Home / Browse projects / Bengaluru Urban, Karnataka / GM GLOBAL TECHIES TOWN TOWER C
GM GLOBAL TECHIES TOWN TOWER C
By M/s.Gulam Mustafa Enterprises Pvt Ltd
RG-KA-93633 · RERA PRM/KA/RERA/1251/308/PR/170928/001289
Source: official RERA Karnataka filing
Red flags
- 112 complaints at RERA Karnataka
- Completion date moved by 21 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
GM GLOBAL TECHIES TOWN TOWER C is a Residential/Group Housing project by M/s.Gulam Mustafa Enterprises Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/170928/001289 on 28 Sep 2017. Possession is promised by 18 May 2023. The completion date has moved by 21 months from the original filing. 112 complaints are on record with the regulator.
At a glance
Project
- NameGM GLOBAL TECHIES TOWN TOWER C
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/308/PR/170928/001289
- ReraGenie IDRG-KA-93633
Builder
- NameM/s.Gulam Mustafa Enterprises Pvt Ltd
- Entity typeCompany
- CINU70100KA1982PTC004720
- Authorized SignatoryMr.M.J.Stephen
- OthersMr.Manoj S Mudakkayil
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on28 Sep 2017
- Promised completion18 May 2023
- Revised completionRevised to 18 May 2023 (originally 18 Aug 2021)
- Buildings1 building record
- Documents filed79 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C | - | - | - | 1416 | 0 | 1416 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | Not applicable |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr.Jayaprakash Narayan |
| Engineer | Mr. B.E. Pruthviraja |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka112
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/190218/0002184 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 18/02/2019 |
| CMP/211113/0008552 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 13/11/2021 |
| CMP/220523/0009507 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 23/05/2022 |
| CMP/220525/0009530 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 25/05/2022 |
| CMP/220525/0009532 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 25/05/2022 |
| CMP/220531/0009550 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 31/05/2022 |
| CMP/220531/0009553 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 31/05/2022 |
| CMP/220601/0009565 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 01/06/2022 |
| CMP/220603/0009583 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 03/06/2022 |
| CMP/220603/0009584 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 03/06/2022 |
| CMP/220606/0009592 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 06/06/2022 |
| CMP/220607/0009598 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 07/06/2022 |
| CMP/220614/0009623 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 14/06/2022 |
| CMP/220624/0009675 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 24/06/2022 |
| CMP/220704/0009715 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 04/07/2022 |
| CMP/220707/0009727 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 07/07/2022 |
| CMP/220713/0009745 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 13/07/2022 |
| CMP/220715/0009753 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 15/07/2022 |
| CMP/220719/0009761 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 19/07/2022 |
| CMP/220719/0009763 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 19/07/2022 |
| CMP/220719/0009766 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 19/07/2022 |
| CMP/220720/0009775 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 20/07/2022 |
| CMP/220720/0009776 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 20/07/2022 |
| CMP/220720/0009780 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 20/07/2022 |
| CMP/220720/0009783 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 20/07/2022 |
| CMP/220722/0009792 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 22/07/2022 |
| CMP/220725/0009810 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 25/07/2022 |
| CMP/220726/0009815 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 26/07/2022 |
| CMP/220726/0009816 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 26/07/2022 |
| CMP/220726/0009817 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 26/07/2022 |
| CMP/220801/0009831 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 01/08/2022 |
| CMP/220811/0009864 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 11/08/2022 |
| CMP/220811/0009877 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 11/08/2022 |
| CMP/220816/0009894 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 16/08/2022 |
| CMP/220816/0009895 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 16/08/2022 |
| CMP/220816/0009898 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 16/08/2022 |
| CMP/220816/0009899 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 16/08/2022 |
| CMP/220816/0009901 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 16/08/2022 |
| CMP/220817/0009905 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 17/08/2022 |
| CMP/220818/0009909 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 18/08/2022 |
| CMP/220818/0009910 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 18/08/2022 |
| CMP/220822/0009928 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 22/08/2022 |
| CMP/220825/0009934 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 25/08/2022 |
| CMP/220829/0009958 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 29/08/2022 |
| CMP/220830/0009961 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 30/08/2022 |
| CMP/220902/0009970 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 02/09/2022 |
| CMP/220902/0009973 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 02/09/2022 |
| CMP/220907/0009982 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 07/09/2022 |
| CMP/220907/0009983 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 07/09/2022 |
| CMP/220907/0009984 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 07/09/2022 |
| CMP/220908/0009987 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 08/09/2022 |
| CMP/220908/0009992 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 08/09/2022 |
| CMP/220908/0009993 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 08/09/2022 |
| CMP/220912/0010004 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 12/09/2022 |
| CMP/220913/0010006 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 13/09/2022 |
| CMP/220914/0010012 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 14/09/2022 |
| CMP/220920/0010033 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 20/09/2022 |
| CMP/220922/0010043 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 22/09/2022 |
| CMP/221029/0010140 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 29/10/2022 |
| CMP/221117/0010354 | - | M/s.Gulam Mustafa Enterprises Pvt Ltd | 17/11/2022 |
Documents filed79
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/170928/001289 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Incorporation certificate GMEP.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: ARC CER of prcentage of completion.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Eng cer for work done ason date_compressed.pdf | - |
| CA Certificate for Funds UtilizationFile: Form-Ex3 Chartered Accountant Certificate-Tower C utilized.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: ARC cer of percentage of completion of development tow c.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Eng cer for pending work_compressed.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form-Ex4 Chartered Accountant Certificate-Tower C funds req for compl_compressed (1).pdf | - |
| AffidavitFile: Form B.pdf | - |
| Latest Encumbrance CertificateFile: EC from 27-09-2022 to 13-10-2022 Sy No 273.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: sold and unsold unit details of GTT TOWER C.pdf | - |
| Document 1File: EC from 27-09-2022 to 13-10-2022 Sy No 28-6.pdf | - |
| Document 2File: EC from 27-09-2022 to 13-10-2022 Sy No 28-3.pdf | - |
| Document 3File: EC from 27-09-2022 to 13-10-2022 Sy No 28-2.pdf | - |
| Document 4File: EC from 27-09-2022 to 13-10-2022 Sy No 28-4.pdf | - |
| Document 5File: EC from 27-09-2022 to 13-10-2022 Sy No 28-1.pdf | - |
| Document 6File: EC from 27-09-2022 to 13-10-2022 Sy No 29-3.pdf | - |
| Document 7File: EC from 27-09-2022 to 13-10-2022 Sy No 30-7.pdf | - |
| Document 8File: EC from 27-09-2022 to 11-10-2022 Sy No 30-32.pdf | - |
| Document 9File: EC from 27-09-2022 to 13-10-2022 Sy No 23-3.pdf | - |
| Document 10File: EC from 27-09-2022 to 13-10-2022 Sy No 30-33.pdf | - |
| Document 11File: EC from 27-09-2022 to 13-10-2022 Sy No 30-14.pdf | - |
| Document 12File: EC from 27-09-2022 to 13-10-2022 Sy No 21-3.pdf | - |
| Document 13File: EC from 27-09-2022 to 13-10-2022 Sy No 47.pdf | - |
| Document 14File: EC from 27-09-2022 to 13-10-2022 Sy No 30-9.pdf | - |
| Document 15File: EC from 27-09-2022 to 13-10-2022 Sy No 30-8.pdf | - |
| Document 16File: EC from 27-09-2022 to 13-10-2022 Sy No 48.pdf | - |
| Document 17File: EC from 27-09-2022 to 13-10-2022 Sy No 30-36.pdf | - |
| Document 18File: EC from 27-09-2022 to 13-10-2022 Sy No 30-34.pdf | - |
| Document 19File: EC from 27-09-2022 to 11-10-2022 Sy No 30-7.pdf | - |
| Document 20File: EC from 27-09-2022 to 11-10-2022 Sy No 30-13.pdf | - |
| Document 21File: EC from 27-09-2022 to 11-10-2022 Sy No 30-11.pdf | - |
| Document 22File: EC from 27-09-2022 to 11-10-2022 Sy No 30-10.pdf | - |
| Document 23File: EC from 27-09-2022 to 11-10-2022 Sy No 30-12.pdf | - |
| Application for Commencement Certificate | - |
| Legible Floor Plan for GTT Tower C | - |
| Combined DP And Approval | - |
| Sale Deed - GTT- Tower- C | - |
| Sale & const Agreemnet Combined | - |
| Title Deeds & location compressed | - |
| Legible Floor Plan for GTT Tower C | - |
| Combined DP And Approval | - |
| Allotment Letter-GTT- C | - |
| GM GTT Brochure | - |
| Combined_nocs And Aknow | - |
| Project specification | - |
| EC for GTT | - |
| Legible khatas combined | - |
| Combined jda & GPA | - |
| Legible-Conversion Orders Combined GTT (2) | - |
| SHLCC | - |
| Noc Fire DGP ak GTT | - |
| NOC-Airport authority-GTT | - |
| NOC from BESCOM ak-GTT | - |
| NOC Water ak GTT | - |
| NOC-KSPCB-GTT | - |
| NOC-SEIA | - |
| NOC BSLNL -GTT | - |
| Tower_1_3_Elevation_Plan | - |
| Balance Sheet 2015 - 2016File: 20 GMEPL BS 2016.pdf | - |
| Balance Sheet 2014 - 2015File: 15 GMEPL BS 2015.pdf | - |
| Balance Sheet 2013 - 2014File: 11 GMEPL BS 2014.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 21 GMEPL P&L 2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: 16 GMEPL P&L 2015.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: 12 GMEPL P&L 2014.pdf | - |
| Director's Report 2015 - 2016File: GMEPL Directors Report 2016.pdf | - |
| Director's Report 2014 - 2015File: GMEPL Directors Report 2015.pdf | - |
| Director's Report 2013 - 2014File: GMEPL Directors Report 2014.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash flow statement 2016.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash flow statement 2015.pdf | - |
| Auditor's Report 2015 - 2016File: 22 GMEPL Adit report 2016.pdf | - |
| Auditor's Report 2014 - 2015File: 18 GMEPL Audit Report 2015.pdf | - |
| Auditor's Report 2013 - 2014File: 13 GMEPL Audit Report 2014.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 19 GMEPL IT Return 2016.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: 17 GMEPL IT Retrun 2015.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: 14 GMEPL IT Return 2014.pdf | - |
| Affidavait cum Declaration Tower C | - |
| Prospectus/BrochureFile: GM GTT Brochure.pdf | - |
| Advertisement Copy 1File: Advertisement GTT.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_170928_001289.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep GM GLOBAL TECHIES TOWN TOWER C on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: M/s.Gulam Mustafa Enterprises Pvt Ltd
M/s.Gulam Mustafa Enterprises Pvt Ltd has 2 registrations on RERA Karnataka, including GM GLOBAL TECHIES TOWN TOWER C and GM GLOBAL TECHIES TOWN TOWER- A. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if GM GLOBAL TECHIES TOWN TOWER C is delayed beyond 18 May 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of GM GLOBAL TECHIES TOWN TOWER C?
The registered promoter entity is M/s.Gulam Mustafa Enterprises Pvt Ltd, a company as per the filing. Its CIN U70100KA1982PTC004720 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in GM GLOBAL TECHIES TOWN TOWER C?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GM GLOBAL TECHIES TOWN TOWER C?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at GM GLOBAL TECHIES TOWN TOWER C?
The professionals named in the filing: Architect: Mr.Jayaprakash Narayan; Engineer: Mr. B.E. Pruthviraja. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GM GLOBAL TECHIES TOWN TOWER C?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback