Registration transferred No litigation declared Mixed Development project

Garuda kingsford

By GARUDA KINGSFORD

RG-KA-35396 · RERA PRM/KA/RERA/1251/446/PR/251024/007177 · Last updated on RERA Karnataka portal: 20 Oct 2024

Source: official RERA Karnataka filing

Red flags

  • Registration transferred

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2028Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 92 documents Report an error

Garuda kingsford is a Mixed Development project by GARUDA KINGSFORD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/251024/007177 on 25 Oct 2024. Possession is promised by 20 Sep 2028.

At a glance

Project

  • NameGaruda kingsford
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560037
  • Pincode560037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/251024/007177
  • ReraGenie IDRG-KA-35396

Builder

  • NameGARUDA KINGSFORD
  • Entity typePartnership Firm
  • GSTIN29ABAFG3017G1ZP
  • Authorized SignatoryKONDURU SRINIVASULU

Key dates

this monthRegisteredOct 2024PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistration transferred
  • Registered on25 Oct 2024
  • Promised completion20 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GARUDA KINGSFORD-----60

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 20 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,389 sq m
Named landowners1
LandownerVillageDistrict
SHREEMAD. VIBHUTHIPURA VEERASIMHASANA SAMSTHANA MATHA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 74.16 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 63.00 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 6.00 cr-
On-site expenditure-Salaries of workersRs 2.00 cr-
On-site expenditure-Consultants FeesRs 1.50 cr-
On-site expenditure-Site OverheadRs 50.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 50.00 lakh-
Payment of taxesRs 50.00 lakh-
Payment of cessRs 15.00 lakh-
Payment of feesRs 25,000-
Payment of chargesRs 25,000-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKarthikeyan V
EngineerAmbrish G
Chartered AccountantH Chandrashekara Udupa

