Registration approved No litigation declared Residential/Group Housing project

HEAVIE EDEN

By SENTIENT DEVELOPERS PRIVATE LIMITED

RG-KA-73548 · RERA PRM/KA/RERA/1251/446/PR/210222/004725 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2026Possession promisedmoved 24 months from the original
14 of 14Construction stages doneevery applicable stage filed complete
13 of 28Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 109 documents Report an error

HEAVIE EDEN is a Residential/Group Housing project by SENTIENT DEVELOPERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/210222/004725 on 21 Feb 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 15 of the 28 units on this registration are recorded sold or booked, and 14 of 14 construction stages are filed complete.

At a glance

Project

  • NameHEAVIE EDEN
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560035
  • Pincode560035
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/210222/004725
  • ReraGenie IDRG-KA-73548

Builder

  • NameSENTIENT DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45309KA2020PTC137488
  • GSTIN29AAFCH3946N1ZY
  • Authorized SignatorySRIRAJKUMAR RAMALINGA REDDY
  • Managing DirectorSRIRAJKUMAR RAMALINGA REDDY
  • DirectorsSRIRAJKUMAR RAMALINGA REDDY, KUPPUREDDY RAMESH
  • Project HeadKiran Kumar

Key dates

this monthRegisteredFeb 2022First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed109 files

Current status

54%15 of 28 units booked
186.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---28028

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 14 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymYes100%
ParksNoNot applicable
Power BackupYes100%
Piped GasYes100%
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,097 sq m
Named landowners1
LandownerVillageDistrict
SS DEVELOPERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.46 cr
Cost incurredRs 21.34 cr
Spent of the estimate186.25%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 8.60 crRs 15.92 cr
Payment of taxesRs 97.00 lakhRs 1.57 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 70.00 lakhRs 1.33 cr
On-site expenditure-Salaries of workersRs 65.00 lakhRs 1.64 cr
On-site expenditure-Consultants FeesRs 24.00 lakhRs 60.57 lakh
Payment of feesRs 12.20 lakh-
On-site expenditure-Site OverheadRs 10.00 lakhRs 25.24 lakh
Payment of cessRs 6.70 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.00 lakhRs 2.52 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAVEEN MAHANTESH
EngineerSURYAKANTH PAVARE
Chartered AccountantJayachandra Reddy Gurumunti

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/250203/004725Dec 2024 → Dec 2025

Reason as filed by the promoterForce Majeure; Delay in getting loan

ExtensionDec 2025 → Dec 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed109

As listed on the registration, under the names the promoter filed them with; the newest 80 of 109 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/210222/004725 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Heavie Form 4 - Signed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate - Q2 - Signed.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: HEAVIE EDEN - Form - 6 - Signed.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Heavie Form 4 - Signed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate - Q1 Signed.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: HEAVIE EDEN - Form - 6 - Signed.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Heavie Form 4 - Q4 - Signed.pdf18 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate - Q4 - Signed.pdf18 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engeneer Certificate - Q4 - Signed.pdf18 May 2026
Q4 2025-26 Water supply and sewage board18 May 2026
Q4 2025-26 KPTCL- BESCOM18 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Q3 - Signed.pdf21 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 - Q3 - Signed.pdf21 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Q3 - Signed.pdf21 Feb 2026
Q3 2025-26 Water supply and sewage board21 Feb 2026
Q3 2025-26 KPTCL- BESCOM21 Feb 2026
Covering LetterFile: Covering Letter.pdf25 Jan 2025
Commencement Certificate valid for 5 yearsFile: COMMENCEMENT CERTIFICATE Heavie Eden.pdf25 Jan 2025
Audit ReportFile: Audit Report.pdf25 Jan 2025
chartered accountant certificate for total estimation costFile: 1 CA Certificate.pdf17 Feb 2022
CA UDIN for 2020-21 financial statementFile: Audit Report (HEAVIE DEVELOPERS PVT LTD-2021).pdf17 Feb 2022
sale deed and title deed in the name of Balakrishna ganapathyFile: 4 Sale deed Annamayya and balakrishna.pdf17 Feb 2022
sale deed and title deed anilFile: 4 Sale deed Anil Kumar.pdf17 Feb 2022
sale deed and title deed anil and annamayyaFile: 4 Sale deed doc Annamayya and anilkumar.pdf17 Feb 2022
sale deed and title deed BalakrishnaFile: 4 Sale deed Doc Balakrishna.pdf17 Feb 2022
E.C. from 19-09--2021 to upto dateFile: 5 EC till date.pdf17 Feb 2022
Sub-registrar regarding value of the property on the basis of guidance valueFile: Guidance Value - sub registrar.pdf17 Feb 2022
notarized Non- litigation affidavit with respect the propertyFile: 7 Notarized Non litigation affidavit.pdf17 Feb 2022
Building license letterFile: 8 Building License Number.pdf17 Feb 2022
KSPCB NOCFile: 9 NOC KSPCB.pdf17 Feb 2022
NOC Water supplyFile: 13 BWSSB Appln.pdf17 Feb 2022
NOC BescomFile: 13 NOC BESCOM.PDF17 Feb 2022
blank proforma of AOSFile: 14 AGREEMENT TO SELL - RERA - Heaive Developers.pdf17 Feb 2022
blank proforma Sale deedFile: 15 SALE DEED RERA - Builder share - Heavie Developers.pdf17 Feb 2022
STP demarcated site plan and STP design drawingFile: STP Design drawing.pdf17 Feb 2022
signed copy of project specificationFile: 17 Signed project specification.pdf17 Feb 2022
section 3(1) notarized affidavitFile: 18 Acknowledgement number with Original copy of section 3(1) notarized affidavit.pdf17 Feb 2022
Reply to the queriesFile: Reply to queries.pdf17 Feb 2022
RTC, survey 6/7-
Mutation, survey 6/7-
Encumbrance Certificate, survey 6/7-
Conversion/Alienation Order, survey 6/7-
Sale/Title/Gift Deed, survey 6/7-
JDA, survey 6/7-
Khatha, survey 6/7-
Registration CertificateFile: CERTIFICATE OF INCORPORATION.PDF-
Organization StructureFile: Org Chart.pdf-
Certificate issued by CA Form 1File: CA Certificate.pdf-
Certificate issued by Architect Form 2File: NMAD-RERA-Jan2022 (1).pdf-
Certificate issued by Engineer Form 3File: Engineers_Certificte.pdf-
Project Details-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: JDA Affidavit Cum Declaration-1-5.pdf-
Certificate from Chartered AccountFile: Building license.jpeg-
Balance Sheet 2020 - 2021File: Heavie BS 20-21.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Heavie PL 20-21.pdf-
Director's Report 2020 - 2021File: 20211225151927_compressed 33_compressed-compressed_compressed_compressed (1)_compressed.pd-
Auditor's Report 2020 - 2021File: Audit Report (HEAVIE DEVELOPERS PVT LTD-2021)_compressed.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ackoledge.pdf-
CC-
Bescom Approval Letter-
Temp00002 (2) (1) (1)-
R2_HEAVIE EDEN 09 DEC 21 (1)-
Temp00002 (2) (1) (1)-
R2_HEAVIE EDEN 09 DEC 21 (1)-7-8-
Temp00002 (2) (1) (1)-
Temp00002 (2) (1) (1)-
Engineers_Certificte-
Annexure 79-
JDA Affidavit Cum Declaration-6-46 (1)-
Conversion Certificate (1)-
Draft SALE DEED-cln-23-01-2022-
draft Allotment letter_RERA_HEAVIE_cln-24-01-2022-
R2_HEAVIE EDEN 09 DEC 21 (1) (1)-

How this compares with Bengaluru Urban

54%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 24 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep HEAVIE EDEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmHEAVIE EDENOther 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: SENTIENT DEVELOPERS PRIVATE LIMITED

SENTIENT DEVELOPERS PRIVATE LIMITED has 1 registration on RERA Karnataka, including HEAVIE EDEN. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HEAVIE EDEN is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HEAVIE EDEN?

The registered promoter entity is SENTIENT DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45309KA2020PTC137488 and GSTIN 29AAFCH3946N1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HEAVIE EDEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HEAVIE EDEN?

The professionals named in the filing: Architect: NAVEEN MAHANTESH; Engineer: SURYAKANTH PAVARE; Chartered Accountant: Jayachandra Reddy Gurumunti. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HEAVIE EDEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HEAVIE EDEN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HEAVIE EDEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.