Home / Browse projects / Bengaluru Urban, Karnataka / GP Aditya

Registration approved Residential/Group Housing project

GP Aditya

By VIJAYA LAKSHMI CONSTRUCTIONS

RG-KA-64174 · RERA PRM/KA/RERA/1251/310/PR/190626/002629 · Last updated on RERA Karnataka portal: 26 Aug 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2023Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 111 documents Report an error

GP Aditya is a Residential/Group Housing project by VIJAYA LAKSHMI CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190626/002629 on 26 Jun 2019. Possession is promised by 30 Dec 2023. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameGP Aditya
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/190626/002629
  • ReraGenie IDRG-KA-64174

Builder

  • NameVIJAYA LAKSHMI CONSTRUCTIONS
  • Entity typePartnership Firm
  • Authorized SignatorySiva Ram Prasad Gorantla
  • OthersPrasanth Parandham Nag Gorantla, Lakshmi Gorantla, Usha Rani Gorantla, Sri Ranga Pujitha Gorantla

Key dates

this monthRegisteredJun 2019First promiseMar 2022Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Jun 2019
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 31 Mar 2022)
  • Buildings1 building record
  • Documents filed111 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GP Adithya---44044

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 26 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 26 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,672 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.26 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2022 → Dec 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/230425/002629Dec 2022 → Dec 2023

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed111

As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190626/002629 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
consent lettersFile: 201 conent letter.pdf26 Aug 2021
consent lettersFile: 302 consent letter.pdf26 Aug 2021
consent lettersFile: 401 consent letter.pdf26 Aug 2021
consent lettersFile: 504 consent letter (1).pdf26 Aug 2021
affidavit cum DeclarationFile: gp aditya affidavit.pdf26 Aug 2021
Consent LetterFile: consunt letters 302,201 & 401.pdf13 Aug 2021
Consent LetterFile: 504 consent Letter.pdf13 Aug 2021
Consent LetterFile: consent letter 3.pdf13 Aug 2021
Sold and Unsold inventoryFile: unsold and sold inventory.pdf13 Aug 2021
Sold and Unsold inventoryFile: Sold Unsold Details.xlsx13 Aug 2021
BANK STATEMENTFile: BANK STATEMENT.pdf15 Jun 2021
MODIFIED AREA STAEMENTFile: MODIFIED AREA STATEMENT.pdf15 Jun 2021
SOLD INVENTORYFile: sold inventory.pdf15 Jun 2021
UNSOLD INVENTORYFile: unsold inventory.pdf15 Jun 2021
ELEVATIONFile: MODIFIED ELEVATION.jpg15 Jun 2021
GROUND FLOORFile: MODIFIED GROUND FLOOR PLAN.jpg15 Jun 2021
TYPICAL FLOOR PLANFile: MODIFIED TYPICAL FLOOR PLAN.jpg15 Jun 2021
LOWER BASEMENTFile: MODIFIEDLOWER BASEMENT FLOOR.jpg15 Jun 2021
REPLY TO QUERYFile: REPLY TO QUERY.pdf15 Jun 2021
CertificateFile: VLC GST Certificate.pdf-
Already registered project ongoing detailsFile: PRMKARERA1251310PR190626002629.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: PLAN LICENSE LETTER.pdf-
Elevation, Sections, Specifications ( If changes are there )File: SECTION ELEVATION SHEET 4.pdf-
List Of AllotteesFile: ALLOTTEES LIST.pdf-
Consent LetterFile: consent letters.pdf-
List Of Pending LitigationsFile: NIL Litigation.pdf-
Chartered Accountant CertificateFile: Form 4 C A CERTIFICATE.pdf-
Notarized AffidavitFile: Affidavit.pdf-
Engineer CertificateFile: Form 6 Engineer.pdf-
Architect CertificateFile: Form 5 Architect.pdf-
Structural Engineer Certificate for stability of structureFile: structural stability_20210308172008.pdf-
Modification of Plan DetailsFile: site Plan.pdf-
Modification of Plan DetailsFile: ALL PLANS.pdf-
Modification of Plan DetailsFile: COMMENCEMENT CERTIFICATE.pdf-
Modification of Plan DetailsFile: COMMENCEMENT CERTIFICATE.pdf-
Modification of Plan DetailsFile: SOLD UNSOLD INVENTORY.xlsx-
Modification of Plan DetailsFile: SOLD UNSOLD INVENTORY.xlsx-
Document 1File: NOC-AAI.pdf-
Document 2File: NOC-BESCOM.pdf-
Document 3File: NOC-BSNL.pdf-
Document 4File: NOC-BWSSB.pdf-
Document 5File: NOC-KSPCB.pdf-
Document 6File: Fire NOC.pdf-
ALL PLANSFile: ALL PLANS.pdf-
LOWER BASEMENT PLANFile: LOWER BASEMENT PLAN.pdf-
SECTION ELEVATION PLANFile: SECTION ELEVATION SHEET 4.pdf-
SITE PLANFile: SITE PLAN GROUND FLOOR PLAN.pdf-
TYPICAL FLOOR PLANFile: TYPICAL FLOOR PLAN.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1 Architect Certificate For Status of Work as on date (1).pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5 (1).PDF-
CA Certificate for Funds UtilizationFile: Form-Ex3 Chartered Accountant Certificate For Fund Utilization (1).pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2 Architect Certificate For Pending Work as on date (1).pdf-
Engineer Certificate for Pending Work Completion Schedule.File: form-Ex6.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4 Chartered Accountant Certificate For Fund Required (2).pdf-
AffidavitFile: form B_compressed.pdf-
Latest Encumbrance CertificateFile: NA1.pdf-
Details Of Sold/ Un-sold UnitsFile: SOLD UNSOLD INVENTORY.xlsx-
NOC DetailsFile: bescom sanction copy-compressed.pdf-
CC 7-1-2019-
all plans_compressed-
Proforma Sale Deed-
Proforma Sale Agreement-
All Sale Deeds-
Sectional Plan-
Sectional Plan-
Allotment letter-
Project Specification details-
EC-
Sec 3(1) Affudvait-
VIJAYALAKSHMI(AFFIDAVIT CUM DECLARATION)-
KHATHA-
JDA_ GPA & sharing agreement-
NOC-FIRE_compressed-
Airport Noc-
BESCOM Noc-
BWSSB Noc-
KSPCB Noc-
BSNL Noc-
Unnamed document-
All floor plans-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GP Aditya on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGP AdityaOther 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: VIJAYA LAKSHMI CONSTRUCTIONS

VIJAYA LAKSHMI CONSTRUCTIONS has 1 registration on RERA Karnataka, including GP Aditya. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GP Aditya is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GP Aditya?

The registered promoter entity is VIJAYA LAKSHMI CONSTRUCTIONS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GP Aditya?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in GP Aditya?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GP Aditya. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GP Aditya to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.