Home / Browse projects / Bengaluru Urban, Karnataka / GOVIANU NAKSHATHRA

Registration approved No litigation declared Residential/Group Housing project

GOVIANU NAKSHATHRA

By Mahesh Govindaraju

RG-KA-28699 · RERA PRM/KA/RERA/1251/309/PR/100125/007375 · Last updated on RERA Karnataka portal: 2 Jan 2025

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2027Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

GOVIANU NAKSHATHRA is a Residential/Group Housing project by Mahesh Govindaraju in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/100125/007375 on 10 Jan 2025. Possession is promised by 31 Mar 2027.

At a glance

Project

  • NameGOVIANU NAKSHATHRA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/100125/007375
  • ReraGenie IDRG-KA-28699

Builder

  • NameMahesh Govindaraju
  • Entity typeProprietorship
  • GSTIN29AOHPM6441E1ZU
  • Authorized SignatoryMahesh Govindaraju

Key dates

this monthRegisteredJan 2025PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Jan 2025
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAKSHATHRA---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 2 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 2 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Arjun--
Vijayalakshmi R--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.08 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 10.00 cr-
On-site expenditure-Consultants FeesRs 1.50 cr-
Administrative CostRs 1.50 cr-
Payment of taxesRs 1.08 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi J Adiga
EngineerVishnu Kumar
Chartered AccountantMahaveer Bhansali Jain

