ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Hamiton Towers

Registration approved No litigation declared Residential/Group Housing project

Hamiton Towers

By Pelagsus Infrastructures Pvt Ltd

RG-KA-00913 · RERA PRM/KA/RERA/1251/310/PR/140223/005705 · Last updated on RERA Karnataka portal: 12 Jan 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 92 documents Report an error

Hamiton Towers is a Residential/Group Housing project by Pelagsus Infrastructures Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/140223/005705 on 14 Feb 2023. Possession is promised by 31 Dec 2024.

At a glance

Project

  • NameHamiton Towers
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/140223/005705
  • ReraGenie IDRG-KA-00913

Builder

  • NamePelagsus Infrastructures Pvt Ltd
  • Entity typeCompany
  • CINU45201GJ2008PTC053260
  • GSTIN29AAECP6930D1ZE
  • Authorized SignatoryManoj Barai
  • Managing DirectorRakesh Israni
  • DirectorGunjan Israni
  • Project HeadDipan Shah

Key dates

this monthRegisteredFeb 2023PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Feb 2023
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---39039

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 12 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasYes-
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
Pelagsus Infrastructures Pvt Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 77.50 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 46.50 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 20.00 cr-
Payment of taxesRs 6.00 cr-
On-site expenditure-Salaries of workersRs 5.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPG Patki
EngineerBE Pruthviraja
Chartered AccountantVirang Mehta

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed92

As listed on the registration, under the names the promoter filed them with; the newest 80 of 92 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/140223/005705 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration for KSPCB NocFile: 1 Declaration for KSPCB Noc.pdf12 Jan 2023
Declaration for SEIAA NocFile: 1 Declaration for SEIAA Noc.pdf12 Jan 2023
Declaration for Commencement certiFile: 2 Declaration for Commencement certi.pdf12 Jan 2023
Proforma of AOSFile: 3 Proforma of AOS.pdf12 Jan 2023
Architect CertificateFile: 4 Architect Certificate.pdf12 Jan 2023
SRO Valuation CertificateFile: SRO valuation Pelagsus.pdf10 Nov 2022
Non Litigation AffidavitFile: Affidavit RERA no cases due.pdf10 Nov 2022
KSPCB NOCFile: KSPCB NOC & CFE.pdf10 Nov 2022
SEIAA NOC / CorigendumFile: Norma Corrigendum SEIAA.pdf10 Nov 2022
SEIAA Extension notificationFile: EC NOC time extension 10 years gazette notification.pdf10 Nov 2022
MOEF Extension notificationFile: MoEF Notification one year extension.pdf10 Nov 2022
Validity of Building DrawingFile: Validity of Building plan.pdf10 Nov 2022
Specification sheet with signatureFile: Specification.pdf10 Nov 2022
AFS Draft as per RERA FormatFile: AFS draft - Hamilton Tower.pdf10 Nov 2022
Updated BWSSB NOCFile: BWSSB NOC updated.pdf10 Nov 2022
1 AffidavitFile: 31Affidavit.pdf10 Feb 2022
Allotment LetterFile: Allotment.pdf10 Feb 2022
Aggrement of SaleFile: AOS.pdf10 Feb 2022
BBMP Renewal ApplicationFile: BBMP Modified.pdf10 Feb 2022
BWSSBFile: BWSSB NOC.pdf10 Feb 2022
Demarced plan for fees and area clarificationFile: Demarced Layout Plan.pdf10 Feb 2022
ECFile: EC.pdf10 Feb 2022
Financial Statement for delayFile: Financial Statement.pdf10 Feb 2022
Katha extractFile: Khata Extract.pdf10 Feb 2022
KathaFile: Khata.pdf10 Feb 2022
Project SpecificationsFile: Project specs.pdf10 Feb 2022
Property value proofFile: PVC.pdf10 Feb 2022
RTCFile: RTC.pdf10 Feb 2022
sale deed 1File: Sale deed 1.pdf10 Feb 2022
sale deed 2File: Sale deed 2.pdf10 Feb 2022
sale deed 3File: Sale deed 3.pdf10 Feb 2022
sale deed 4File: Sale deed 4.pdf10 Feb 2022
sale deed 5File: Sale deed 5.pdf10 Feb 2022
SEIAAFile: SIEAA.pdf10 Feb 2022
STPFile: STP.pdf10 Feb 2022
Registration CertificateFile: Certificate of Incorporation after change of name Pelagsus.pdf-
Organization StructureFile: Organization chart.pdf-
Certificate issued by CA Form 1File: CA Certificate.pdf-
Certificate issued by Architect Form 2File: Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Form-B Affidavit.pdf-
Certificate from Chartered AccountFile: CA Certificate.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet-20-21.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet-19-20.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet -18-19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit & Loss 20-21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit & Loss-19-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P & L -18-19.pdf-
Director's Report 2019 - 2020File: Director Report_2019-20_.pdf-
Director's Report 2018 - 2019File: Director Report-18-19.pdf-
Cash Flow Statement 2020 - 2021File: Cash Flow-20-21.pdf-
Cash Flow Statement 2019 - 2020File: Cash FLow-19-20.pdf-
Auditor's Report 2020 - 2021File: Auditor Report-20-21_compressed.pdf-
Auditor's Report 2019 - 2020File: Auditor Report-19-20.pdf-
Auditor's Report 2018 - 2019File: Audit Report - 18-19.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR-19-20.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR-19-20.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR-18-19.pdf-
BBMP modified building plan license-
BESCOM NOC 2020-
BWSSB 2012-
Layout-
Combine_compressed (1)-
Layout-
Project specifications_compressed-
Sections-
ADP-
MCY - Structural Stability Letter 20210819-
Title Report Pelagsus-
Conversion orders combined_compressed (1)-
AFS draft-
Allotment letter 05-01-2022-
Light-Hamilton-Towers-Bangalore-
Form-B -HAMILTON TOWER-
3 (1) notarised affidavit-
BESCOM NOC 2020-
BWSSB 2012-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Hamiton Towers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Pelagsus Infrastructures Pvt Ltd

Pelagsus Infrastructures Pvt Ltd has 1 registration on RERA Karnataka, including Hamiton Towers. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Hamiton Towers is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Hamiton Towers?

The registered promoter entity is Pelagsus Infrastructures Pvt Ltd, a company as per the filing. Its CIN U45201GJ2008PTC053260 and GSTIN 29AAECP6930D1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Hamiton Towers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Hamiton Towers?

The professionals named in the filing: Architect: PG Patki; Engineer: BE Pruthviraja; Chartered Accountant: Virang Mehta. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hamiton Towers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hamiton Towers. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hamiton Towers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.