Home / Browse projects / Nanded, Maharashtra / GVC SHAGUN CITY IV
GVC SHAGUN CITY IV
RG-MH-05029 · RERA P51100047816 · Last updated on MahaRERA portal: 23 Jun 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Nanded registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GVC SHAGUN CITY IV is a Residential / Group Housing project by SHAGUN BUILDCON in Nanded, Maharashtra, registered with MahaRERA as P51100047816 on 28 Nov 2022. The registration is recorded completed; possession was promised by 31 Dec 2025.
At a glance
Project
- NameGVC SHAGUN CITY IV
- TypeResidential / Group Housing
- Location
- GVC SHAGUN CITY
- KAUTHA
- Nanded Waghala (M Corp.)
- Nanded
- 431603
- Pincode431603
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51100047816
- ReraGenie IDRG-MH-05029
Builder
- NameSHAGUN BUILDCON
- Entity typePartnership
- PartnersGANGAPRASAD RAMESHWAR TOSHNIWAL, PRADEEP GAJANANRAO CHADAWAR, DURGAPASAD RAMESHWAR TOSHNIWAL, PAWAN PADEEP CHADAWAR
- Other registrations2 more →
- Completed1 of 3
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on28 Nov 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings13 building records
- Documents filed78 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B1 | NA | 2 | 0 | 0 | 0 | 0 |
| B2 | NA | 2 | 0 | 0 | 0 | 0 |
| B3 | NA | 2 | 0 | 0 | 0 | 0 |
| B4 | NA | 2 | 0 | 0 | 0 | 0 |
| B5 | NA | 2 | 0 | 0 | 0 | 0 |
| B6 | NA | 2 | 0 | 0 | 0 | 0 |
| B7 | NA | 2 | 0 | 0 | 0 | 0 |
| B8 | NA | 2 | 0 | 0 | 0 | 0 |
| B9 | NA | 2 | 0 | 0 | 0 | 0 |
| B10 | NA | 2 | 0 | 0 | 0 | 0 |
| B11 | NA | 2 | 0 | 0 | 0 | 0 |
| B12 | NA | 2 | 0 | 0 | 0 | 0 |
| APARTMENT | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building13
As on 23 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
100 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Internal walls, at 70%.
B173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B373%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B473%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B573%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B673%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B773%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B873%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B973%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B1073%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B1173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B1273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
APARTMENT66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 23 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 30% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 30% |
| Open Parking | No | Not applicable |
Parking filed24
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| B1 | 2 | 2 |
| B2 | 2 | 2 |
| B3 | 2 | 2 |
| B4 | 2 | 2 |
| B5 | 2 | 2 |
| B6 | 2 | 2 |
| B7 | 2 | 2 |
| B8 | 2 | 2 |
| B9 | 2 | 2 |
| B10 | 2 | 2 |
| B11 | 2 | 2 |
| B12 | 2 | 2 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SOURABH S KARANDIKAR |
| Engineer | SANDESH PATIL |
| Chartered Accountant | CA MAYUR AGARWAL |
| Partner | Role in project |
|---|---|
| SHAGUN BUILDCON | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Aug 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Aug 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Aug 2022
Documents filed78
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: REPLY MAIL.pdf | 23 Jun 2025 |
| Occupational CertificateFile: SHAGUN BUILDCON (78R) OC COVERING LETTER.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B1_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B2_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B3_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B4_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B5_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B6_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B7_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B8_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B9_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B10_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B11_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-B12_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: UNIT NO-A1,A2 & A3_compressed.pdf | 10 Jun 2025 |
