Home / Browse projects / Bengaluru Urban, Karnataka / GREEN STOREYS

Registration approved No litigation declared Residential/Group Housing project

GREEN STOREYS

By MODERN SPACES

RG-KA-10802 · RERA PRM/KA/RERA/1251/308/PR/170125/007394 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
6 of 17Construction stages donefurthest along: Masonry Construction, 95%
81 of 135Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 107 documents Report an error

GREEN STOREYS is a Residential/Group Housing project by MODERN SPACES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/170125/007394 on 17 Jan 2025. Possession is promised by 31 Dec 2026. 54 of the 135 units on this registration are recorded sold or booked, and 6 of 17 construction stages are filed complete.

At a glance

Project

  • NameGREEN STOREYS
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/170125/007394
  • ReraGenie IDRG-KA-10802

Builder

  • NameMODERN SPACES
  • Entity typePartnership Firm
  • GSTIN29ABRFM2213K1ZX
  • Authorized SignatoryShravanth P
  • Other registrations4 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJan 2025PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Jan 2025
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed107 files

Current status

40%54 of 135 units booked
39.4%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower -A---62062
Tower -B---73073

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 17 construction stages are filed complete. The stage furthest along is Masonry Construction, at 95%.

Building: 48% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction95%
Plastering inside , outside & Ceiling35%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification20%
Dadoing, Skirting, Flooring, Tiles work (All types)40%
Railing and Grill fixing15%
Electrification, Water supply and Sanitary Finishing10%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
MODERN SPACES--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 97.63 cr
Cost incurredRs 38.42 cr
Spent of the estimate39.35%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 68.00 crRs 25.78 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 18.63 crRs 11.00 cr
On-site expenditure-Consultants FeesRs 11.00 crRs 1.64 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLakshman D N
EngineerVenkatesh Choppa
Chartered AccountantCA- SUHAS D - SUHAS DEVERAJ AND ASSOCIATES

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed107

As listed on the registration, under the names the promoter filed them with; the newest 80 of 107 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/170125/007394 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Green Storyes Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Green Storyes Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Green Storyes Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: 2026-06-30_Form 4_Green Storeys (Signed).pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: GREEN_STOREYS_RERA_FORM 5.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: GREEN_STOREYS_RERA_FORM 6.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_Green Storeys.pdf20 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: GS Form 5.pdf20 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: GS Form 6.pdf20 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_Green Storeys.pdf21 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM_5_Green Storeys.pdf21 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM_6_Green Storeys.pdf21 Jan 2026
RTC, survey 44-
Mutation, survey 44-
Encumbrance Certificate, survey 44-
Conversion/Alienation Order, survey 44-
Sale/Title/Gift Deed, survey 44-
Khatha, survey 44-
Registration CertificateFile: Form C Reg Cert.pdf-
GST CertificateFile: MSA GST Certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM_1_GREEN_STOREYS.pdf-
Certificate issued by Architect Form 2File: FORM_2_Architect.pdf-
Certificate issued by Engineer Form 3File: Form_3_Engineer.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit_Non_Litigation.pdf-
Balance Sheet 2023 - 2024File: MSA Signed Financilas 2023-24.pdf-
Balance Sheet 2022 - 2023File: MSA Signed Financilas 2022-23.pdf-
Balance Sheet 2021 - 2022File: MSA Signed Financials 2021-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: MSA Signed Financilas 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: MSA Signed Financilas 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: MSA Signed Financials 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR FY 2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR FY 2021-22.pdf-
Commencement Letter-
1 Site Plan-
11 Sections-
structural_report_GreenStoreys-
Specification_list_Green_storeys-
Reliquishment deed-
GREEN STOREYS AOS-
ALLOTMENT LETTER-
Form_B_Affidavit_green_Storeys-
Non_Violation_Affidavit_Green_Storeys-
LEGAL_OPINION-
BESCOM NOC 14-01-2016-
Water NOC - Green storey's-
KSPCB NOC 20-03-2015-
SEIAA or MOEF NOC 6-5-2015-
Green Stories-FIRE NOC 28-09-2017-
MPN Builders Airport NOC-
MPN BSNL NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Old RTC-
SALE_DEED - Title Doc-

How this compares with Bengaluru Urban

40%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GREEN STOREYS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: MODERN SPACES

MODERN SPACES has 5 registrations on RERA Karnataka, including GREEN STOREYS and Modern Spaces Felicity Engrace 1. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GREEN STOREYS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GREEN STOREYS?

The registered promoter entity is MODERN SPACES, a partnership firm as per the filing. Its GSTIN 29ABRFM2213K1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GREEN STOREYS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GREEN STOREYS?

The professionals named in the filing: Architect: Lakshman D N; Engineer: Venkatesh Choppa; Chartered Accountant: CA- SUHAS D - SUHAS DEVERAJ AND ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREEN STOREYS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREEN STOREYS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREEN STOREYS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.