ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / GODREJ COUNTRY ESTATE

Completed No litigation declared Plotted project

GODREJ COUNTRY ESTATE

By GODREJ PROJECTS DEVELOPMENT LIMITED

RG-MH-45151 · RERA P99000048245 · Last updated on MahaRERA portal: 18 Oct 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Apr 2026Possession promisedregistration recorded completed
362 of 442Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

GODREJ COUNTRY ESTATE is a Plotted project by GODREJ PROJECTS DEVELOPMENT LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000048245 on 19 Dec 2022. The registration is recorded completed; possession was promised by 30 Apr 2026. 80 of the 442 units on this registration are recorded sold or booked. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGODREJ COUNTRY ESTATE
  • TypePlotted
  • Location
    • MHASROLI KURNZE ROAD
    • KURNZE
    • kurnzhe
    • Vikramgad
    • Palghar
    • 401403
  • Pincode401403
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000048245
  • ReraGenie IDRG-MH-45151

Builder

  • NameGODREJ PROJECTS DEVELOPMENT LIMITED
  • Entity typeCompany
  • CINU70102MH2010PLC210227
  • GSTIN27AAECG0366L1ZG
  • Associate Vice President Region Head MMR TwoPriyamvada Navet
  • Other registrations5 more →
  • Completed5 of 6
  • Declared earlier projects16 →

Key dates

this monthRegisteredDec 2022PromisedApr 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Dec 2022
  • Promised completion30 Apr 2026
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed85 files

Current status

18%80 of 442 units booked
19.9%Work done, per cost certificate

Figures as on 18 Oct 2024, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities16

As on 18 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes55%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
Common facilities in Amenity areasYes15%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area204,265 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityCollector Office, Palghar
Permissible FSI173400.83

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJEEVAN PRAKASH BUILDING GROUND FLOOR SIR PHIROZSHAH MEHTA ROAD FORT MUMBAI 400001
Estimated costRs 138.29 cr
Cost incurredRs 27.59 cr
Work done19.95%
BuildingWingEstimatedIncurred
-NARs 138.29 crRs 27.59 cr

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
GODREJ PROJECTS DEVELOPMENT LIMITED-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000395453Gopal Krishna MundhraGodrej Projects Development Ltd02/05/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Apr 2024

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged_organized_compressed (1).pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged_organized_compressed (1).pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged_organized_compressed (1).pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Country Estate Form 5 FY 2023 24.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Country Estate Form 5 FY 2023 24.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Country Estate Form 5 FY 2023 24.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Manor Form 1 Q1 '25.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Manor ENGG CERTI Q1.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2AFY 23pdf.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Sold Manor (1).pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q1 CA Certificate.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A fy 24.pdf1 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Deed of conveyance - Godrej Country Estate - for sale as per old NA order - for 21 custome25 Apr 2024
Proforma of Agreement for saleFile: Deed of conveyance Godrej Country Estate 1542024 for sale as per old NA order revised.pdf25 Apr 2024
Proforma of Agreement for saleFile: Deed of conveyance Godrej Country Estate 15042024 for sale as per revsied NA order 002 rev25 Apr 2024
Proforma of Agreement for saleFile: Deed of conveyance - Godrej Country Estate - for sale as per old NA order - for 21 custome25 Apr 2024
Architect’s Certificate on Completion of Project (Form 4)File: Signed Form 4.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Godrej Project Development Ltd (2).pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory SOld Manor.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Manor Q4 CA certificate_compressed.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej - CE- Rera Engg Q4.pdf15 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf15 Apr 2024
Other - LegalFile: 05- EXT_Liasoning_Manor, Palghar, Godrej Country Estate.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Project Development Ltd.pdf31 Mar 2024
Home Buyer /Allottee Grievance Redressal CellFile: Home Buyer Allottee Grievance Redressal Cell Godrej Country Estate.pdf26 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Manor.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE compressed.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate - manor compressed (1).pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GCE Engineers Certi Q1 FY24.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Manor - Form 3 Q1.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Godrej country estate.pdf18 Oct 2023
Building plan approval or NA orderFile: GCE Combined NA Layout Approval.pdf11 Oct 2023
Layout approvalFile: GCE Combined Approved Layout Plan Part 1.pdf11 Oct 2023
Layout approvalFile: GCE Combined Approved Layout Plan Part 2.pdf11 Oct 2023
Copy of Layout Approval (in case of layout)File: GCE Combined Approved Layout Plan Part 1.pdf11 Oct 2023
Copy of Layout Approval (in case of layout)File: GCE Combined Approved Layout Plan Part 2.pdf11 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: GCE Combined NA Layout Approval.pdf11 Oct 2023
Proforma of Agreement for saleFile: GCE Updated AFS.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate3103.pdf8 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate3103.pdf8 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Inventory Status3103.pdf8 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate3103.pdf8 Jun 2023
Building plan approval or NA orderFile: RERA DOCUMENT-13-12-2022.pdf13 Dec 2022
Building plan approval or NA orderFile: Area Clarification Letter.pdf13 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Area Clarification Letter.pdf13 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: RERA DOCUMENT-13-12-2022.pdf13 Dec 2022
Other - TechnicalFile: RERA DOCUMENT-13-12-2022.pdf13 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Manor_Architects Certificate.pdf7 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Manor_Engineers Certificate.pdf7 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Revised CA Certificate.pdf7 Dec 2022
Other - TechnicalFile: Area Clarification Letter.pdf7 Dec 2022
Other - TechnicalFile: Manor_RERA_Deed Of Conveyance_Compressed.pdf7 Dec 2022
Layout approvalFile: NA APPROVED LAYOUT PARCEL A compressed.pdf28 Nov 2022
Layout approvalFile: NA APPROVED LAYOUT PARCEL B.pdf28 Nov 2022
Building plan approval or NA orderFile: NA ORDER PARCEL A.pdf28 Nov 2022
Building plan approval or NA orderFile: NA ORDER PARCEL B.pdf28 Nov 2022
PAN CardFile: GPDL New PAN Card.pdf28 Nov 2022
Copy of the legal title reportFile: Manor Legal Title Report.pdf28 Nov 2022
Details of encumbrances concerned to FinanceFile: legal - NEC.pdf28 Nov 2022
Details of encumbrances concerned to LegalFile: legal - NEC.pdf28 Nov 2022
Copy of Layout Approval (in case of layout)File: NA APPROVED LAYOUT PARCEL A compressed.pdf28 Nov 2022
Copy of Layout Approval (in case of layout)File: NA APPROVED LAYOUT PARCEL B.pdf28 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER PARCEL A.pdf28 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER PARCEL B.pdf28 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER PARCEL A.pdf28 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER PARCEL B.pdf28 Nov 2022
Declaration about Commencement CertificateFile: Declaration of CC.pdf28 Nov 2022
Declaration in FORM BFile: Form B.pdf28 Nov 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf28 Nov 2022
Proforma of Allotment letterFile: Allotment Letter (Manor) (Upload).pdf28 Nov 2022

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
GODREJ SUMMITSECTOR 104 VILLAGE GURUGRAM HARYANA1,177CompletedSep 2018Late, Dec 2018
GODREJ BKCG BLOCK BANDRA KURLA COMPLEX BANDRA EAST MUMBAI 40005130CompletedJun 2016May 2016
GODREJ PLATINUMINTERNATIONAL AIRPORT ROAD HEBBAL BENGALURU KARNATAKA 560024108CompletedMar 2016Late, Jan 2017
GODREJ GENESISPLOT NO X1 9 TO 14 BLOCK EB AND GP SECTOR V SALT LAKE KOLKATA 700091125CompletedSep 2015Late, Dec 2015

How this compares with Palghar

18%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GODREJ COUNTRY ESTATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KURNZE3,200+ in Palghar

Builder: GODREJ PROJECTS DEVELOPMENT LIMITED

Godrej Projects Development Limited has 6 registrations on MahaRERA, including Godrej RKS and GODREJ COUNTRY ESTATE. Its filings disclose 16 earlier MahaRERA projects: declares 10 of 16 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if GODREJ COUNTRY ESTATE is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GODREJ COUNTRY ESTATE?

The registered promoter entity is GODREJ PROJECTS DEVELOPMENT LIMITED, a company as per the filing. Its CIN U70102MH2010PLC210227 and GSTIN 27AAECG0366L1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GODREJ COUNTRY ESTATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GODREJ COUNTRY ESTATE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GODREJ COUNTRY ESTATE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in GODREJ COUNTRY ESTATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GODREJ COUNTRY ESTATE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GODREJ COUNTRY ESTATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.