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed92

As listed on the registration, under the names the promoter filed them with; the newest 80 of 92 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/251024/007177 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
chartered accountant certificate form-1File: 1 Form 1 CA Certificate.pdf20 Oct 2024
sources of funds to complete the projectFile: 2 Source Of Fund.pdf20 Oct 2024
RTC 2024-25File: 1 RTC 2024-25.pdf20 Oct 2024
EC from 1-4-2008 to till dateFile: 2 EC 1-4-2008 TO 16-9-2024.pdf20 Oct 2024
Title deedFile: 3 Title Deed Document.pdf20 Oct 2024
Engineer certificateFile: 2 Engineer Certificate.pdf20 Oct 2024
Cost of construction certified by the registered Civil EngineerFile: 3 Civil Engineer Certificate.pdf20 Oct 2024
Project section 3(1) notarized affidavit - Colur CopyFile: 4 SEC 3 AFFIDAVIT.pdf20 Oct 2024
Self-attested BWSSB NOCFile: 5 Self Attested BWSSB NOC and Fees Receipt.pdf20 Oct 2024
STP design drawingFile: 6 STP Design With Project Name and Address.pdf20 Oct 2024
land calculation sheetFile: 7 Land Cost.pdf20 Oct 2024
Proforma of the Allotment letterFile: 8 Allotment Letter.pdf20 Oct 2024
Proforma of Agreement for saleFile: 9 Agreement of Sale Proforma.pdf20 Oct 2024
% Collection Account Bank Account StatementFile: 1 Garuda Kingsford MSE Collection Account.pdf14 Oct 2024
70% RERA Account Bank Account StatementFile: 2 Garuda Kingsford MSE RERA Account.pdf14 Oct 2024
30% ESCROW Account Bank Account StatementFile: 3 Garuda Kingsford MSE Escrow Account.pdf14 Oct 2024
Bank AffidavitFile: 4 Bank Affidavit.pdf14 Oct 2024
Balance Sheet And Profit and Loss Account- Since it is new company we have not filed Balance sheetFile: Balance Sheet and Profir and loss account.pdf14 Oct 2024
Chartered Accountant KYC and Membership Registration certificateFile: 4 Chartered Accountant KYC and Membership Registration certificate Self Attested.pdf14 Oct 2024
Sources Of Funds to complete the projectFile: Source Of Fund.pdf14 Oct 2024
Firm PAN Self AttestedFile: 6 Firm Self Attested PAN.pdf14 Oct 2024
Partners Financial StatementFile: 7 Partners Financials.pdf14 Oct 2024
Form 1 Chartered Accountant CertificateFile: Form-1-CA Certificate.pdf14 Oct 2024
RTC 2024 25File: 1 RTC 2024-25.pdf14 Oct 2024
Authenticated RTCFile: 2 RTC 2024-25.pdf14 Oct 2024
EC 1-4-2008 to till dateFile: 3 EC 1-4-2008 to 2024.pdf14 Oct 2024
Title DeedFile: 4 Title Deed JDA.PDF14 Oct 2024
Affidavit regarding all pending or cleared litigationsFile: 5 Affidavit Non Litigation.pdf14 Oct 2024
notarized affidavit in form-BFile: 6 Form 3B.pdf14 Oct 2024
Notarised JD cum AffidavitFile: 7 JD Cum Affidavit.pdf14 Oct 2024
Advocate Search ReportFile: 8 Advocate Search Report.pdf14 Oct 2024
Single Layout Approval PlanFile: 1 Single Layout approval plan.pdf14 Oct 2024
Layout Approval Order CopyFile: 2 Single Layout Order Copy.pdf14 Oct 2024
Building Plan Blue PrintFile: 3 Buliding Plan Blue print.pdf14 Oct 2024
Extract Of Master PlanFile: 4 Master Plan.pdf14 Oct 2024
Village MapFile: 6 Village Map.PDF14 Oct 2024
ADLR SketchFile: 8 ADLR Scketch.PDF14 Oct 2024
Each Floor and Section PlanFile: 9 Each Floor Plan & Section Plan.pdf14 Oct 2024
KSPCB NOCFile: 10 KSPCB NOC.pdf14 Oct 2024
SEIAA NOCFile: 12 SEIAA NOC.pdf14 Oct 2024
Project Engineer Details along with the self AttestedFile: 4 Engineer Details and Certificate.pdf14 Oct 2024
Engineer CertificateFile: 5 Engineer Certificate.pdf14 Oct 2024
Estimated Cost of constructionFile: 6 Civil Engineer Certificate.pdf14 Oct 2024
Project Specification by incorporating the projectFile: 7 project specifications.pdf14 Oct 2024
Section 3(1) AffidavitFile: 8 SEC 3(1) AFFIDAVIT.pdf14 Oct 2024
Proforma Allotment LetterFile: 9 Proforma Allotment Letter.pdf14 Oct 2024
Self Attested copy of BESCOM NOC and BWSSBFile: 10 Self Attested BESCOM and BWSSB NOC.pdf14 Oct 2024
STP Desighn DrawingFile: 11 STP Design Drawing.pdf14 Oct 2024
Structural Safety Engineer CertificateFile: 12 Structural Safety Certificate.PDF14 Oct 2024
Land Cost Calculation Sheet as per guidance value - Self attestedFile: 13 Land Cost calculation.pdf14 Oct 2024
Airport NOCFile: 15 Airport Authority - NOC.pdf14 Oct 2024
RTC, survey 198-
Mutation, survey 198-
Encumbrance Certificate, survey 198-
Conversion/Alienation Order, survey 198-
JDA, survey 198-
Khatha, survey 198-
Registration CertificateFile: Firm Registration Certficate.pdf-
Partnership DeedFile: Partnership Deed.PDF-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: 1 Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: NON LITIGATION AFFIDAVIT.pdf-
Certificate from Chartered AccountFile: 1 Form 1 CA Certificate.pdf-
BESCOM Approval-
BWSSB NOC Garuda KingsFord-
Plan Copies-PRJ_10847_23-24-
Plan Copies-PRJ_10847_23-24-
Plan Copies-PRJ_10847_23-24-
Plan Copies-PRJ_10847_23-24-
Project Specification-
Plan Copies-PRJ_10847_23-24-
Plan Copies-PRJ_10847_23-24-
Soil Testing Report -Garuda kingsford-
JDA --

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Garuda kingsford on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGaruda kingsfordOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: GARUDA KINGSFORD

GARUDA KINGSFORD has 1 registration on RERA Karnataka, including Garuda kingsford. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Garuda kingsford is delayed beyond 20 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Garuda kingsford?

The registered promoter entity is GARUDA KINGSFORD, a partnership firm as per the filing. Its GSTIN 29ABAFG3017G1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Garuda kingsford?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Garuda kingsford?

The professionals named in the filing: Architect: Karthikeyan V; Engineer: Ambrish G; Chartered Accountant: H Chandrashekara Udupa. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Garuda kingsford?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Garuda kingsford. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Garuda kingsford to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.