GOPAL KRISHNA
RG-MH-12238 · RERA P51700001570 · Last updated on MahaRERA portal: 12 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 96 months
- 7 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOPAL KRISHNA is a Residential / Group Housing project by SONAL DEV-CON PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700001570 on 29 Jul 2017. Possession is promised by 30 Apr 2027. The completion date has moved by 96 months from the original filing. 27 of the 54 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameGOPAL KRISHNA
- TypeResidential / Group Housing
- Location
- sector 30&31
- Near Agroli Pond
- Navi Mumbai (M Corp.)
- Thane
- 400614
- Pincode400614
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700001570
- ReraGenie IDRG-MH-12238
Builder
- NameSONAL DEV-CON PVT LTD
- Entity typeCompany
- Managing DirectorRAMDAS NATHA NILAKH
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Jul 2017
- Promised completion30 Apr 2027
- Revised completionRevised to 30 Apr 2027 (originally 30 Apr 2019)
- Buildings1 building record
- Documents filed99 files
Current status
Figures as on 12 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GOPAL KRISHNA | NA | 22 | 20 | 54 | 0 | 54 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 0%.
GOPAL KRISHNA: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed100
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ADITYA BIRLA HOUSING FINANCE LTD. | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GOPAL KRISHNA | NA | Rs 25.00 cr | Rs 25.00 cr |
| - | NA | Rs 25.00 cr | Rs 25.00 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJESH RADHAKRISHAN CHANDA |
| Engineer | V K JAIN |
| Chartered Accountant | RAMESH D KATHIRIA |
| Partner | Role in project |
|---|---|
| SONAL DEV-CON PVT LTD | - |
Extensions applied for7
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to the activities of the concerned department has been in slow mode for the last several months and we are hopeful that the Occupancy Certificate would be issued sooner than later.
Reason as filed by the promoterThat we have received the virtual completion certificate from the Architect of our building on 25/01/2019 and also obtained various NOC's such as NOC for Property Tax, Health NOC, License for Lift, approval for drainage connection, etc. and after obtaining all the NOC's from the concern authorities will apply for the Occupancy Certificate which may take 3 to 4 months hence seeking extension.
Reason as filed by the promoterAlthough we have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to prolong lockdown on account of COVID-19 and the activities of the concern department has been in slow mode for the last 8 months and the promoters are hopeful that the Occupancy Certificate would be issued sooner than later.
Reason as filed by the promoterWE HAVE COMPLETED THE 100% WORK OF THE BUILDING PROJECT AS PER THE PLANS APPROVED AND OBTAINED ALL THE CLEARANCES EXCEPT AVIATION NOC AND THEREFORE THE OCCUPANCY CERTIFICATE HAS NOT BEEN GRANTED BY THE MUNICIPAL CORPORATION AND THE SAME MAY BE RECEIVED AT ANY POINT OF TIME. IT IS THEREFORE HUMBLE PRAYAED THAT EXTENSION MAY BE GRANTED.
Reason as filed by the promoterWe have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.
Reason as filed by the promoterWe have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.
Reason as filed by the promoterWe have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2027
Documents filed99
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: FORM 2A - GOPAL KRISHNA - 2025 - 2026.pdf | 12 May 2026 |
| Form 5 (FY 2025-2026)File: FORM 5 - GOPAL KRISHNA - 2025-2026.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: FORM 1 - GOPAL KRISHNA - 31-03-2026.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 - GOPAL KRISHNA - 31-03-2026.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 - GOPAL KRISHNA - 31-03-2026.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 - GOPAL KRISHNA - 31-12-2025.pdf | 8 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 - GOPAL KRISHNA - 31-12-2025.pdf | 8 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 - GOPAL KRISHNA - 31-12-2025.pdf | 8 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 - GOPAL KRISHNA - 30-09-2025.pdf | 7 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 - GOPAL KRISHNA - 30-09-2025.pdf | 7 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 - GOPAL KRISHNA - 30-09-2025.pdf | 7 Apr 2026 |
| Form 1File: FORM 1 - 30-06-2025.pdf | 4 Oct 2025 |
| Form 2File: FORM 2 - 30-06-2025.pdf | 4 Oct 2025 |
| Form 3File: FORM 3 - 30-06-2025.pdf | 4 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 30-06-2025.pdf | 4 Oct 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 - GOPAL KRISHNA - 2024 - 2025.pdf | 7 Jun 2025 |
| Form 1File: FORM 1 - 31-03-2025.pdf | 31 May 2025 |
| Form 2File: FORM 2 - 31-03-2025.pdf | 31 May 2025 |
| Form 3File: FORM 3 - 31-03-2025.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 31-03-25.pdf | 31 May 2025 |
| Form 1File: FORM 1 - 31-12-2024.pdf | 31 May 2025 |
| Form 2File: FORM 2 - 31-12-2024.pdf | 31 May 2025 |
| Form 3File: FORM 3 - 31-12-2024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 31-12-24.pdf | 31 May 2025 |
| Form 1File: FORM 1 - 30-09-2024.pdf | 31 May 2025 |
| Form 2File: FORM 2 - 30-09-2024.pdf | 31 May 2025 |
| Form 3File: FORM 3 - 30-09-2024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 30-09-24.pdf | 31 May 2025 |
| Form 1File: FORM 1 - 30-06-2024.pdf | 31 May 2025 |
| Form 2File: FORM 2 - 30-06-2024.pdf | 31 May 2025 |
| Form 3File: FORM 3 - 30-06-2024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 30-06-24.pdf | 31 May 2025 |
| Declaration in FORM BFile: FORM B - GOPAL KRISHNA.pdf | 18 May 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY - GOPAL KRISHNA.pdf | 18 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22-23.pdf | 18 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form, 1 Q 1.pdf | 16 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form, 1 Q 2.pdf | 16 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form, 1 Q 3.pdf | 16 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form, 1 Q 4.pdf | 16 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: from 2 A.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: form 3 Q-1_compressed.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: form 3 Q-2_compressed.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: form 3 Q-3_compressed.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: form 3 Q-4_compressed.pdf | 15 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5.pdf | 15 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from 2 10 2023.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 7 2023.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 10 2023.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 1 2024.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 4 2024.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 1 2024.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 1 2024.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: from 2 A.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - 2022-23 - SONAL DEV CON.pdf | 19 Aug 2023 |
| Certificates of CA (Form 3)File: CA CERTFICATE - SONAL.pdf | 19 Aug 2023 |
| Declaration in FORM BFile: FORM B - GOPAL KRISHNA.pdf | 1 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf | 28 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 31-03-2023.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-03-2018.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-03-2019.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-03-2020.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-03-2021.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 31-03-2022.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 30-04-2023.pdf | 17 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY - GOPAL KRISHNA.pdf | 2 Jun 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200238686455_For_Asset_Based_Search_02_06_2022_10_56_56_739.pdf | 2 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - GOPAL KRISHNA - 19-20.pdf | 26 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - GOPAL KRISHNA - 20-21.pdf | 26 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - 20 - 21.pdf | 21 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - 2021.pdf | 21 Apr 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf | 8 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf | 8 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - 2018 - 2019.pdf | 8 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - 2019 - 2020.pdf | 8 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - 2020.pdf | 8 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - GOPAL KRISHNA.pdf | 11 Nov 2020 |
| Certificates of CA (Form 5)File: FORM 5 - GOPAL KRISHNA.pdf | 24 Apr 2019 |
| Copy of the legal title reportFile: title certificate Gopal Krishna.pdf | 26 Mar 2019 |
| Details of encumbrancesFile: LETTER OF ENCUMBRANCES.pdf | 26 Mar 2019 |
| Declaration in FORM BFile: FORM B - GOPAL KRISHNA.pdf | 26 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 99 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GOPAL KRISHNA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Agroli Pond7,600+ in Thane
Filed coordinates, straight-line distance. 73 registered projects within 2 km.
REGENCY SQUARE
REGENCY INFRABUILD LLP
NMS MIDAS
DHARTI DHAN REALTY
AAKAR CELESTIAL
Aakar Infratech
PRIYANKA AVENUE
PRIYANKA REGENCY LLP
AAKAR 88
Aakar Signature Co.
VIVA COMPLEX
PURAB ESTATES PVT. LTD.
See every Thane project, with the district possession charts
Builder: SONAL DEV-CON PVT LTD
SONAL DEV-CON PVT LTD has 3 registrations on MahaRERA, including YOGI KRISHNA and GOPAL KRISHNA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if GOPAL KRISHNA is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOPAL KRISHNA?
The registered promoter entity is SONAL DEV-CON PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOPAL KRISHNA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GOPAL KRISHNA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOPAL KRISHNA?
The professionals named in the filing: Architect: RAJESH RADHAKRISHAN CHANDA; Engineer: V K JAIN; Chartered Accountant: RAMESH D KATHIRIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOPAL KRISHNA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback