Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Feb 2027Possession promisedmoved 11 months from the original
184 of 225Construction stages doneacross 25 buildings; furthest along: Installation of lifts, 95%
11 of 82Units unsoldnot recorded sold or booked
Jump to the 57 documents Report an error

GOKULDHAM PREMIUM BUNGLOWS is a Residential/Group Housing project by GURUJI GOKULDHAM PREMIUM in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA12720/EX1/200526/280227 on 21 Dec 2023. Possession is promised by 28 Feb 2027. The completion date has moved by 11 months from the original filing. 71 of the 82 units on this registration are recorded sold or booked, and 184 of 225 construction stages are filed complete.

At a glance

Project

  • NameGOKULDHAM PREMIUM BUNGLOWS
  • TypeResidential/Group Housing
  • Location
    • GOKULDHAM PREMIUM BUNGLOWS
    • B/H CIRCUIT HOUSE
    • NEAR GAYATRI TEMPLE
    • MANSA
    • GANDHINAGAR - 382845
    • MANSA
    • Gandhinagar
    • 382845
  • Pincode382845
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA12720/EX1/200526/280227
  • ReraGenie IDRG-GJ-24208

Builder

  • NameGURUJI GOKULDHAM PREMIUM
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →
  • Past their filed date1

Key dates

this monthRegisteredDec 2023First promiseMar 2026Revised toFeb 2027

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2027
  • Registered on21 Dec 2023
  • Promised completion28 Feb 2027
  • Revised completionRevised to 28 Feb 2027 (originally 31 Mar 2026)
  • Buildings25 building records
  • Documents filed57 files

Current status

87%71 of 82 units booked
99.0%Of the estimated cost spent so far

Figures as on 11 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
42,46,48,53,55,59---606
5,72,16---303
79---101
11,31,66---303
25---101
63,69,75,71---404
73,57---202
77---101
45---101
36---101
1,3,4,7,9,13,15,17,18,19,20,21---12012
22,23,24,27,29,34,35,37,38,39---10010
40,2,6,26,10,12,14---707
30,32,33,52---404
68---101
43,44---202
47---101
49,50---202
54---101
56---101
60,61,62,64,65,67,76,78,80,82---10010
83,58---202
8,28,70,74---404
81---101
41---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 25 buildings; the table lists the first 20.

184 of 225 construction stages are filed complete across 25 buildings. The stage furthest along is Installation of lifts, at 95%.

42,46,48,53,55,5988%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
5,72,1688%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
7989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
11,31,6689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
2589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
63,69,75,7188%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
73,5789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
7789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
4589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
3689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
1,3,4,7,9,13,15,17,18,19,20,2188%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
22,23,24,27,29,34,35,37,38,3988%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
40,2,6,26,10,12,1488%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
30,32,33,5288%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
6888%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
43,4488%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
4788%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
49,5088%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
5488%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
5688%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes95%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes95%
Landscaping and tree plantingYes95%
Street lightingYes95%
Community buildingsYes95%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes95%
Water conservation, rain water harvestingYes95%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes95%
Emergency evacuationNoNot applicable
Use of renewable energyYes95%
SecurityYes95%
Letter boxYes95%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,912 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 17.65 cr
Cost incurredRs 17.48 cr
Spent of the estimate99.05%
BuildingWingEstimatedIncurred
1,3,4,7,9,13,15,17,18,19,20,21NARs 2.93 crRs 2.91 cr
22,23,24,27,29,34,35,37,38,39NARs 2.44 crRs 2.42 cr
60,61,62,64,65,67,76,78,80,82NARs 1.88 crRs 1.87 cr
40,2,6,26,10,12,14NARs 1.71 crRs 1.69 cr
42,46,48,53,55,59NARs 1.13 crRs 1.11 cr
30,32,33,52NARs 92.01 lakhRs 90.01 lakh
8,28,70,74NARs 86.42 lakhRs 86.42 lakh
63,69,75,71NARs 75.26 lakhRs 74.26 lakh
5,72,16NARs 67.81 lakhRs 66.71 lakh
11,31,66NARs 67.61 lakhRs 67.61 lakh
43,44NARs 37.63 lakhRs 36.13 lakh
49,50NARs 37.63 lakhRs 36.53 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhaumikkumar Chandravadanbhai Donga
EngineerTRUPESH MAHESHBHAI MACHHI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA12720/EX1/200526/280227Applied Mar 2026; approved May 2026

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA12720/EX1/200526/280227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)11 May 2026
Architect's certificate (Form 1)2 May 2026
Engineer's certificate (Form 2)2 May 2026
Engineer's certificate annexure2 May 2026
Site photograph, 42,46,48,53,55,591 May 2026
Site photograph, 5,72,161 May 2026
Site photograph, 791 May 2026
Site photograph, 11,31,661 May 2026
Site photograph, 251 May 2026
Site photograph, 63,69,75,711 May 2026
Site photograph, 73,571 May 2026
Site photograph, 771 May 2026
Site photograph, 451 May 2026
Site photograph, 361 May 2026
Site photograph, 1,3,4,7,9,13,15,17,18,19,20,211 May 2026
Site photograph, 22,23,24,27,29,34,35,37,38,391 May 2026
Site photograph, 40,2,6,26,10,12,141 May 2026
Site photograph, 30,32,33,521 May 2026
Site photograph, 681 May 2026
Site photograph, 43,441 May 2026
Site photograph, 471 May 2026
Site photograph, 49,501 May 2026
Site photograph, 541 May 2026
Site photograph, 561 May 2026
Site photograph, 60,61,62,64,65,67,76,78,80,821 May 2026
Site photograph, 83,581 May 2026
Site photograph, 8,28,70,741 May 2026
Site photograph, 811 May 2026
Site photograph, 411 May 2026
RERA registration certificate21 Dec 2023
Extension certificate-
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

87%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 11 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep GOKULDHAM PREMIUM BUNGLOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MANSA1,600+ in Gandhinagar

2 kmGOKULDHAM PREMIUM BUNGLOOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: GURUJI GOKULDHAM PREMIUM

GURUJI GOKULDHAM PREMIUM has 2 registrations on GujRERA, including GOKULDHAM PREMIUM PLOTS and GOKULDHAM PREMIUM BUNGLOWS. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if GOKULDHAM PREMIUM BUNGLOWS is delayed beyond 28 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of GOKULDHAM PREMIUM BUNGLOWS?

The registered promoter entity is GURUJI GOKULDHAM PREMIUM, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in GOKULDHAM PREMIUM BUNGLOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GOKULDHAM PREMIUM BUNGLOWS?

The professionals named in the filing: Architect: Bhaumikkumar Chandravadanbhai Donga; Engineer: TRUPESH MAHESHBHAI MACHHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOKULDHAM PREMIUM BUNGLOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOKULDHAM PREMIUM BUNGLOWS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOKULDHAM PREMIUM BUNGLOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.