Home / Browse projects / Bengaluru Urban, Karnataka / Gopalan Florenza

Registration approved No litigation declared Residential/Group Housing project

Gopalan Florenza

By GOPALAN ENTERPRISES

RG-KA-07684 · RERA PRM/KA/RERA/1251/310/PR/190726/002733 · Last updated on RERA Karnataka portal: 14 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 57 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Jan 2026Possession promisedmoved 57 months from the original
5 of 15Construction stages donefurthest along: Electrification, 95%
176 of 480Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 115 documents Report an error

Gopalan Florenza is a Residential/Group Housing project by GOPALAN ENTERPRISES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190726/002733 on 26 Jul 2019. Possession is promised by 24 Jan 2026. The completion date has moved by 57 months from the original filing. 304 of the 480 units on this registration are recorded sold or booked, and 5 of 15 construction stages are filed complete.

At a glance

Project

  • NameGopalan Florenza
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/190726/002733
  • ReraGenie IDRG-KA-07684

Builder

  • NameGOPALAN ENTERPRISES
  • Entity typePartnership Firm
  • Authorized SignatoryC.Pramod
  • Board MemberC.Gopalan
  • Other registrations3 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2019First promiseApr 2021Revised toJan 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Jul 2019
  • Promised completion24 Jan 2026
  • Revised completionRevised to 24 Jan 2026 (originally 24 Apr 2021)
  • Buildings5 building records
  • Documents filed115 files

Current status

63%304 of 480 units booked
7.1%Of the estimated cost spent so far

Figures as on 14 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---96096
Block B---96096
Block C---96096
Block D---96096
Block E---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 15 construction stages are filed complete. The stage furthest along is Electrification, at 95%.

Building: 94% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification90%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing90%
Electrification, Water supply and Sanitary Finishing95%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network95%
Weather Proof work(tile,concrete)95%
Painting90%
Elevation work90%
Internal and External work including landscapes as per santioned drawings90%

Progress on shared amenities41

As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes80%
Internal Roads & FootpathsYes70%
Sewage and Drainage SystemYes90%
Parks & Tree plantingNoNot applicable
Street LightingYes75%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes95%
Solid waste management and disposalYes80%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsYes95%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes93%
Emergency Evacuation servicesYes95%
Storm water drainsYes85%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes75%
ElectricityYes75%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes70%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksNoNot applicable
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes90%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes90%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes95%
TerraceYes95%
Outer WallYes100%
Open parking areas and common storage spacesYes90%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes90%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,039 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 149.55 cr
Cost incurredRs 10.65 cr
Spent of the estimate7.12%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 119.49 crRs 3.90 cr
On-site expenditure-Site OverheadRs 22.00 crRs 4.13 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 crRs 2.12 cr
On-site expenditure-Salaries of workersRs 2.40 crRs 30.00 lakh
On-site expenditure-Consultants FeesRs 50.00 lakhRs 20.00 lakh
Payment of feesRs 10.00 lakh-
Payment of taxesRs 5.60 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKRISHNAMURTHY KV
EngineerVINOD JAIN

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApr 2021 → Jan 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/220613/002733Jan 2022 → Jan 2023

Reason as filed by the promoterothers

ExtensionJan 2023 → Jan 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed115

As listed on the registration, under the names the promoter filed them with; the newest 80 of 115 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190726/002733 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Qtr 4 - 2025-26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Arch Qtr 4 - 2025-26.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Qtr 4 - 2025-26.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Cert Q3 2025-26.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Arch Cert Q3 2025-26.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Cert Q3 2025-26.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
Change of Account - Approval mail enclosedFile: Approval letter.jpg6 Jun 2022
Covering letter for BESCOM & BWSSB NOC relatedFile: Cover letter Florenza Extension.pdf6 Jun 2022
Affidavit - BESCOMFile: Affidavit - BESCOM.pdf6 Jun 2022
Affidavit - BWSSBFile: Affidavit - BWSSB.pdf6 Jun 2022
BESCOM - AcknowledgementFile: ACK BESCOM NOC.pdf6 Jun 2022
BWSSB - AcknowledgementFile: ACK Application BWSSB.pdf6 Jun 2022
NOC - BESCOMFile: BESCOM NOC.pdf6 Jun 2022
NOC - BWSSBFile: NOC BWSSB - Florenza.pdf6 Jun 2022
Valid BWSSB NOCFile: NOC BWSSB - Florenza.pdf9 Apr 2022
Acknowledgement of Request for NOC- BESCOMFile: ACK BESCOM NOC.pdf9 Apr 2022
Updated Form BFile: Form B R1.pdf9 Apr 2022
Revised Form BFile: Form B.pdf18 Feb 2022
Commencement CertificateFile: Florenza Commencement certificate.pdf18 Feb 2022
Sanction letter - ReceivedFile: Renewed approved sanction.pdf18 Feb 2022
KSPCB NOCFile: KSPCB NOC R1.pdf18 Feb 2022
SEIAA NOCFile: SLEIAA.pdf18 Feb 2022
Approved drawingFile: florenza approved site plan.pdf18 Feb 2022
Approved cross sectionsFile: Section & Elevation.pdf18 Feb 2022
Architect certificateFile: Architect Cert Form Ex 2 R1.pdf18 Feb 2022
Engineer CertificateFile: Engg Certi Form Ex 6 R1.pdf18 Feb 2022
Form Ex 7File: Affidavit for extension.pdf18 Feb 2022
Cost DetailsFile: Cost Details.pdf18 Feb 2022
Structural Stability CertificateFile: Structural Stability Certificate - GOPALAN FLORENZA_25-01-2022.pdf18 Feb 2022
STP DrawingsFile: STP_LAYOUT PLAN SECTIONS 1.pdf18 Feb 2022
STP DrawingsFile: STP_LAYOUT PLAN SECTIONS 2.pdf18 Feb 2022
STP DrawingsFile: STP_LAYOUT PLAN SECTIONS 3.pdf18 Feb 2022
STP DrawingsFile: STP_LAYOUT PLAN SECTIONS 4.pdf18 Feb 2022
STP DrawingsFile: STP_LAYOUT PLAN SECTIONS 5.pdf18 Feb 2022
STP LocationFile: STP location.jpg18 Feb 2022
Relinquishment deedFile: Relinquishment Deed Florenza.pdf25 Jan 2022
Approved building planFile: Renewed approved drawing.pdf25 Jan 2022
Extended Project Registration certificateFile: PRMKARERA1251310PR190726002733-R2.pdf25 Jan 2022
Bank Account no not matching.File: Florenza change request application.jpg25 Jan 2022
Bank account not matchingFile: Letter to RERA regarding Bank statement of 765 account.pdf25 Jan 2022
proforma of Agreement of saleFile: Gopalan Florenza Final agreement.pdf25 Jan 2022
Abstract of sold and unsold flat detailsFile: SoldUnsoldDetails.xlsx25 Jan 2022
BESCOM NOCFile: BESCOM NOC.pdf25 Jan 2022
AAI NOCFile: Airport Authority.pdf25 Jan 2022
SEIAA NOCFile: SLEIAA.pdf25 Jan 2022
BWSSB NOCFile: BWSSB.pdf25 Jan 2022
CertificateFile: GE_-_REGN_FORM_D_001.jpg-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Architect Form Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Form Ex5.pdf-
CA Certificate for Funds UtilizationFile: CA Form Ex5.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Form Ex2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Form Ex6.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Form Ex4.pdf-
AffidavitFile: Form Ex-7.pdf-
Latest Encumbrance CertificateFile: Land EC 2021 Nov 001.jpg-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Relinquishment Deed Florenza.pdf-
CC request letter-
site plan-
typical floor-
agreement for sale-
agreement for sale-
Final Sale Deed-
section & elevation-
BDA-1-
allotment letter-florenza-
A4 - Florenza-compressed-

How this compares with Bengaluru Urban

63%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 57 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Gopalan Florenza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGopalan FlorenzaOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: GOPALAN ENTERPRISES

GOPALAN ENTERPRISES has 4 registrations on RERA Karnataka, including GOPALAN LAKEFRONT and Gopalan Olympia. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Gopalan Florenza is delayed beyond 24 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Gopalan Florenza?

The registered promoter entity is GOPALAN ENTERPRISES, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Gopalan Florenza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Gopalan Florenza?

The professionals named in the filing: Architect: KRISHNAMURTHY KV; Engineer: VINOD JAIN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gopalan Florenza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gopalan Florenza. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gopalan Florenza to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.