Registration approved Residential/Group Housing project

Geown OASIS

By Geown Casper Properties Pvt Ltd

RG-KA-37142 · RERA PRM/KA/RERA/1251/308/PR/180406/001489

Source: official RERA Karnataka filing

Red flags

  • 6 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2021Possession promisedmoved 9 months from the original
6Complaints at RERA Karnatakaon this registration
Jump to the 49 documents Report an error

Geown OASIS is a Residential/Group Housing project by Geown Casper Properties Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180406/001489 on 6 Apr 2018. Possession is promised by 30 Aug 2021. The completion date has moved by 9 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameGeown OASIS
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180406/001489
  • ReraGenie IDRG-KA-37142

Builder

  • NameGeown Casper Properties Pvt Ltd
  • Entity typeCompany
  • CINU70100KA2012PTC065567
  • Authorized SignatoryDhiraj kumar
  • DirectorsVikas Bansal, Mahesh Sudhakarna, Amit Gupta

Key dates

this monthRegisteredApr 2018First promiseNov 2020Revised toAug 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Apr 2018
  • Promised completion30 Aug 2021
  • Revised completionRevised to 30 Aug 2021 (originally 30 Nov 2020)
  • Buildings23 building records
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building-1---909
Building-2---909
Building-3---909
Building-4---909
Building-5---909
Building-6---909
Building-7---909
Building-8---808
Building-9---505
Building-10---303
Building-11---303
Building-12---303
Building-13---303
Building-14---303
Building-15---303
Building-16---303
Building-17---303
Building-18---404
Building-19---303
Building-20---404
Building-21---202
Building-22---202
Building-23---202

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesNoNot applicable
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area26,810 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 46.63 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionNov 2020 → Aug 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka6

Case no.ComplainantRespondentFiled
CMP/210322/0007821-Geown Casper Properties Pvt Ltd22/03/2021
CMP/220330/0009293-Geown Casper Properties Pvt Ltd30/03/2022
CMP/220426/0009387-Geown Casper Properties Pvt Ltd26/04/2022
CMP/220817/0009904-Geown Casper Properties Pvt Ltd17/08/2022
01061/2023-Geown Casper Properties Pvt Ltd06/07/2023
01855/2023-Geown Casper Properties Pvt Ltd19/12/2023

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180406/001489 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Company Incorporation Certificate.pdf-
Coomencement Certificate-
GEOWN_Sanction_Plan_and_Proposed_Plan (1)-
GEOWN_Sanction_Plan_and_Proposed_Plan (1)-
Sale Deed Geown Oasis RERA draft 05-10-2017-
Proforma Sale Agreement-
Akarband RTC Sale Deed Tippani Mutation-
GEOWN_Sanction_Plan_and_Proposed_Plan (1)-
APA CDP Kallahalli-
Booking Form-
Brochure1-
Geown_Oasis_Specification-
EC-
Katha-
JDA-
Conversion-
GEOWN Sanction Plan and Proposed Plan-
GEOWN Sanction Plan and Proposed Plan-
Conversion-
Balance Sheet 2016 - 2017File: Financials 2015-16.pdf-
Balance Sheet 2015 - 2016File: Financials 2014-15.pdf-
Balance Sheet 2014 - 2015File: Financials 2013-14.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Financials 2015-16.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Financials 2014-15.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Financials 2013-14.pdf-
Director's Report 2016 - 2017File: Financials 2015-16.pdf-
Director's Report 2015 - 2016File: Financials 2014-15.pdf-
Director's Report 2014 - 2015File: Financials 2013-14.pdf-
Cash Flow Statement 2016 - 2017File: Financials 2015-16.pdf-
Cash Flow Statement 2015 - 2016File: Financials 2014-15.pdf-
Auditor's Report 2016 - 2017File: Financials 2015-16.pdf-
Auditor's Report 2015 - 2016File: Financials 2014-15.pdf-
Auditor's Report 2014 - 2015File: Financials 2013-14.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Financials 2015-16.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Financials 2014-15.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Financials 2013-14.pdf-
Form B-
Prospectus/BrochureFile: Brochure Oasis.pdf-
Advertisement Copy 1File: Oasis flyer.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_180406_001489.xlsx-
Occupancy CertificateFile: OC for Oasis P-1.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Bescom_Approval.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: NOC Water.jpg-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: external .pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: common.pdf-
Details of undivided share of land handed over to the association of allotteesFile: UDS.pdf-
Architect certificate for having completed the work(in format no 5)File: form 5.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form-4 CA.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Geown OASIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Geown Casper Properties Pvt Ltd

Geown Casper Properties Pvt Ltd has 1 registration on RERA Karnataka, including Geown OASIS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Geown OASIS is delayed beyond 30 Aug 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Geown OASIS?

The registered promoter entity is Geown Casper Properties Pvt Ltd, a company as per the filing. Its CIN U70100KA2012PTC065567 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Geown OASIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Geown OASIS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in Geown OASIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Geown OASIS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Geown OASIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.