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/100125/007375 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
AffidaviteFile: AFFIDAVIT .pdf2 Jan 2025
Designated bank account number matched with CA CertificateFile: Bank Account.pdf2 Jan 2025
Source of FundsFile: SOURCE OF FUNDS.pdf2 Jan 2025
Previous projects annual audit non submission penalty not yet paidFile: Old projects Audit querry.pdf2 Jan 2025
E KathaFile: E Khatha - R vijaya.pdf2 Jan 2025
JDAFile: JDA Gnakshathra.pdf2 Jan 2025
Legal OpinionFile: Gnakshathra SBI legal Opinion.pdf2 Jan 2025
Guidance CertificateFile: Govt Guidance Value Certificate Nakshatra.pdf2 Jan 2025
Building PlanFile: Updated PRJ_1993_22-23.pdf2 Jan 2025
Village MapFile: Village Map.pdf2 Jan 2025
Each Floor PlanFile: Updated PRJ_1993_22-23.pdf2 Jan 2025
KSPCB NOCFile: Consent For Establishment KSPCB.pdf2 Jan 2025
AREA SPECIFICATIONFile: AREA SPECIFICATION.pdf2 Jan 2025
Structure stability reportFile: Structure stability report.pdf2 Jan 2025
GNAKSHATHARA FLAT AREAFile: GNAKSHATHARA FLAT AREA .xlsx2 Jan 2025
BWSSB RECEIPTFile: BWSSB NOC.pdf2 Jan 2025
BWSSB Demand NoteFile: BWSSB Demand Note.pdf2 Jan 2025
Form 1 new - Govianu Nakshathra signedFile: 1 Form 1 new - Govianu Nakshathra signed.pdf24 Sep 2024
Clarification on PenaltyFile: 2 Clarification on Penalty.pdf24 Sep 2024
Source of Funds with supporting docsFile: 3 Source of Funds with supporting docs.pdf24 Sep 2024
Amalgamated Katha PresentFile: 1 Amalgamated Katha Present.pdf24 Sep 2024
Gnakshathra legal OpinionFile: 2 Gnakshathra legal Opinion.pdf24 Sep 2024
ECC-01042024-25994File: 3 ECC-01042024-25994.pdf24 Sep 2024
Guidelines value Self AttestedFile: 4 Guidelines value Self Attested.pdf24 Sep 2024
JDA G NakshathraFile: 5 JDA G Nakshathra.pdf24 Sep 2024
Khatha Amalgamation LetterFile: 6 Khatha Amalgamation Letter.pdf24 Sep 2024
BBMP Approved PlanFile: 1 BBMP Approved Plan.pdf24 Sep 2024
CDP DemarcationFile: 2 CDP Demarcation.pdf24 Sep 2024
NOC KSPCBFile: 3 NOC KSPCB.pdf24 Sep 2024
RERA bank AffidavitFile: 4 RERA bank Affidavit.pdf24 Sep 2024
Form-6 GOVIANU NAKSHATRA 24-09-2024File: 6 Form-6 GOVIANU NAKSHATRA 24-09-2024.pdf24 Sep 2024
BWSSB Covering LetterFile: 7 BWSSB Covering Letter.pdf24 Sep 2024
Zonal Regulation 2015File: Zonal Regulation 2015.pdf24 Sep 2024
Common Areas and AmenitiesFile: 5 Common Areas and Amenities.pdf24 Sep 2024
KSPCB CircularFile: KSPCB Circular.pdf24 Sep 2024
Agreement_of_Sale_Proforma nakshatraFile: Agreement_of_Sale_Proforma nakshatra.pdf24 Sep 2024
CA License Self AttestedFile: CA License Self Attested.pdf21 Aug 2024
GST CertificateFile: GST Certificate.pdf21 Aug 2024
Mahesh FY 2021-22 with UDINFile: Mahesh FY 2021-22 with UDIN.pdf21 Aug 2024
Mahesh FY 2022-23 with UDINFile: Mahesh FY 2022-23 with UDIN.pdf21 Aug 2024
Mahesh PANFile: Mahesh PAN.pdf21 Aug 2024
Amalgamated Katha PresentFile: Amalgamated Katha Present.pdf21 Aug 2024
Current year RTCFile: Current year RTC.pdf21 Aug 2024
EC 2004-2024File: EC 2004-2024.pdf21 Aug 2024
Gift Deed 3986 (20-21) to V N RangayyaFile: Gift Deed 3986 (20-21) to V N Rangayya.pdf21 Aug 2024
Guidelines value Self AttestedFile: Guidelines value Self Attested.pdf21 Aug 2024
Khatha Amalgamation LetterFile: Khatha Amalgamation Letter.pdf21 Aug 2024
BBMP Approved Plan with Section and Floor plansFile: BBMP Approved Plan with Section and Floor plans.pdf21 Aug 2024
BESCOM NOC AND RECEIPTFile: BESCOM NOC AND RECEIPT .pdf21 Aug 2024
Estimation cost of ConstructionFile: Estimation cost of Construction.pdf21 Aug 2024
Form-3 GOVIANU NAKSHATRAFile: Form-3 GOVIANU NAKSHATRA.pdf21 Aug 2024
Notarized Affidavit for 3(1) VoilationFile: Notarized Affidavit for 3(1) Voilation.pdf21 Aug 2024
Proforma Allotment LetterFile: Proforma Allotment Letter.pdf21 Aug 2024
Project SpecificationFile: Project Specification.pdf21 Aug 2024
Village MapFile: Village Map.pdf21 Aug 2024
Zonal Regulation 2015File: Zonal Regulation 2015.pdf21 Aug 2024
Registration CertificateFile: GST Registration Certificate.pdf-
GST CertificateFile: GST Registration Certificate.pdf-
Certificate issued by CA Form 1File: Form 1 new - Govianu Nakshathra signed.pdf-
Certificate issued by Architect Form 2File: Form-2 Govianu Nakshatra.pdf-
Certificate issued by Engineer Form 3File: Form-3 GOVIANU NAKSHATRA.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non-Litigation Details- With JDA.pdf-
Certificate from Chartered AccountFile: Form 1 new - Govianu Nakshathra signed.pdf-
Balance Sheet 2022 - 2023File: Mahesh IT Returns FY 2022-23 with UDIN.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Mahesh IT Returns FY 2022-23 with UDIN.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Mahesh IT Returns FY 2022-23 with UDIN.pdf-
BBMP Building License-
BBMP Approved Plan-
BBMP Approved Plan-
JDA and GPA-
Affidavit FORM B-
Notarized Affidavit for 3(1) Voilation-
Joint Affidavit from Promoter and Landowner-
BWSSB Application Gnakshathra-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GOVIANU NAKSHATHRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Mahesh Govindaraju

Mahesh Govindaraju has 1 registration on RERA Karnataka, including GOVIANU NAKSHATHRA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GOVIANU NAKSHATHRA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GOVIANU NAKSHATHRA?

The registered promoter entity is Mahesh Govindaraju, a proprietorship as per the filing. Its GSTIN 29AOHPM6441E1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GOVIANU NAKSHATHRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GOVIANU NAKSHATHRA?

The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: Vishnu Kumar; Chartered Accountant: Mahaveer Bhansali Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOVIANU NAKSHATHRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOVIANU NAKSHATHRA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOVIANU NAKSHATHRA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.