| Occupational CertificateFile: LAYOUT_compressed.pdf | 10 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHAGUN 4 20241231.pdf | 23 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHAGUN 4 20241231.pdf | 23 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHAGUN 4 31122024.pdf | 23 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SHAGUN BUILDCON PH IV 20240930.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHAGUN 4 20240630.pdf | 27 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHAGUN 4 20240630.pdf | 27 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHAGUN 4 20240630.pdf | 27 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHAGUN 4 31032024.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHAGUN 4 31032024.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHAGUN 4 31032024.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHAGUN IV FORM 3 20240115.pdf | 9 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SHAGUN IV FORM 3 20240115.pdf | 9 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHAGUN IV FORM 3 20240115.pdf | 9 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHAGUN 4 30092023.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SHAGUN BUILDCON FORM 5.pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHAGUN 4 20230630 SELF DECLARATION.pdf | 28 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: COMP SHAGUN CITY PHASE IV 31012023.pdf | 14 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: SHAGUN BUILDCON DEVIATION REPORT 1.pdf | 18 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: SHAGUN BUILDCON DEVIATION REPORT 2.pdf | 18 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: SHAGUN BUILDCON AGREEMENT 1.pdf | 16 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: SHAGUN BUILDCON AGREEMENT 2.pdf | 16 Nov 2022 |
| Proforma of Agreement for saleFile: Shagun City Phase IV.pdf | 18 Oct 2022 |
| Proforma of Allotment letterFile: Shagun City Phase IV.pdf | 18 Oct 2022 |
| Proforma of Allotment letterFile: ALLOTMENT IV compressed.pdf | 18 Oct 2022 |
| Proforma of Agreement for saleFile: ALLOTMENT IV compressed.pdf | 18 Oct 2022 |
| Details of encumbrances concerned to FinanceFile: enumbrances.pdf | 29 Aug 2022 |
| Details of encumbrances concerned to LegalFile: encumbrances phase iv.pdf | 29 Aug 2022 |
| Declaration about Commencement CertificateFile: commencement declaration.pdf | 29 Aug 2022 |
| Declaration in FORM BFile: form b iv.pdf | 29 Aug 2022 |
| CERSAI detailsFile: cersai iv.pdf | 29 Aug 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RERA Model Draft.pdf | 29 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank details.pdf | 29 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: ALLOTMENT DEVIATION IV.pdf | 29 Aug 2022 |
| Layout approvalFile: GUT NO 174 LAYOUT.pdf | 24 Aug 2022 |
| Building plan approvalFile: 1.pdf | 24 Aug 2022 |
| Building plan approvalFile: 2.pdf | 24 Aug 2022 |
| Building plan approvalFile: 3.pdf | 24 Aug 2022 |
| Building plan approvalFile: 4.pdf | 24 Aug 2022 |
| Building plan approvalFile: 5.pdf | 24 Aug 2022 |
| Building plan approvalFile: 6.pdf | 24 Aug 2022 |
| Building plan approvalFile: 7.pdf | 24 Aug 2022 |
| Building plan approvalFile: 8.pdf | 24 Aug 2022 |
| Building plan approvalFile: 9.pdf | 24 Aug 2022 |
| Building plan approvalFile: 10.pdf | 24 Aug 2022 |
| Building plan approvalFile: 25.pdf | 24 Aug 2022 |
| PAN CardFile: SHAGUN BUILDCON PAN CARD PDF.pdf | 24 Aug 2022 |
| Copy of the legal title reportFile: SHAGUN BUILDCON GUT NO 174 SEARCH REPORT (1).pdf | 24 Aug 2022 |
| Copy of Layout Approval (in case of layout)File: GUT NO 174 LAYOUT.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 9.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 10.pdf | 24 Aug 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 25.pdf | 24 Aug 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COVER PAGE.pdf | 24 Aug 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COVER PAGE 2.pdf | 24 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: m p agarwal phase iv rectified compressed.pdf | 24 Aug 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nanded
Computed across the 100+ Nanded projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 78 filed documents as one ZIP, foldered, with a manifest
Keep GVC SHAGUN CITY IV on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KAUTHA100+ in Nanded
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
Vishwakarma Layout
VISHWAKARMA HOUSING PVT. LTD
SHRI SWAMI SAMARTH HEIGHTS
SHRI SWAMI SAMARTH ESTATES
GVC GANGADHAM PHASE I
GVC DEVELOPERS
GVC GANGADHAM SKYILA
GVC DEVELOPERS
A R KHIYANI CITY
M B BUILDERS AND DEVELOPERS
PADMANABHA RESIDENCY
SHREE SAMARTH BUILDERS AND DEVELOPERS
See every Nanded project, with the district possession charts
Builder: SHAGUN BUILDCON
SHAGUN BUILDCON has 3 registrations on MahaRERA, including HORIZON PARK and GVC SHAGUN CITY IV. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nanded district page.
Frequently asked questions
What are my rights if GVC SHAGUN CITY IV is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GVC SHAGUN CITY IV?
The registered promoter entity is SHAGUN BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GVC SHAGUN CITY IV?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GVC SHAGUN CITY IV?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GVC SHAGUN CITY IV?
The professionals named in the filing: Architect: SOURABH S KARANDIKAR; Engineer: SANDESH PATIL; Chartered Accountant: CA MAYUR AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GVC SHAGUN CITY IV?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.