ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / GALAXY TOWER

Registration approved No litigation declared Residential/Group Housing project

GALAXY TOWER

By Ashish Kumar

RG-KA-29160 · RERA PRM/KA/RERA/1251/446/PR/270125/007434 · Last updated on RERA Karnataka portal: 14 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2028Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
24 of 24Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 139 documents Report an error

GALAXY TOWER is a Residential/Group Housing project by Ashish Kumar in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/270125/007434 on 27 Jan 2025. Possession is promised by 30 Jun 2028. 0 of the 24 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameGALAXY TOWER
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560035
  • Pincode560035
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/270125/007434
  • ReraGenie IDRG-KA-29160

Builder

  • NameAshish Kumar
  • Entity typeProprietorship
  • GSTIN29AHNPA1441K2ZB
  • Authorized SignatoryAshish Kumar

Key dates

this monthRegisteredJan 2025PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on27 Jan 2025
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed139 files

Current status

0%0 of 24 units booked
6.4%Of the estimated cost spent so far

Figures as on 14 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%
Common storage spacesYes100%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,877 sq m
Named landowners1
LandownerVillageDistrict
Mrs Mary Rao and Mr. Jayamuni Rao--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.46 cr
Cost incurredRs 34.70 lakh
Spent of the estimate6.36%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.56 crRs 32.62 lakh
Payment of taxesRs 50.00 lakh-
On-site expenditure-Consultants FeesRs 20.00 lakh-
Administartive costRs 20.00 lakh-
On-site expenditure-Site Overhead-Rs 2.08 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSathisha K P
EngineerRoshan
Chartered AccountantGude Babu Rao

