Home / Browse projects / Bengaluru Rural, Karnataka / GODREJ FLORENNE PHASE II
GODREJ FLORENNE PHASE II
RG-KA-74073 · RERA PRM/KA/RERA/1250/304/PR/150926/008943 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
GODREJ FLORENNE PHASE II is a Residential/Group Housing project by Godrej Properties Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/150926/008943 on 15 Sep 2026. Possession is promised by 30 Sep 2031. 5 of the 68 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.
At a glance
Project
- NameGODREJ FLORENNE PHASE II
- TypeResidential/Group Housing
- Location
- Hosakote
- Bengaluru Rural
- 560117
- Pincode560117
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/304/PR/150926/008943
- ReraGenie IDRG-KA-74073
Builder
- NameGodrej Properties Limited
- Entity typeCompany
- CINL74120MH1985PLC035308
- GSTIN29AAACG3995M1ZX
- Authorized SignatoryAbishek Kalro
- Md & CeoGAURAV PANDEY
- DirectorsGAURAV PANDEY, PIROJSHA ADI GODREJ, NADIR B GODREJ, SUTAPA BANERJEE, DR INDU BHUSHAN, JAYASHREE VAIDHYANATHAN, SUMEET NARANG
- Project HeadAbhishek Kalro
- Other registrations16 more →
- Declared earlier projects8 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Sep 2026
- Promised completion30 Sep 2031
- Revised completionNone
- Buildings4 building records
- Documents filed396 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 6 | 0 | 6 |
| 4 | - | - | - | 22 | 0 | 22 |
| 5 | - | - | - | 20 | 0 | 20 |
| 6 | - | - | - | 20 | 0 | 20 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 0% |
| Foundation footing work | 0% |
| Upto Plinth Level | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 13% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | No | Not applicable |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership44
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
| Godrej Properties Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 193.52 cr | Rs 4.01 cr |
| On-site expenditure-Consultants Fees | Rs 40.50 cr | Rs 2.77 cr |
| On-site expenditure-Site Overhead | Rs 10.25 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shreyas M |
| Engineer | Dinesha Shetty |
| Chartered Accountant | Bhavesh D Shah |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed396
As listed on the registration, under the names the promoter filed them with; the newest 80 of 396 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/150926/008943 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Godrej Florenne Ph 2- FINAL.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect - Godrej Florenne - 30-Sep-26 - Ph2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Godrej Florenne-Ph2.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Declaration for Non-applicability of Floorewise Inventory details.File: No of Floors Declaration-phase 2.pdf | 11 Sep 2026 |
| Final Agreement for Sale -11-09-2026File: Final Agreement for Sale -11-09-2026-Phase II.pdf | 11 Sep 2026 |
| Phase & Unitwise Area details phase-2File: phase & Unitwise Area details phase-2.pdf | 11 Sep 2026 |
| Queries ResponseFile: Queries Response.pdf | 10 Sep 2026 |
| 121/1-ECFile: 121-1-EC.pdf | 10 Sep 2026 |
| 121/2-ECFile: 121-2-EC.pdf | 10 Sep 2026 |
| 121/3-ECFile: 121-3-EC.pdf | 10 Sep 2026 |
| 121/4-ECFile: 121-4-EC.pdf | 10 Sep 2026 |
| 121/5-ECFile: 121-5-EC.pdf | 10 Sep 2026 |
| 121/6-ECFile: 121-6-EC.pdf | 10 Sep 2026 |
| 121/7-ECFile: 121-7-EC.pdf | 10 Sep 2026 |
| 121/8-ECFile: 121-8-EC.pdf | 10 Sep 2026 |
| SY No-7/1- Advocate Search ReportFile: Signed ROT - Sy No 7-1 - 20082026.pdf | 10 Sep 2026 |
| Sy No-53/2- Advocate Search ReportFile: Signed ROT - Sy No 53-2 - 20082026.pdf | 10 Sep 2026 |
| Sy No-55/3- Advocate Search ReportFile: Signed ROT - Sy No 55-3 - 20082026.pdf | 10 Sep 2026 |
| Sy No-116- Advocate Search ReportFile: Signed ROT - Sy No 116.pdf | 10 Sep 2026 |
| Sy No-117/7 to 117/10- Advocate Search ReportFile: Signed ROT - Sy No 117-7 to 117-10.pdf | 10 Sep 2026 |
| Sy No-118- Advocate Search ReportFile: Signed ROT - Sy No 118.pdf | 10 Sep 2026 |
| Sy No-120 Series- Advocate Search ReportFile: Signed ROT - Sy No 120 Series.pdf | 10 Sep 2026 |
| Sy No-121 Series-Part1- Advocate Search ReportFile: Signed ROT - Sy No 121 Part 1-.pdf | 10 Sep 2026 |
| Sy No-121 Series-Part2- Advocate Search ReportFile: Signed ROT - Sy No 121 part 2.pdf | 10 Sep 2026 |
| Sy No-122 Series-Part1- Advocate Search ReportFile: Signed ROT - Sy No 122 Part 1.pdf | 10 Sep 2026 |
| Sy No-122 Series-Part2- Advocate Search ReportFile: Signed ROT - Sy No 122 part 2.pdf | 10 Sep 2026 |
| Sy No-123 of 1,2 & 4 Series- Advocate Search ReportFile: Signed ROT - Sy No 123 of 1, 3 and 4.pdf | 10 Sep 2026 |
| Floor-wise area statementFile: Floor wise area ST-Phase II.pdf | 10 Sep 2026 |
| Phasewise area statementFile: Phasewise Unit Area St-Phase II.pdf | 10 Sep 2026 |
| Updated Project SpecificationsFile: Project specification-Phase II.pdf | 10 Sep 2026 |
| Updated Agreement for SaleFile: Agreement for Sale-Phase II.pdf | 10 Sep 2026 |
| Phasewise Demarcation of land in approved PlanFile: PHASEWISE DEMARCATION.pdf | 10 Sep 2026 |
| Building LicenceFile: Building License.pdf | 10 Sep 2026 |
| ADLR SketchFile: ADRL SKetch ( ).pdf | 10 Sep 2026 |
| CDP extractFile: CDP Extract.pdf | 10 Sep 2026 |
| Phasewise DeclarationFile: Phasewise Declaration.pdf | 10 Sep 2026 |
| RTC, survey 116/4 | - |
| Mutation, survey 116/4 | - |
| Encumbrance Certificate, survey 116/4 | - |
| Conversion/Alienation Order, survey 116/4 | - |
| Sale/Title/Gift Deed, survey 116/4 | - |
| Khatha, survey 116/4 | - |
| RTC, survey 116/5 | - |
| Mutation, survey 116/5 | - |
| Encumbrance Certificate, survey 116/5 | - |
| Conversion/Alienation Order, survey 116/5 | - |
| Sale/Title/Gift Deed, survey 116/5 | - |
| Khatha, survey 116/5 | - |
| RTC, survey 116/6 | - |
| Mutation, survey 116/6 | - |
| Encumbrance Certificate, survey 116/6 | - |
| Conversion/Alienation Order, survey 116/6 | - |
| Sale/Title/Gift Deed, survey 116/6 | - |
| Khatha, survey 116/6 | - |
| RTC, survey 116/7 | - |
| Mutation, survey 116/7 | - |
| Encumbrance Certificate, survey 116/7 | - |
| Conversion/Alienation Order, survey 116/7 | - |
| Sale/Title/Gift Deed, survey 116/7 | - |
| Khatha, survey 116/7 | - |
| RTC, survey 117/7 | - |
| Mutation, survey 117/7 | - |
| Encumbrance Certificate, survey 117/7 | - |
| Conversion/Alienation Order, survey 117/7 | - |
| Sale/Title/Gift Deed, survey 117/7 | - |
| Khatha, survey 117/7 | - |
| RTC, survey 117/8 | - |
| Mutation, survey 117/8 | - |
| Encumbrance Certificate, survey 117/8 | - |
| Conversion/Alienation Order, survey 117/8 | - |
| Sale/Title/Gift Deed, survey 117/8 | - |
| Khatha, survey 117/8 | - |
| RTC, survey 117/9 | - |
| Mutation, survey 117/9 | - |
| Encumbrance Certificate, survey 117/9 | - |
| Conversion/Alienation Order, survey 117/9 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep GODREJ FLORENNE PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Filed coordinates, straight-line distance. 9 registered projects within 2 km.
AR BELLE VIE PHASE 1
S & S PROPERTIES and JMD Developers
UNITED SUVARNA HOMES
UNITED SUVARNA HOMES
GODREJ FLORENNE
Godrej Properties Limited
GODREJ FLORENNE PHASE III
Godrej Properties Limited
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Ozone Urbana
Ozone Urbana Infra Developers Pvt Ltd
See every Bengaluru Rural project, with the district possession charts
Builder: Godrej Properties Limited
Godrej Properties Limited has 17 registrations on RERA Karnataka, including Godrej Woodland Phase 2 and GODREJ PARKSHIRE. Its filings declare 8 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if GODREJ FLORENNE PHASE II is delayed beyond 30 Sep 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of GODREJ FLORENNE PHASE II?
The registered promoter entity is Godrej Properties Limited, a company as per the filing. Its CIN L74120MH1985PLC035308 and GSTIN 29AAACG3995M1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in GODREJ FLORENNE PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at GODREJ FLORENNE PHASE II?
The professionals named in the filing: Architect: Shreyas M; Engineer: Dinesha Shetty; Chartered Accountant: Bhavesh D Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GODREJ FLORENNE PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback