Home / Browse projects / Bengaluru Urban, Karnataka / HIGHCLIFF

Registration approved No litigation declared Residential/Group Housing project

HIGHCLIFF

By HIREN WAHEN BUILDTECH

RG-KA-59101 · RERA PRM/KA/RERA/1251/446/PR/171031/001436 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 11 complaints at RERA Karnataka
  • Completion date moved by 98 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Jun 2027Possession promisedmoved 98 months from the original
6 of 18Construction stages donefurthest along: RCC or MS Framed structure, 90%
63 of 196Units unsoldnot recorded sold or booked
11Complaints at RERA Karnatakaon this registration
Jump to the 127 documents Report an error

HIGHCLIFF is a Residential/Group Housing project by HIREN WAHEN BUILDTECH in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/171031/001436 on 31 Oct 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 98 months from the original filing. 133 of the 196 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete. 11 complaints are on record with the regulator.

At a glance

Project

  • NameHIGHCLIFF
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/171031/001436
  • ReraGenie IDRG-KA-59101

Builder

  • NameHIREN WAHEN BUILDTECH
  • Entity typePartnership Firm
  • Authorized SignatoryW.LALIT SINGH
  • DirectorNARENDRA BABU K
  • OthersPRAKASH LAKSHMAIAH
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2017First promiseApr 2019Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Oct 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 22 Apr 2019)
  • Buildings3 building records
  • Documents filed127 files

Current status

68%133 of 196 units booked
75.4%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---79079
B---65065
C---52052

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 90%.

Building: 85% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure90%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification60%
Dadoing, Skirting, Flooring, Tiles work (All types)80%
Railing and Grill fixing80%
Electrification, Water supply and Sanitary Finishing70%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network80%
Weather Proof work(tile,concrete)80%
Painting60%
Elevation work90%
Internal and External work including landscapes as per santioned drawings70%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes70%
Internal Roads & FootpathsYes71%
Sewage and Drainage SystemYes85%
Parks & Tree plantingYes51%
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes60%
Solid waste management and disposalYes60%
Water conservationYes60%
Energy managementYes0%
Fire protection and fire safety requirementsYes80%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes10%
Emergency Evacuation servicesYes20%
Storm water drainsYes90%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes70%
ElectricityYes10%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes80%
Club HouseYes80%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes80%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes90%
LiftsYes90%
Staircases and Lift lobbies, corridor,lobbies, corridorYes90%
Fire escapesYes90%
Common entrance and exit for the building / common portico/foyer/verandahYes85%
BasementYes99%
TerraceYes90%
Outer WallYes95%
Open parking areas and common storage spacesYes50%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes60%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,694 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 177.98 cr
Cost incurredRs 134.25 cr
Spent of the estimate75.43%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 125.00 crRs 84.39 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 51.38 crRs 42.14 cr
On-site expenditure-Salaries of workersRs 1.20 crRs 7.72 cr
On-site expenditure-Site OverheadRs 40.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVBT CONSORTIUM
EngineerPRASAD CONSULTANTS

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApr 2019 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/200205/001436not stated → Apr 2020

Reason as filed by the promoterothers

ExtensionApr 2020 → Jun 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka11

Case no.ComplainantRespondentFiled
CMP/190730/0003217-HIREN WAHEN BUILDTECH30/07/2019
CMP/190730/0003564-HIREN WAHEN BUILDTECH30/07/2019
CMP/200820/0002147-HIREN WAHEN BUILDTECH20/08/2020
CMP/211227/0008752-HIREN WAHEN BUILDTECH27/12/2021
00669/2023-HIREN WAHEN BUILDTECH04/05/2023
00866/2023-HIREN WAHEN BUILDTECH01/06/2023
01036/2023-HIREN WAHEN BUILDTECH30/06/2023
00987/2024-HIREN WAHEN BUILDTECH08/10/2024
00988/2024-HIREN WAHEN BUILDTECH08/10/2024
00994/2024-HIREN WAHEN BUILDTECH09/10/2024
01213/2026-HIREN WAHEN BUILDTECH12/10/2026

Documents filed127

As listed on the registration, under the names the promoter filed them with; the newest 80 of 127 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/171031/001436 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 Signed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architecture Certificate - 12-10-2026 (1).pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Cert - Sep 26 - Highcliff (1).pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered Accountant15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architecture Certificate June - 2026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Cert June 26' HWB.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architecture Certificate March-26 (1).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Cert - Mar 26 - HIGHCLIFF.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate SIgend.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architecture Certificate Dec-25_compressed.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Cert Dec 25.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
Q3 2025-26 Fire and Safety20 Feb 2026
Q3 2025-26 Airport Authority of India20 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department20 Feb 2026
TDR HWB-07-02-2024File: 1 TDR HWB-07-02-2024.pdf4 Mar 2025
Approved modified Building planFile: 2 Approved modified Building plan.pdf4 Mar 2025
Modified Building LicenceFile: 2 Modified Building Licence.pdf4 Mar 2025
Consent Letters - 19File: 3 Consent Letters.pdf4 Mar 2025
Consent Letters - 39File: 3 Consent Letters - 39.pdf4 Mar 2025
List of Sold UnitsFile: 4 List of Sold Units.pdf4 Mar 2025
List of Unsold UnitsFile: 4 List of Unsold Units.pdf4 Mar 2025
Structural Stability CertificateFile: 5 Structural Stability Certificate.pdf4 Mar 2025
Reply to QueryFile: Reply to Query.pdf4 Mar 2025
CertificateFile: incorporation certificate-hiren wahen buildtech.jpg-
Project Details-
Already registered project ongoing detailsFile: Signed CA Certificate HIren wahen Q2 FY 24-25.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Approved modified Building plan.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Approved modified Building plan.pdf-
List Of AllotteesFile: List of Allottees.pdf-
List Of ComplaintsFile: List of Complaints.pdf-
Consent LetterFile: Consent Letter Mr Meghomallar Das and Mrs Arjita Ganguly.pdf-
Chartered Accountant CertificateFile: Form 4 CA Certificate.pdf-
Notarized AffidavitFile: Affidavit.pdf-
Engineer CertificateFile: Form 6 Eng Cert Sep 24.pdf-
Architect CertificateFile: Form 5 Architect Certificate.pdf-
Structural Engineer Certificate for stability of structureFile: Structural Stability Certificate.pdf-
Modification of Plan DetailsFile: SITE PLAN-ilovepdf-compressed.pdf-
Modification of Plan DetailsFile: Approved modified Building plan.pdf-
Modification of Plan DetailsFile: Sold and Unosold Details as per previous plan.pdf-
Modification of Plan DetailsFile: Sold and Unsold Details as per modified plan.pdf-
Document 1File: Airport NOC 31-05-2023.pdf-
Document 2File: BESCOM NOC - 17 04 2023.pdf-
Document 3File: BSNL NOC.pdf-
Document 4File: BWSSB NOC 22-10-2024.pdf-
Document 5File: FIRE NOC-28-05-2024.pdf-
Document 6File: HAL NOC-11-05-2024.pdf-
Document 7File: PCB NOC-CFE Exp Annexure.pdf-
Document 8File: PCB NOC-CFE Exp Copy.pdf-
Consent Letter-Mr Prince KumarFile: Consent Letter-Mr Prince Kumar.pdf-
Consent Letter-MrArunshankarFile: Consent Letter-MrArunshankar.pdf-
Consent Letter-Mrs Itika Aggarwal&Mr Keshav GoyalFile: Consent Letter-Mrs Itika Aggarwal&Mr Keshav Goyal.pdf-
Consent Letter-Mrs Shwetha Raj MishraFile: Consent Letter-Mrs Shwetha Raj Mishra.pdf-
Consent Letter-MrThirumalaiprabhu NagarajanFile: Consent Letter-MrThirumalaiprabhu Nagarajan.pdf-
Mahendra Kathe-B3-303File: Mahendra Kathe-B3-303.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
ARCHSTONE-OngoingAug 2017Not delivered

How this compares with Bengaluru Urban

68%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 98 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep HIGHCLIFF on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: HIREN WAHEN BUILDTECH

HIREN WAHEN BUILDTECH has 1 registration on RERA Karnataka, including HIGHCLIFF. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HIGHCLIFF is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HIGHCLIFF?

The registered promoter entity is HIREN WAHEN BUILDTECH, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HIGHCLIFF?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HIGHCLIFF?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at HIGHCLIFF?

The professionals named in the filing: Architect: VBT CONSORTIUM; Engineer: PRASAD CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HIGHCLIFF?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HIGHCLIFF. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HIGHCLIFF to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.