Home / Browse projects / Mumbai Suburban, Maharashtra / GARODIA NAGAR MAHAVIR DHAM CHS LTD
GARODIA NAGAR MAHAVIR DHAM CHS LTD
By GARODIA NAGAR MAHAVIR DHAM CHS LTD
RG-MH-05219 · RERA P51800052562 · Last updated on MahaRERA portal: 31 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GARODIA NAGAR MAHAVIR DHAM CHS LTD is a Residential / Group Housing project by GARODIA NAGAR MAHAVIR DHAM CHS LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800052562 on 11 Sep 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 2 complaints are on record with the regulator.
At a glance
Project
- NameGARODIA NAGAR MAHAVIR DHAM CHS LTD
- TypeResidential / Group Housing
- Location
- GARODIA NAGAR
- GHATKOPAR EAST
- Kirol
- Kurla
- Mumbai Suburban
- 400077
- Pincode400077
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800052562
- ReraGenie IDRG-MH-05219
Builder
- NameGARODIA NAGAR MAHAVIR DHAM CHS LTD
- Entity typeSociety
- ChairpersonSHARMISHTA JITENDRA PARIKH
- SecretoryVINAYAK DINKAR KHOT
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Sep 2023
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed79 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MAHAVIR DHAM | NA | 19 | 14 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.
MAHAVIR DHAM: 80% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 45% |
Progress on shared amenities15
As on 31 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | Yes | 60% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed107
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YASH RAJESH AGARWAL |
| Engineer | NAVANATH AIWALE |
| Engineer | Hiren Shah |
| Engineer | RAJENDRA P BHANKAR |
| Chartered Accountant | HARSH DEDHIA |
| Partner | Role in project |
|---|---|
| GARODIA NAGAR MAHAVIR DHAM CHS LTD | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400729 | yash Rajesh Agarwal | GARODIA NAGAR MAHAVIR DHAM CHS LTD | 11/11/2024 |
| CC12500763 | Yagnesh Nilesh Shah | GARODIA NAGAR MAHAVIR DHAM CHS LTD | 06/03/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Mar 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Mar 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed79
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FROM 1 - 30-06-2025.pdf | 31 Jul 2025 |
| Form 2File: FORM 2 - 30-06-2025.pdf | 31 Jul 2025 |
| Form 3File: FORM 3 - 30-06-2025.pdf | 31 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold inventory - 30-06-2025.pdf | 31 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: JUNE 2024.pdf | 28 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: SEPT 2024.pdf | 28 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DEC 2024.pdf | 28 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: MARCH 2025.pdf | 28 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q4 2014-25.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q4 2024-25.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q4 2024-25.pdf | 21 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 4 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MARCH 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JUNE 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SEPTEMBER 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DECEMBER 2024.pdf | 20 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MARCH 2024.pdf | 20 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JUNE 2024.pdf | 20 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SEPTEMBER 2024.pdf | 20 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DECEMBER 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MARCH 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JUNE 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SEPTEMBER 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DECEMBER 2024.pdf | 20 Mar 2025 |
| Layout approvalFile: HIGH LIGHTED 1.pdf | 12 Mar 2024 |
| Building plan approvalFile: Amended Plan Approval Letter.pdf | 12 Mar 2024 |
| Building plan approvalFile: 2.pdf | 12 Mar 2024 |
| Building plan approvalFile: 3.pdf | 12 Mar 2024 |
| Building plan approvalFile: 4.pdf | 12 Mar 2024 |
| Building plan approvalFile: 5.pdf | 12 Mar 2024 |
| Building plan approvalFile: 6.pdf | 12 Mar 2024 |
| Building plan approvalFile: 7.pdf | 12 Mar 2024 |
| Building plan approvalFile: 8.pdf | 12 Mar 2024 |
