ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / GMC FIRST GATES

Registration approved No litigation declared Plotted Development project

GMC FIRST GATES

By M/s GMC LANDMARKS LLP

RG-KA-39767 · RERA PRM/KA/RERA/1251/308/PR/080925/008071 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2030Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 138 documents Report an error

GMC FIRST GATES is a Plotted Development project by M/s GMC LANDMARKS LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/080925/008071 on 8 Sep 2025. Possession is promised by 31 Mar 2030.

At a glance

Project

  • NameGMC FIRST GATES
  • TypePlotted Development
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/080925/008071
  • ReraGenie IDRG-KA-39767

Builder

  • NameM/s GMC LANDMARKS LLP
  • Entity typePartnership Firm
  • GSTIN29ABBFG7724R1ZN
  • Authorized SignatoryKUMARA GIRI REDDY KONDA

Key dates

this monthRegisteredSep 2025PromisedMar 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Sep 2025
  • Promised completion31 Mar 2030
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed138 files

Current status

26.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners7
LandownerVillageDistrict
KUMARA GIRI REDDY KONDA--
KUMARA GIRI REDDY KONDA--
KUMARA GIRI REDDY KONDA--
KUMARA GIRI REDDY KONDA--
KUMARA GIRI REDDY KONDA--
KUMARA GIRI REDDY KONDA--
KUMARA GIRI REDDY KONDA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.29 cr
Cost incurredRs 59.56 lakh
Spent of the estimate26.02%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 1.60 crRs 16.73 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 30.50 lakhRs 25,000
On-site expenditure-Consultants FeesRs 10.00 lakhRs 20,000
Payment of PremiumsRs 10.00 lakh-
On-site expenditure-Salaries of workersRs 6.00 lakhRs 12.23 lakh
On-site expenditure-Site OverheadRs 5.00 lakhRs 29.69 lakh
Any OtherRs 5.00 lakh-
Payment of feesRs 2.50 lakh-
Payment of taxes-Rs 45,624

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerMANDHADI VENKAT RAMANA REDDY
Chartered AccountantSesha Chalapathi Janne

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed138

As listed on the registration, under the names the promoter filed them with; the newest 80 of 138 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/080925/008071 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA CERTIFICATE Q2 26.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGINEER CERTIFICATE Q2 26 27.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA CERTIFICATE .pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGINEER CERTIFICATE.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
MR 34/1,3,4,6,7File: MR 34 1 3 4 6 7.pdf4 Sep 2025
MR 34/5File: MR 34 5 .pdf4 Sep 2025
MR 34/8File: MR 34 8.pdf4 Sep 2025
EC 34/1File: 34 1 EC.pdf4 Sep 2025
EC 34/3File: 34 3 EC.pdf4 Sep 2025
EC 34/4File: 34 4 EC.pdf4 Sep 2025
EC 34/5File: 34 5 EC.pdf4 Sep 2025
EC 34/6File: 34 6 EC.pdf4 Sep 2025
EC 34/7File: 34 7 EC.pdf4 Sep 2025
EC 34/8File: 34 8 EC.pdf4 Sep 2025
JDA CLARIFICATIONFile: JDA Clarification.pdf4 Sep 2025
Agreement of SaleFile: Agreement of Sale.pdf4 Sep 2025
BESCOM NOC and Fees ReceiptFile: BESCOM NOC and Fees Receipt .pdf4 Sep 2025
Water NOCFile: Water NOC.pdf4 Sep 2025
RTC, survey 34/1-
Mutation, survey 34/1-
Encumbrance Certificate, survey 34/1-
Conversion/Alienation Order, survey 34/1-
Sale/Title/Gift Deed, survey 34/1-
Khatha, survey 34/1-
RTC, survey 34/3-
Mutation, survey 34/3-
Encumbrance Certificate, survey 34/3-
Conversion/Alienation Order, survey 34/3-
Sale/Title/Gift Deed, survey 34/3-
Khatha, survey 34/3-
RTC, survey 34/4-
Mutation, survey 34/4-
Encumbrance Certificate, survey 34/4-
Conversion/Alienation Order, survey 34/4-
Sale/Title/Gift Deed, survey 34/4-
Khatha, survey 34/4-
RTC, survey 34/5-
Mutation, survey 34/5-
Encumbrance Certificate, survey 34/5-
Conversion/Alienation Order, survey 34/5-
Sale/Title/Gift Deed, survey 34/5-
Khatha, survey 34/5-
RTC, survey 34/6-
Mutation, survey 34/6-
Encumbrance Certificate, survey 34/6-
Conversion/Alienation Order, survey 34/6-
Sale/Title/Gift Deed, survey 34/6-
Khatha, survey 34/6-
RTC, survey 34/7-
Mutation, survey 34/7-
Encumbrance Certificate, survey 34/7-
Conversion/Alienation Order, survey 34/7-
Sale/Title/Gift Deed, survey 34/7-
Khatha, survey 34/7-
RTC, survey 34/8-
Mutation, survey 34/8-
Encumbrance Certificate, survey 34/8-
Conversion/Alienation Order, survey 34/8-
Sale/Title/Gift Deed, survey 34/8-
Khatha, survey 34/8-
Registration CertificateFile: FIRM REGISTRATION CERTIFICATE.jpg-
GST CertificateFile: GST LANDMARKS LLP .pdf-
Partnership DeedFile: PARTNERSHIP DEED.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GMC FIRST GATES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: M/s GMC LANDMARKS LLP

M/s GMC LANDMARKS LLP has 1 registration on RERA Karnataka, including GMC FIRST GATES. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GMC FIRST GATES is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GMC FIRST GATES?

The registered promoter entity is M/s GMC LANDMARKS LLP, a partnership firm as per the filing. Its GSTIN 29ABBFG7724R1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GMC FIRST GATES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GMC FIRST GATES?

The professionals named in the filing: Engineer: MANDHADI VENKAT RAMANA REDDY; Chartered Accountant: Sesha Chalapathi Janne. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GMC FIRST GATES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GMC FIRST GATES. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GMC FIRST GATES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.