Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Geown Oasis Phase-2 is a Plotted Development project by Geown Casper Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/210208/003878 on 8 Feb 2021. Possession is promised by 31 Dec 2023.
At a glance
Project
- NameGeown Oasis Phase-2
- TypePlotted Development
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/308/PR/210208/003878
- ReraGenie IDRG-KA-29536
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Feb 2021
- Promised completion31 Dec 2023
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed82 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Geown Casper Properties Private Limited | - | - |
| Sri L. Srinivas Reddy | - | - |
| Sri M. Nagaraju | - | - |
| Smt. Nagarathnamma | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Studio Parametric (Krishna Rao) |
| Engineer | Jayavel. C |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed82
As listed on the registration, under the names the promoter filed them with; the newest 80 of 82 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/210208/003878 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Financial StatementFile: Financial Statement.pdf | 30 Jan 2021 |
| Account Confirmation letterFile: Account confirmation letter.pdf | 30 Jan 2021 |
| Bank passbookFile: Passbook.jpg | 30 Jan 2021 |
| Account DetailsFile: Account Details.pdf | 27 Jan 2021 |
| Bank passbookFile: Passbook.jpg | 27 Jan 2021 |
| Bank passbook with confirmation letter from Axis bankFile: Passbook with bank confirmation letter.pdf | 27 Jan 2021 |
| previous project detailsFile: Previous Project and Relinquishment clarification.pdf | 27 Jan 2021 |
| CertificateFile: Company Incorporation Certificate.pdf | - |
| Initial Plan Approval Letter | - |
| Layout Planc | - |
| Layout Plan | - |
| Sale Deed Geown Oasis Ph-2 | - |
| Agt Sell Oasis Ph-2 | - |
| Sale Deeds and Partition Deeds | - |
| Layout Planc | - |
| GOP2_Booking_Form | - |
| Brochure | - |
| Project Specification | - |
| Up to Encumbrance Certificte | - |
| Sec 3(1) Non-violation Affidavit | - |
| Joint Declaration Affidavit | - |
| All RTC and MR | - |
| JDA and GPA and Deed of Confirmations | - |
| MOA and AOA | - |
| Conversion Order | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| NOC-Bescom | - |
| NOC-Water | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| supplementary sharing agreement | - |
| Legal Search Report-I | - |
| Legal Search Report-I | - |
| Balance Sheet 2019 - 2020File: Balance Sheet 2018-19.pdf | - |
| Balance Sheet 2018 - 2019File: Balance sheet 2017-18.pdf | - |
| Balance Sheet 2017 - 2018File: Balance Sheet 2016-17.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Profit & Loss 2018-19.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: Profit & Loss 2017-18.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P & L 2016-17.pdf | - |
| Director's Report 2019 - 2020File: Director's Report 2018-19.pdf | - |
| Director's Report 2018 - 2019File: Director's Report 2016-17.pdf | - |
| Director's Report 2017 - 2018File: Director's Report 2016-17.pdf | - |
| Cash Flow Statement 2019 - 2020File: Cash Flow 2018-19.pdf | - |
| Cash Flow Statement 2018 - 2019File: Cash flow 2017-18 not signed.pdf | - |
| Auditor's Report 2019 - 2020File: Auditor Report 2018-19.pdf | - |
| Auditor's Report 2017 - 2018File: Auditors Report 2016-17.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: IT Return 2018-19.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: IT Return 2017-18.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: IT Return 2016-17.pdf | - |
| Form-B Affidavit | - |
| Prospectus/BrochureFile: Brochure _ phase II (1).pdf | - |
| Advertisement Copy 1File: Advertisement Copy _ phase II.pdf | - |
| Plot Excel SheetFile: PRM_KA_RERA_1251_308_PR_210208_003878 (3).xlsx | - |
| Final plan technical sanction LetterFile: Geown Oasis P-2 BMRDA Approval.pdf | - |
| Final layout plan sanctionedFile: Final Plan technical sanction letteR (1).pdf | - |
| Completion CertificateFile: Completion Order or site release order- phase 2 geown.pdf | - |
| Site release order Copies(1st,2nd phase and final release order)File: Completion Order or site release order- phase 2 geown.pdf | - |
| Relinquishment deed executed handed over detailsFile: Relinquishment deed for BMRDA document No13580 13576.pdf | - |
| Certificate issued by P.W.D/ Panchayath Raj/Urban Local Bodies for completion of RoadFile: Pwd NOC - Phase 2 Geown.jpeg | - |
| Certificate issued by the Karnataka Urban Water supplyFile: Water NOC - Phase 2 Geown.jpg | - |
| Certificate issued by the concerned power supply(ESCOM'S)File: Electricity - NOC.jpeg | - |
| Whether the transformer has been erected within layout and copy of power sanctioned to the layout issued by ESFile: Electricity - NOC.jpeg | - |
| Chartered Accountant Certificate (Form-4)File: FORM-4CC - CA Certificate for Closure.pdf | - |
| Architect's Certificate (Form-5)File: Form 5 -Architects Certificate - for Completed Project.pdf | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Geown Oasis | - | Ongoing | May 2021 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Geown Oasis Phase-2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Geown Casper Properties Private Limited
Geown Casper Properties Private Limited has 4 registrations on RERA Karnataka, including Geown Oasis Phase-3 and Geown Oasis Phase-2. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Geown Oasis Phase-2 is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Geown Oasis Phase-2?
The registered promoter entity is Geown Casper Properties Private Limited, a company as per the filing. Its CIN U70100KA2012PTC065567 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Geown Oasis Phase-2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Geown Oasis Phase-2?
The professionals named in the filing: Architect: Studio Parametric (Krishna Rao); Engineer: Jayavel. C. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Geown Oasis Phase-2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback