ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / GARUDADRI GARDENS

Registration approved No litigation declared Residential/Group Housing project

GARUDADRI GARDENS

By SRI GARUDADRI CONSTRUCTIONS

RG-KA-17700 · RERA PRM/KA/RERA/1251/310/PR/291223/006517 · Last updated on RERA Karnataka portal: 28 Dec 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 134 documents Report an error

GARUDADRI GARDENS is a Residential/Group Housing project by SRI GARUDADRI CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/291223/006517 on 29 Dec 2023. Possession is promised by 10 Jun 2025.

At a glance

Project

  • NameGARUDADRI GARDENS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/291223/006517
  • ReraGenie IDRG-KA-17700

Builder

  • NameSRI GARUDADRI CONSTRUCTIONS
  • Entity typePartnership Firm
  • GSTIN29ADVFS8650A1ZJ
  • Authorized SignatoryM Venkatesh
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2023PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Dec 2023
  • Promised completion10 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed134 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GARUDADRI GARDENS---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 28 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
R P MOORTHY--
USHA MOORTHY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 17.13 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 16.61 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 15.00 lakh-
On-site expenditure-Salaries of workersRs 12.00 lakh-
On-site expenditure-Consultants FeesRs 12.00 lakh-
Payment of feesRs 7.00 lakh-
On-site expenditure-Site OverheadRs 5.00 lakh-
Payment of PremiumsRs 1.50 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG BHANUMATHY
EngineerARUN KUMAR S R
Chartered AccountantRadhakrishna Tantry

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed134

As listed on the registration, under the names the promoter filed them with; the newest 80 of 134 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/291223/006517 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
ITR of M VENKATESHFile: ITR M Venkatesh.pdf28 Dec 2023
ITR of M CHIRANJEEVIFile: ITR of Chiranjeevi.pdf28 Dec 2023
ITR OF PRATEETH RAI BHASKARFile: ITR OF PRATEETH RAI BHASKAR.pdf28 Dec 2023
FY 20-21 Financial Statement with promoter signatureFile: 2021.pdf17 Dec 2023
FY 2021-22 Financial statement with promoter signatureFile: 2022.pdf17 Dec 2023
FY 2022-23 Financial statement with promoter signatureFile: 2023.pdf17 Dec 2023
EC from1/4/2004 to till dateFile: EC.pdf17 Dec 2023
FAR Acheived Net Area 1.88File: FAR.pdf17 Dec 2023
Area Statement - Eng Certified copyFile: Area Statement.pdf17 Dec 2023
Eng Form - 6 for ongoing projectFile: Form -6, Engineer.pdf17 Dec 2023
ECFile: EC Final.pdf14 Dec 2023
CA Form 1 - RegFile: Reg Certificate.pdf14 Dec 2023
Land Cost CalculationFile: Land Cost Calc.pdf14 Dec 2023
Eng License CertificateFile: Eng License Self Attested.pdf14 Dec 2023
Title Deed of Land OwnerFile: Sale Deed of RP Murthy.pdf14 Dec 2023
Title Deed - Land OwnerFile: Sale Deed of Usha Murthy.pdf14 Dec 2023
Advocate Search ReportFile: Advocate Search Report.pdf14 Dec 2023
Approved Plan CopyFile: BBMP PLAN.PDF14 Dec 2023
FARFile: FAR.xlsx14 Dec 2023
Financials Sri Garudadri Constructions AY 2022-23File: Financials Sri Garudadri Constructions AY 2022-23.pdf14 Dec 2023
Financials Sri Garudadri Constructions AY 2021-22File: Financials Sri Garudadri Constructions AY 2021-22.pdf14 Dec 2023
Financials Sri Garudadri Constructions AY 2020-21File: Financials Sri Garudadri Constructions AY 2020-21.pdf14 Dec 2023
Sources of FundsFile: Sources of Funds.pdf14 Dec 2023
Prateeth Rai ITR and Financials AY 2023-24File: Prateeth Rai ITR and Financials AY 2023-24.pdf14 Dec 2023
M Venkatesh ITR and Financials AY 2023-24File: M Venkatesh ITR and Financials AY 2023-24.pdf14 Dec 2023
Chiranjeevi ITR and Financials AY 2023-24File: Chiranjeevi ITR and Financials AY 2023-24.pdf14 Dec 2023
RERA Bank Account ConfirmationFile: RERA Bank Account Confirmation.pdf14 Dec 2023
Reason for DelayFile: Reason for Delay.pdf14 Dec 2023
Engineer certificateFile: Engineer certificate.pdf14 Dec 2023
Commencement CertificateFile: Commencement Cert.pdf21 Nov 2023
Eng. License self attestedFile: Eng License.pdf21 Nov 2023
Engineer CertificateFile: Engineer Certificate.pdf21 Nov 2023
COA Certificate Self AttestedFile: COA Archiect.pdf21 Nov 2023
Architect CertificateFile: Architect Certificate.pdf21 Nov 2023
CA Reg CertificateFile: CA Reg Certificate.pdf21 Nov 2023
BWSSB NOCFile: BWSSB NOC.pdf21 Nov 2023
BWSSB Paid ReceiptFile: Receipt of BWSSB.jpg21 Nov 2023
Village MAP with Proposed SiteFile: VILLAGE MAP with Proposed Site.pdf21 Nov 2023
CDP with Proposed SiteFile: CDP with Proposed Site.pdf21 Nov 2023
Area StatementFile: Garudadri Constructions.pdf21 Nov 2023
Advocate Search ReportFile: Advocate Search Report.pdf14 Oct 2023
Agreement of Sale - ProformaFile: Agreement of Sale Proforma.pdf14 Oct 2023
BESCOM NOC Self AttestedFile: BESCOM NOC.pdf14 Oct 2023
EC CopiesFile: Final EC Copies.pdf14 Oct 2023
Commencement Certificate ApplicationFile: CC Application.pdf14 Oct 2023
Guidance Value - Land CostFile: SR Value.pdf14 Oct 2023
Mutation CopiesFile: Mutation Copies.pdf14 Oct 2023
Eng. Certificate - Self AttestedFile: srinivasaraobolimunta_10119.pdf14 Oct 2023
RTC - 1File: RTC - 1.pdf14 Oct 2023
RTC - 2File: RTC - 2.pdf14 Oct 2023
RTC - 3File: RTC 3.jpg14 Oct 2023
RTC - 4File: RTC 4.jpg14 Oct 2023
RTC - 5File: RTC 5.jpg14 Oct 2023
Village MAPFile: Village MAP.pdf14 Oct 2023
STPFile: STP.pdf14 Oct 2023
Sale Deed of UshamoorthyFile: Sale Deed of Ushamoorthy.pdf14 Oct 2023
Sale Deed of R P MoorthyFile: Sale Deed of RP Moorthy.pdf14 Oct 2023
Land Documents - 1File: Form 1 Appendex.jpg14 Oct 2023
Land Documents - 2File: Form Vi.jpg14 Oct 2023
Land Documents - 3File: Land Documents.jpg14 Oct 2023
Land Documents - 4File: Records.jpg14 Oct 2023
Architect COA CertificateFile: COA Certificate.pdf14 Oct 2023
Registration CertificateFile: Reg Certificate.pdf-
Partnership DeedFile: new partnership deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Reg Certificate.pdf-
Certificate issued by Architect Form 2File: Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer (Reg).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Ligitaion.pdf-
Certificate from Chartered AccountFile: Cost Approval.pdf-
Balance Sheet 2020 - 2021File: BS 2021-22.pdf-
Balance Sheet 2019 - 2020File: BS 20-21.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL 2021-22.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL 20-21.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR V-2021-22.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GARUDADRI GARDENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SRI GARUDADRI CONSTRUCTIONS

SRI GARUDADRI CONSTRUCTIONS has 2 registrations on RERA Karnataka, including GARUDADRI GARDENIA and GARUDADRI GARDENS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GARUDADRI GARDENS is delayed beyond 10 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GARUDADRI GARDENS?

The registered promoter entity is SRI GARUDADRI CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29ADVFS8650A1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GARUDADRI GARDENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GARUDADRI GARDENS?

The professionals named in the filing: Architect: G BHANUMATHY; Engineer: ARUN KUMAR S R; Chartered Accountant: Radhakrishna Tantry. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GARUDADRI GARDENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GARUDADRI GARDENS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GARUDADRI GARDENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.