Home / Browse projects / Bengaluru Urban, Karnataka / G R FLORET

Registration approved Litigation declared Residential/Group Housing project

G R FLORET

By SGR BUILDTECH LLP

RG-KA-37889 · RERA PRM/KA/RERA/1251/310/PR/210129/003799 · Last updated on RERA Karnataka portal: 16 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
0 of 3Construction stages donefurthest along: Earth work and other leveling..., 99%
66 of 156Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 78 documents Report an error

G R FLORET is a Residential/Group Housing project by SGR BUILDTECH LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210129/003799 on 29 Jan 2021. Possession is promised by 31 Dec 2026. 90 of the 156 units on this registration are recorded sold or booked, and 0 of 3 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameG R FLORET
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/210129/003799
  • ReraGenie IDRG-KA-37889

Builder

  • NameSGR BUILDTECH LLP
  • Entity typePartnership Firm
  • Authorized SignatoryCHIKKANAYAKANAHALLI RAMASETTY GOPALAKRISHNA
  • Board MembersCHIKKANAYAKANAHALLI RAMASETTY GOPALAKRISHNA, ASWATHANARAYANA NAGARATHNAIAHSETTY PARATHALA
  • Declared earlier projects2 →

Key dates

this monthRegisteredJan 2021PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Jan 2021
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed78 files

Current status

58%90 of 156 units booked
5.7%Of the estimated cost spent so far

Figures as on 16 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASTER---84084
BIGONIA---72072

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 3 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 99%.

Building: 98% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work99%
Foundation footing workNot applicable
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure99%
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing95%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes25%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes25%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes95%
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,396 sq m
Named landowners7
LandownerVillageDistrict
Sumitha Todarwal--
Smitha V Harithasa--
Shubha V Harithasa--
Aditi V Harithasa--
R Venkatakrishna--
Indira A Rao--
Dinesh Todarwal--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 64.02 cr
Cost incurredRs 3.63 cr
Spent of the estimate5.68%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 64.02 crRs 3.38 cr
On-site expenditure-Salaries of workers-Rs 25.57 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKrishna Rao Associates .A.I.A.,LEED
EngineerMr.V.G.PALAKSHA

Litigation declared1

CaseCourtStatus
1491I ADD SENIOR CIVIL JUDGE BANGALORE RURAL-

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/220427/0009392-SGR BUILDTECH LLP27/04/2022

Documents filed78

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210129/003799 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SGR - RERA Certificate.pdf16 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architech Cert.pdf16 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineering Certificate.pdf16 Jul 2026
Q4 2025-26 Water supply and sewage board16 Jul 2026
Q4 2025-26 KPTCL- BESCOM16 Jul 2026
Q4 2025-26 Fire and Safety16 Jul 2026
Q4 2025-26 Airport Authority of India16 Jul 2026
Q4 2025-26 BSNL/Telecommunication Department16 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf23 Jun 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) 3.pdf23 Jun 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eng Certificate.pdf23 Jun 2026
Q3 2025-26 Water supply and sewage board23 Jun 2026
Q3 2025-26 KPTCL- BESCOM23 Jun 2026
Q3 2025-26 Fire and Safety23 Jun 2026
Q3 2025-26 Airport Authority of India23 Jun 2026
Q3 2025-26 BSNL/Telecommunication Department23 Jun 2026
Project End date change declarationFile: DECLARATION.pdf20 Jan 2021
SubmissionFile: Clarfication about end date G R FLORET.pdf30 Nov 2020
Bank StatementFile: Financial Statement.pdf28 Nov 2020
ClarificationFile: Clarfication about end date G R FLORET.pdf28 Nov 2020
CertificateFile: Certificate of Incorporation.pdf-
BBMP building licensec-
Site Plan1-
All plans-
Proforma of Agreement for Sale-
two sale deeds-
Section plan and Elevation5-
Site Plan1-
ALLOTMENT LETTER -G R FLORET-
Project Brochure-
Specification-
upto date Encumbrance Certificate-
SECTION 3 AFFIDAVIT-
JDA Affidavit cum DeclarationC-
Amalgamated Khatha Certificate and Extract-
JDA and GPA-
Partnership Agreement-
Conversion Order-
Unnamed document-
Unnamed document-
Unnamed document-
Relinquishment Deedc-
Fire NOC-
Airport authority of india-
BESCOM NOC-
BWSSB NOC-
KSPCB NOC-
SEIAA NOC-
Revised BSNL NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
All plans-
Section plan and specifications-
LEGAL OPINION-
Balance Sheet 2019 - 2020File: Balance Sheet 2017-18.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 2016-17.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet 2015-16.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and loss 2017-18.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and loss 2016-17.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit and loss 2015-16.pdf-
Auditor's Report 2019 - 2020File: Audit Report for FY - 2017 18.pdf-
Auditor's Report 2018 - 2019File: Auditors Report - FY - 2016 17.pdf-
Auditor's Report 2017 - 2018File: Auditors Report for F Y - 2015-16.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR V for F Y- 2017-18.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR V for F Y - 2016-17.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR V for F Y - 2015-16.pdf-
DECLARATION - FORM - B - AFFIDAVIT GRF -20112020-
Prospectus/BrochureFile: GR Floret Brochure.pdf-
Advertisement Copy 1File: Advertisement Copy.jpeg-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_210129_003799 (4).xlsx-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
G R REGENT PARK-Completed-No date filed
G R HEIGHTS-Completed-No date filed

How this compares with Bengaluru Urban

58%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep G R FLORET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SGR BUILDTECH LLP

SGR BUILDTECH LLP has 1 registration on RERA Karnataka, including G R FLORET. Its filings declare 2 earlier projects, 2 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if G R FLORET is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of G R FLORET?

The registered promoter entity is SGR BUILDTECH LLP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in G R FLORET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against G R FLORET?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at G R FLORET?

The professionals named in the filing: Architect: Krishna Rao Associates .A.I.A.,LEED; Engineer: Mr.V.G.PALAKSHA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in G R FLORET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About G R FLORET. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save G R FLORET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.