ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Garden of Eden by UKN

Registration approved Commercial project

Garden of Eden by UKN

By UKN Properties Pvt Ltd

RG-KA-50839 · RERA PRM/KA/RERA/1251/446/PR/180217/002407

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Nov 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 66 documents Report an error

Garden of Eden by UKN is a Commercial project by UKN Properties Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180217/002407 on 17 Feb 2018. Possession is promised by 1 Nov 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameGarden of Eden by UKN
  • TypeCommercial
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/180217/002407
  • ReraGenie IDRG-KA-50839

Builder

  • NameUKN Properties Pvt Ltd
  • Entity typeCompany
  • Authorized SignatoryGautam U Nambisan
  • DirectorsVinutha Kondur, Ravindran K
  • Declared earlier projects3 →

Key dates

this monthRegisteredFeb 2018First promiseFeb 2022Revised toNov 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Feb 2018
  • Promised completion1 Nov 2022
  • Revised completionRevised to 1 Nov 2022 (originally 1 Feb 2022)
  • Buildings3 building records
  • Documents filed66 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---055
B---055
C---055

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,608 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVijay and Anjali Architects
EngineerBase Engineering Services

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionFeb 2022 → Nov 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed66

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180217/002407 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of Incorporation.pdf-
edp-
edp-
Site Plan & Elevation-
edp-
edp-
Sale Deed fav Shorff 2097 of 1967-68-
Upper & Lower Basement-
Upper & Lower Basement-
edp-
edp-
edp-
Ec-
Khata-
JDA-
Will of Dara Shroff-
Conversion Order Pattandura-
NOC-
edp-
edp-
edp-
NOC-
KSPC-
NOC-
NOC-
KSPC-
KSPC-
NOC-
edp-
Unnamed document-
edp-
edp-
edp-
edp-
edp-
edp-
edp-
2,3,4 & Terrace Floor-
NOC-
RTC-
EC latest-
Advocate Search-
Balance Sheet 2016 - 2017File: Balance Sheet 15-16.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 14-15.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet 2013-14.pdf-
Audited Profit and Loss Statement 2016 - 2017File: PL 2015-16.pdf-
Audited Profit and Loss Statement 2015 - 2016File: PL 2014-15.pdf-
Audited Profit and Loss Statement 2014 - 2015File: PL 2013-14.pdf-
Director's Report 2016 - 2017File: Directors report -2015-16.pdf-
Director's Report 2015 - 2016File: Directors report -2014-15.pdf-
Director's Report 2014 - 2015File: Directors report -2013-14.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flor 2015-16.pdf-
Cash Flow Statement 2015 - 2016File: cash flow 2014-15.pdf-
Auditor's Report 2016 - 2017File: 2015-16 Auditors report.pdf-
Auditor's Report 2015 - 2016File: Balance Sheet 14-15.pdf-
Auditor's Report 2014 - 2015File: Auditor Report.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: IT return -2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT return -2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT return -2014-15.pdf-
Affidavit cum Declaration-
Prospectus/BrochureFile: Garden Of Eden By Ukn - Broucher.pdf-
Advertisement Copy 1File: Garden Of Eden By Ukn - Broucher.pdf-
Tower Excel SheetFile: Copy of PRM_KA_RERA_1251_446_PR_180217_002407.xlsx-
Loan raised documentFile: Attachment.pdf-
Occupancy CertificateFile: GOE Occupancy Certificate dated 04122020.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Miraya Rose by UKN-Completed-No date filed
Esperanza by UKN-Completed-No date filed
Belvista by UKN-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Garden of Eden by UKN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: UKN Properties Pvt Ltd

UKN Properties Pvt Ltd has 1 registration on RERA Karnataka, including Garden of Eden by UKN. Its filings declare 3 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Garden of Eden by UKN is delayed beyond 1 Nov 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Garden of Eden by UKN?

The registered promoter entity is UKN Properties Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Garden of Eden by UKN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Garden of Eden by UKN?

The professionals named in the filing: Architect: Vijay and Anjali Architects; Engineer: Base Engineering Services. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Garden of Eden by UKN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Garden of Eden by UKN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Garden of Eden by UKN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.