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed139

As listed on the registration, under the names the promoter filed them with; the newest 80 of 139 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/270125/007434 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Galaxy.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Galaxy Tower Form 6 June 26.pdf14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Galaxy tower form4 march 26.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Galaxy Tower Form 6 march 26.pdf13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 (1).pdf6 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate (1).pdf6 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate (4).pdf6 Feb 2026
penalty AffidavitFile: Affidavit clear copy rera.pdf8 Jan 2025
Penalty Affidivate Cum declarationFile: Penalty Affidavit cum declaration.pdf19 Dec 2024
Boghenahalli cdp mapFile: Boghenahalli cdp map.pdf29 Nov 2024
Bogenahalli Village MapFile: Bogenahalli Village Map.pdf29 Nov 2024
Approved PLAN SANCTION All in oneFile: Approved PLAN SANCTION All in one.pdf29 Nov 2024
Occupancy certificate of previous projectFile: Occupancy certificate of previous project.pdf29 Nov 2024
ECC-2-4-24 to 3-11-24File: ECC-2-4-24 to 3-11-24.pdf7 Nov 2024
Bescom Temp Conne with Fees recFile: Bescom Temp Conne with Fees rec.pdf7 Nov 2024
Single plot layoutFile: Single plot layout.pdf8 Oct 2024
BHOGANAHALLI SY. NO.78File: BHOGANAHALLI SY NO 78.pdf8 Oct 2024
village map_BhoganahalliFile: village map_Bhoganahalli (1).pdf8 Oct 2024
Boghenahalli cdp mapFile: Boghenahalli cdp map.pdf8 Oct 2024
Hissa AtlasFile: Hissa Atlas.pdf8 Oct 2024
Approved plan all in one planFile: Approved PLAN SANCTION All in one.pdf10 Sep 2024
Architect lisence attestedFile: Architect lisence attested.pdf10 Sep 2024
Boghenahalli cdp mapFile: Boghenahalli cdp map.pdf10 Sep 2024
ITR 2021File: ITR 2021.pdf2 Aug 2024
ITR 2022File: ITR 2022.pdf2 Aug 2024
ITR 2023File: ITR 2023.pdf2 Aug 2024
BS with schedule 2021File: BS with schedule 2021.pdf2 Aug 2024
BS with schedule 2022File: BS with schedule 2022.pdf2 Aug 2024
BS with schedule 2022File: BS with schedule 2023.pdf2 Aug 2024
PL with schedule 2021File: PL with schedule 2021.pdf2 Aug 2024
PL 2022File: PL 2022.pdf2 Aug 2024
PL with schedule 2023File: PL with schedule 2023.pdf2 Aug 2024
Bank Account detailsFile: Bank Account details.jpeg2 Aug 2024
Bank affidavit oriFile: Bank affidavit ori.pdf2 Aug 2024
S O F wit BS and loan letterFile: S O F wit BS and loan letter.pdf2 Aug 2024
Form 1 CA certificateFile: Form 1 CA certificate.pdf2 Aug 2024
Membership copyFile: Membership copy.pdf2 Aug 2024
Common Area and AmenitiesFile: Common Area and Amenities.pdf2 Aug 2024
Bank account noFile: Bank account no.pdf26 Jun 2024
Engineer lisenceFile: Engineer lisence.pdf26 Jun 2024
Area statementFile: Area statement.pdf26 Jun 2024
Arch lisenceFile: Arch lisence.pdf26 Jun 2024
Arch certiFile: Arch certi.pdf26 Jun 2024
Abstract estimationFile: ESTIMATION (1) (1).pdf26 Jun 2024
Village MapFile: Village Map.pdf26 Jun 2024
BUILDING LICENSE PLAN SARJAPURAFile: BUILDING LICENSE PLAN SARJAPURA.pdf26 Jun 2024
Boghenahalli cdp mapFile: Boghenahalli cdp map.pdf26 Jun 2024
Approved PLAN SANCTION All in oneFile: Approved PLAN SANCTION All in one.pdf26 Jun 2024
Declara Single plot layout plan and orderFile: Declara Single plot layout plan and order.pdf26 Jun 2024
Declaration of Commencement certiFile: Declaration of Commencement certi.pdf26 Jun 2024
Declaration of Relinquishment deedFile: Declaration of Relinquishment deed.pdf26 Jun 2024
No litigation AffidavitFile: No litigation.pdf2 May 2024
BUILDING LICENSE PLAN SARJAPURAFile: BUILDING LICENSE PLAN SARJAPURA.pdf2 May 2024
EC 1-04-2004till2-4-2024File: EC till date.pdf2 May 2024
Approved PLAN SANCTION All in oneFile: Approved PLAN SANCTION All in one.pdf2 May 2024
ARCHITECT CERTIFICATEFile: ARCHITECT CERTIFICATE .pdf2 May 2024
Form b affidavitFile: Form b .pdf3 Apr 2024
No mortgage affidavitFile: No mortgage affidavit.pdf3 Apr 2024
Section 3 (1) affidavitFile: Section 3 (1) affidavit.pdf3 Apr 2024
JDA AffidavitFile: JDA Affidavit.pdf3 Apr 2024
Agreement for SaleFile: Agreement for Sale.pdf3 Apr 2024
Allotment LetterFile: Allotment Letter (1).pdf3 Apr 2024
Booking Application FormFile: Booking Application Form.pdf3 Apr 2024
Proforma of Sale DeedFile: Sale Deed (2).pdf3 Apr 2024
Carpet AreaFile: Carpet area (2).pdf3 Apr 2024
Common area detailsFile: Common Area.pdf3 Apr 2024
stability certificateFile: stability certificate.pdf3 Apr 2024
STP (1)File: STP (1).pdf3 Apr 2024
EC till dateFile: EC till date.pdf3 Apr 2024
Guidance valueFile: Guidance value.pdf3 Apr 2024
ESTIMATION (1)File: ESTIMATION (1).pdf3 Apr 2024
ARCHITECT CERTIFICATEFile: ARCHITECT CERTIFICATE .pdf3 Apr 2024
Engineer certificateFile: Engineer certificate.pdf3 Apr 2024
land calculationFile: land calculation.pdf3 Apr 2024
Project SpecificationFile: Specification.pdf3 Apr 2024
Title deedFile: Title deed.pdf3 Apr 2024
RTC, survey 78/1-
Mutation, survey 78/1-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GALAXY TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGALAXY TOWEROther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: Ashish Kumar

Ashish Kumar has 1 registration on RERA Karnataka, including GALAXY TOWER. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GALAXY TOWER is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GALAXY TOWER?

The registered promoter entity is Ashish Kumar, a proprietorship as per the filing. Its GSTIN 29AHNPA1441K2ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GALAXY TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GALAXY TOWER?

The professionals named in the filing: Architect: Sathisha K P; Engineer: Roshan; Chartered Accountant: Gude Babu Rao. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GALAXY TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GALAXY TOWER. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GALAXY TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.