-
Audited Profit and Loss Statement 2017 - 2018File: itr_2018_19_itr_pal_bs (1)-ilovepdf-compressed (1).pdf-
Audited Profit and Loss Statement 2016 - 2017File: hinduja_projects_2017_18_itr_and_financials (1)-ilovepdf-compressed (1).pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2016_17_itr_bs_pal (3)-ilovepdf-compressed (1).pdf-
Cash Flow Statement 2017 - 2018File: itr_2018_19_itr_pal_bs (1)-ilovepdf-compressed (1).pdf-
Cash Flow Statement 2016 - 2017File: hinduja_projects_2017_18_itr_and_financials (1)-ilovepdf-compressed (1).pdf-
Auditor's Report 2017 - 2018File: itr_2018_19_itr_pal_bs (1)-ilovepdf-compressed (1).pdf-
Auditor's Report 2016 - 2017File: hinduja_projects_2017_18_itr_and_financials (1)-ilovepdf-compressed (1).pdf-
Auditor's Report 2015 - 2016File: 2016_17_itr_bs_pal (3)-ilovepdf-compressed (1).pdf-
Income Tax Return Acknowledgement 2017 - 2018File: itr_2018_19_itr_pal_bs (1)-ilovepdf-compressed (1).pdf-
Income Tax Return Acknowledgement 2016 - 2017File: hinduja_projects_2017_18_itr_and_financials (1)-ilovepdf-compressed (1).pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 2016_17_itr_bs_pal (3)-ilovepdf-compressed (1).pdf-
FORM B-

How this compares with Bengaluru Urban

49%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep HINDUJA EL JARDIN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Hinduja Projects

Hinduja Projects has 1 registration on RERA Karnataka, including HINDUJA EL JARDIN. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HINDUJA EL JARDIN is delayed beyond 30 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HINDUJA EL JARDIN?

The registered promoter entity is Hinduja Projects, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HINDUJA EL JARDIN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HINDUJA EL JARDIN?

The professionals named in the filing: Architect: Team 2 Architects; Engineer: Team 2 Architects. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HINDUJA EL JARDIN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HINDUJA EL JARDIN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HINDUJA EL JARDIN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.