Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 35 documents Report an error

GOOD EARTH MEDLEY is a Residential/Group Housing project by GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/181210/002213 on 10 Dec 2018. Possession is promised by 31 Dec 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameGOOD EARTH MEDLEY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/181210/002213
  • ReraGenie IDRG-KA-79419

Builder

  • NameGOOD EARTH ECO COMMUNITIES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45209KA2018PTC113216
  • Authorized SignatoryPARTHASARATHY SAMPATHKUMAR
  • DirectorsSTANLEY GEORGE KUDAKKACHIRA, JEETH KATTUNILAM IYPE
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2018First promiseMar 2022Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Dec 2018
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 31 Mar 2022)
  • Buildings2 building records
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-1---79079
BLOCK-2---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes-
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,849 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 78.55 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJayakumar K S
EngineerVenkatarama Reddy B V

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2022 → Dec 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/181210/002213 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: GE ECO COMMUNITIES PVT LTD_CERTIFICATE OF INCORPORATION.PDF-
Medley Plan Sanction Letter_Commencement Letter-
Site Plan-
Floorwise Plan-
Good Earth Eco Communities P L MEDLEY Draft ATS-
Good Earth Eco Communities P L MEDLEY Draft ATS-
Sale Deed-
Approved Section Plan_Medley-
Approved Development Plan_Medley-
MEDLEY Draft Allotment Letter-
Medley Brochure-
Medley Project Specifications-
EC-
Medley Khatha Extract_Form 9 & 11-
Conversion order-
Conversion order-
Conversion order-
Medley_KSPCB Intimation BDA-
SEIAA Noc-
Survey Sketch_ Sy Nos 222,223,226,227 Medley Land-
Survey Sketch_ Sy Nos 222,223,226,227 Medley Land-
Conversion Order Sy Nos 222,223,193,226 & 227-
MEDLEY FORM-B-
Prospectus/BrochureFile: Medley_Brochure_2019.pdf-
Advertisement Copy 1File: Medley_Brochure_2019.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_181210_002213.xlsx-
Loan raised documentFile: No Due Certificate from Bank.pdf-
Occupancy CertificateFile: OC - Medley - Dated 14-03-2022.pdf-
Consent for operation issued by KSPCBFile: KSPCB - CFO - Medley.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Medley_BESCOM NOC_24-11-2018.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Panchayath Water NOC_Sy No 222 223 226 & 227_19-07-2018.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate_Form 5_Medley Completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC Medley.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit Cum Declaration_Project Completion_Medley.pdf-
Engineer CertificateFile: Engineers Certificate_Form 6_Meldey Completion.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GOOD EARTH MEDLEY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGOOD EARTH MEDLEYLapsed / revoked 1Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED

GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED has 3 registrations on RERA Karnataka, including GOOD EARTH OCTAVE and GOOD EARTH CADENCE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GOOD EARTH MEDLEY is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GOOD EARTH MEDLEY?

The registered promoter entity is GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED, a company as per the filing. Its CIN U45209KA2018PTC113216 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GOOD EARTH MEDLEY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GOOD EARTH MEDLEY?

The professionals named in the filing: Architect: Jayakumar K S; Engineer: Venkatarama Reddy B V. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOOD EARTH MEDLEY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOOD EARTH MEDLEY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOOD EARTH MEDLEY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.