ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / GREEN SQUARE

Registration lapsed No litigation declared Others project

GREEN SQUARE

By TRUE VISION DEVELOPERS LLP

RG-MH-14979 · RERA P51600033730 · Last updated on MahaRERA portal: 31 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 20 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Feb 2025Possession promised20 months past this date
1 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

GREEN SQUARE is a Others project by TRUE VISION DEVELOPERS LLP in Nashik, Maharashtra, registered with MahaRERA as P51600033730 on 8 Mar 2022. Possession was promised by 28 Feb 2025 and is now 20 months past that date.

At a glance

Project

  • NameGREEN SQUARE
  • TypeOthers
  • Location
    • BHAGUR REST CAMP ROAD
    • BHAGUR
    • Bhagur Rural
    • Nashik
    • 422502
  • Pincode422502
  • RERA no.P51600033730
  • ReraGenie IDRG-MH-14979

Builder

  • NameTRUE VISION DEVELOPERS LLP
  • Entity typePartnership
  • PartnersRAKESH VISHNUKUMAR SHARMA, SWAPNIL Y SHETE, HIREN NALIN UDANI, NIKUNJ MANSUKHLAL TURAKHIA

Key dates

20 months past promisethis monthRegisteredMar 2022PromisedFeb 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Mar 2022
  • Promised completion28 Feb 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GREEN SQUARE ANA30000
GREEN SQUARE BNA40000
GREEN SQUARE CNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 31 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

GREEN SQUARE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GREEN SQUARE B9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GREEN SQUARE C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered20
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
GREEN SQUARE A02020
GREEN SQUARE B12012
GREEN SQUARE C808

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,596 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
TRUE VISION DEVELOPERS LLPMumbai CityMumbai City

Approvals and building plan

Permissible FSI1797.9
Proposed, not sanctioned1,798 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNASHIK

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRASIK BOTHARA
EngineerJAYESH MAKWANA
Chartered AccountantSUSHIL SAKHARE
PartnerRole in project
TRUE VISION DEVELOPERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Mar 2025

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Merged Completion.pdf31 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certif.pdf21 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert.pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: T V booked inv 310324.pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: TV sol Inv 311224.pdf21 Mar 2025
Other - TechnicalFile: Form 4.pdf21 Mar 2025
Other - TechnicalFile: Completion Certificate.pdf21 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance.pdf21 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: True Vision Form 3 31032024.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: True Vision Form 3 31122024.pdf21 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: True Vision Form 5 22-23.pdf6 Apr 2024
Declaration in FORM BFile: Form B Final_.pdf24 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf24 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate.pdf24 Feb 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf24 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Final.pdf24 Feb 2022
Building plan approvalFile: Plan A Final.pdf18 Feb 2022
Building plan approvalFile: Plan B Final.pdf18 Feb 2022
Building plan approvalFile: Plan C Final.pdf18 Feb 2022
Layout approvalFile: Commencement Certificate True Vision Final.pdf18 Feb 2022
PAN CardFile: True Vision PAN Copy.pdf18 Feb 2022
Copy of the legal title reportFile: TSR - True Vision Final.pdf18 Feb 2022
Details of encumbrancesFile: Declaration for Non-Encumbrances.pdf18 Feb 2022
Copy of Layout Approval (in case of layout)File: Commencement Certificate True Vision Final.pdf18 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan A Final.pdf18 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan B Final.pdf18 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan C Final.pdf18 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate True Vision Final.pdf18 Feb 2022
Declaration about Commencement CertificateFile: Form D Declaration for Commencement.pdf18 Feb 2022
CERSAI detailsFile: Cersai Details.pdf18 Feb 2022
Proforma of Allotment letterFile: Allotment Letter- True Vision Final.pdf18 Feb 2022
Proforma of Allotment letterFile: Draft Agreement True Vision Final.pdf18 Feb 2022

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GREEN SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHAGUR4,100+ in Nashik

Builder: TRUE VISION DEVELOPERS LLP

TRUE VISION DEVELOPERS LLP has 1 registration on MahaRERA, including GREEN SQUARE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that GREEN SQUARE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GREEN SQUARE is delayed beyond 28 Feb 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GREEN SQUARE?

The registered promoter entity is TRUE VISION DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GREEN SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GREEN SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GREEN SQUARE?

The professionals named in the filing: Architect: RASIK BOTHARA; Engineer: JAYESH MAKWANA; Chartered Accountant: SUSHIL SAKHARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREEN SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREEN SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREEN SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.