High Life Towers

By MEENAKSHI INFRRA PROJECTS

RG-KA-04337 · RERA PRM/KA/RERA/1251/309/PR/200923/006268 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2027Possession promisedno revision filed
3 of 19Construction stages donefurthest along: Retaining wall (All types), 90%
245 of 313Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 218 documents Report an error

High Life Towers is a Residential/Group Housing project by MEENAKSHI INFRRA PROJECTS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/200923/006268 on 20 Sep 2023. Possession is promised by 5 Aug 2027. 68 of the 313 units on this registration are recorded sold or booked, and 3 of 19 construction stages are filed complete.

At a glance

Project

  • NameHigh Life Towers
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/200923/006268
  • ReraGenie IDRG-KA-04337

Builder

  • NameMEENAKSHI INFRRA PROJECTS
  • Entity typePartnership Firm
  • GSTIN29AAWFM5966B1ZN
  • Authorized SignatoryK YADAIAH

Key dates

this monthRegisteredSep 2023PromisedAug 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Sep 2023
  • Promised completion5 Aug 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed218 files

Current status

22%68 of 313 units booked
58.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---73073
Tower 2---2400240

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 19 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 90%.

Building: 30% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)90%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)60%
RCC or MS Framed structure49%
Masonry construction: Bricks, Concrete blocks etc37%
Plastering inside , outside & Ceiling12%
Joinery: Doors, Windows, Ventilators etc5%
Basic work of Water supply, Sanitary and Electrification5%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing4%
Electrification, Water supply and Sanitary Finishing0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes25%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes25%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes10%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes7%
LiftsYes7%
Staircases and Lift lobbies, corridor,lobbies, corridorYes5%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes15%
TerraceYes0%
Outer WallYes35%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners3
LandownerVillageDistrict
H R NARAYANA SWAMY--
Athique Ahmed--
Athique Ahmed--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 140.48 cr
Cost incurredRs 81.78 cr
Spent of the estimate58.22%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 140.48 crRs 40.89 cr
On-site expenditure-Site Overhead-Rs 40.50 cr
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 39.14 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIPKUMAR P. R
EngineerPradeep G Kedlaya
Chartered AccountantRAVI SESHAGIRI RAO

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed218

As listed on the registration, under the names the promoter filed them with; the newest 80 of 218 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/200923/006268 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf16 Jan 2026
Q3 2025-26 Water supply and sewage board16 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)16 Jan 2026
Q3 2025-26 KPTCL- BESCOM16 Jan 2026
Q3 2025-26 Fire and Safety16 Jan 2026
Q3 2025-26 Airport Authority of India16 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department16 Jan 2026
Title flow for Atique Ahmed Sy No 81 2BFile: Athique Ahmed Title Deed 81_2B.pdf25 Jul 2023
Title flow for Atique Ahmed Sy No 81 3BFile: Athique Ahmed Title Deed 81_3B.pdf25 Jul 2023
KHATHAFile: KHATHA.pdf25 Jul 2023
MR SY NO 81_2bFile: MR SY NO 81_2b.pdf25 Jul 2023
MR SY NO 81_3bFile: MR SY NO 81_3b.pdf25 Jul 2023
Legal ReportFile: Legal Report.pdf25 Jul 2023
BESCOM NOC WITH FEE PAID RECEIPTFile: BESCOM NOC WITH FEE PAID RECEIPT.pdf29 Jun 2023
Approved Building PlanFile: Block A 1 To 14th Floor Plan.pdf5 Apr 2023
Approved Building PlanFile: Block B 1 To 14th Floor Plan-1-2.pdf5 Apr 2023
Approved Building PlanFile: Elevation And Section Drawing Block A.pdf5 Apr 2023
Approved Building PlanFile: Elevation And Section Drawing Block B-1.pdf5 Apr 2023
Approved Building PlanFile: Ground Floor Plan-3.pdf5 Apr 2023
Approved Building PlanFile: Lower and Upper Basement Plan.pdf5 Apr 2023
Estimated cost of construction AbstractFile: Estimation Cost Details.pdf5 Apr 2023
Allotment LetterFile: Allotment Letter New Format.pdf5 Apr 2023
village map uploaded the kalu dari position is not matching with the layout map clarifyFile: Survey sketch.pdf5 Apr 2023
Project Start Date As of Building LicenseFile: Project Start Date As of Building Licence.pdf5 Apr 2023
Balance Sheet P&L 2020-21File: Balance Sheet P&L 2020-21.pdf28 Feb 2023
Balance Sheet P&L 2021-22File: Balance Sheet P&L 2021-22.pdf28 Feb 2023
Balance Sheet P&L 2022-23File: Balance Sheet P&L 2022-23.pdf28 Feb 2023
Approved Building PlanFile: Approved Building Plan.pdf28 Feb 2023
Village MapFile: Village Map.pdf28 Feb 2023
Copy of ZR Showing the Nala BufferFile: NGT SECONDARY NALA.pdf28 Feb 2023
AOSFile: AOS.pdf28 Feb 2023
Allotment LetterFile: Allotment Letter.pdf28 Feb 2023
BESCOM NOCFile: BESCOM NOC.pdf28 Feb 2023
Firm registration certificateFile: Firm Registration Certificate.pdf30 Jan 2023
partnership deedFile: PARTNERSHIP DEED.pdf30 Jan 2023
joint affidavitFile: JDA Affidavit.pdf30 Jan 2023
RTC syno 81/3BFile: 81 3B RTC.pdf30 Jan 2023
MR syno 81/3BFile: MR SY NO 81_3b.pdf30 Jan 2023
Akarband 81/3BFile: Akarband 81_2a_3b.pdf30 Jan 2023
Conversion Order Sy No 81/3BFile: Conversion order 81 3B.pdf30 Jan 2023
Rectifiaction JDA Page No 1 To 19File: Rectifiaction JDA-1-19.pdf30 Jan 2023
Rectifiaction JDA Page No 20 To 38File: Rectifiaction JDA-20-38.pdf30 Jan 2023
Ground Floor PlanFile: Ground Floor Plan.pdf30 Jan 2023
Elevation And Section Drawing Block AFile: Elevation And Section Drawing Block A.pdf30 Jan 2023
Elevation And Section Drawing Block BFile: Elevation And Section Drawing Block B.pdf30 Jan 2023
Block A 1 To 14th Floor PlanFile: Block A 1 To 14th Floor Plan.pdf30 Jan 2023
Block B 1 To 14th Floor PlanFile: Block B 1 To 14th Floor Plan.pdf30 Jan 2023
Lower and Upper Basement PlanFile: Lower and Upper Basement Plan.pdf30 Jan 2023
Bwssb NocFile: Bwssb Noc.pdf30 Jan 2023
GPAFile: GPA.pdf30 Jan 2023
KSPCB NOCFile: KSPCB NOC.pdf30 Jan 2023

How this compares with Bengaluru Urban

22%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep High Life Towers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: MEENAKSHI INFRRA PROJECTS

MEENAKSHI INFRRA PROJECTS has 1 registration on RERA Karnataka, including High Life Towers. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if High Life Towers is delayed beyond 5 Aug 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of High Life Towers?

The registered promoter entity is MEENAKSHI INFRRA PROJECTS, a partnership firm as per the filing. Its GSTIN 29AAWFM5966B1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in High Life Towers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at High Life Towers?

The professionals named in the filing: Architect: DILIPKUMAR P. R; Engineer: Pradeep G Kedlaya; Chartered Accountant: RAVI SESHAGIRI RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in High Life Towers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About High Life Towers. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save High Life Towers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.