| Building plan approvalFile: 9.pdf | 12 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: HIGH LIGHTED 1.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended Plan Approval Letter.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 9.pdf | 12 Mar 2024 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 12 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Certificate.pdf | 12 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 2410503_FurtherCC_signed_Full till 14 fl.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 11 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 11 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL CA-1-6_merged (1)_compressed.pdf | 6 Sep 2023 |
| Building plan approvalFile: plan today_6-end.pdf | 12 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: plan today_6-end.pdf | 12 Aug 2023 |
| Building plan approvalFile: plan today_2-3.pdf | 9 Aug 2023 |
| Building plan approvalFile: plan today_4-5.pdf | 9 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: plan today_2-3.pdf | 9 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: plan today_4-5.pdf | 9 Aug 2023 |
| Building plan approvalFile: 2288277_IOD_signed.pdf | 29 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2288277_IOD_signed.pdf | 29 May 2023 |
| Copy of the legal title reportFile: Legal Title Report Mahavirdham (1).pdf | 22 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest In Other Real Estate Organizations .pdf | 22 May 2023 |
| Proforma of Agreement for saleFile: RERA SALE AGREEMENT.pdf | 22 May 2023 |
| CERSAI detailsFile: DocScanner 11 May 2023 1-14 pm.pdf | 11 May 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Certificate Concerned To Legal.pdf | 28 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Certificate Concerned to finance .pdf | 28 Apr 2023 |
| Details of encumbrances concerned to LegalFile: No Encumbrance Certificate Concerned To Legal.pdf | 28 Apr 2023 |
| Details of encumbrances concerned to LegalFile: No Encumbrance Certificate Concerned to finance .pdf | 28 Apr 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 28 Apr 2023 |
| Declaration about Commencement CertificateFile: CC DECL.pdf | 24 Apr 2023 |
| Layout approvalFile: plan today_1-1.pdf | 21 Apr 2023 |
| PAN CardFile: Mahavir Dham PAN Card.pdf | 21 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: plan today_1-1.pdf | 21 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed.pdf | 21 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT DETAILS.pdf | 21 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: DEVIATION REPORT ALLOTMENT.pdf | 21 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT AFS.pdf | 21 Apr 2023 |
| Declaration in FORM BFile: Mahavirdham affidavit cum declaration .pdf | 10 Apr 2023 |
| CERSAI detailsFile: Asset Based Search.pdf | 10 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 79 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GARODIA NAGAR MAHAVIR DHAM CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GHATKOPAR EAST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 359 registered projects within 2 km.
Mahindra Rainforest Phase 1
Anthurium Developers Limited
Mahindra Rainforest Phase 2
Anthurium Developers Limited
CRYSTAL PRIME MERIDIAN
ARYAMAAN DEVELOPERS PRIVATE LIMITED
AARADHYA ONEPARK
MICL CREATORS LLP
CENTRONA ZEN-A
ELEVATED AVENUE REALTY LLP
CENTRONA ZEN-B
ELEVATED AVENUE REALTY LLP
See every Mumbai Suburban project, with the district possession charts
Builder: GARODIA NAGAR MAHAVIR DHAM CHS LTD
GARODIA NAGAR MAHAVIR DHAM CHS LTD has 1 registration on MahaRERA, including GARODIA NAGAR MAHAVIR DHAM CHS LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that GARODIA NAGAR MAHAVIR DHAM CHS LTD shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GARODIA NAGAR MAHAVIR DHAM CHS LTD is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GARODIA NAGAR MAHAVIR DHAM CHS LTD?
The registered promoter entity is GARODIA NAGAR MAHAVIR DHAM CHS LTD, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GARODIA NAGAR MAHAVIR DHAM CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GARODIA NAGAR MAHAVIR DHAM CHS LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GARODIA NAGAR MAHAVIR DHAM CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GARODIA NAGAR MAHAVIR DHAM CHS LTD?
The professionals named in the filing: Architect: YASH RAJESH AGARWAL; Engineer: NAVANATH AIWALE; Engineer: Hiren Shah; Engineer: RAJENDRA P BHANKAR; Chartered Accountant: HARSH DEDHIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GARODIA NAGAR MAHAVIR DHAM CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback