ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / fourwalls avenue

Registration approved No litigation declared Residential/Group Housing project

fourwalls avenue

By Fourwalls Avenue

RG-KA-25531 · RERA PRM/KA/RERA/1251/308/PR/220214/004703 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2026Possession promisedmoved 12 months from the original
19 of 19Construction stages doneevery applicable stage filed complete
103 of 203Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 106 documents Report an error

fourwalls avenue is a Residential/Group Housing project by Fourwalls Avenue in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/220214/004703 on 14 Feb 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 100 of the 203 units on this registration are recorded sold or booked, and 19 of 19 construction stages are filed complete.

At a glance

Project

  • Namefourwalls avenue
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/220214/004703
  • ReraGenie IDRG-KA-25531

Builder

  • NameFourwalls Avenue
  • Entity typePartnership Firm
  • Authorized SignatoryTANWEER
  • DirectorsB prasad, tanweer Ahmed Khan

Key dates

this monthRegisteredFeb 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed106 files

Current status

49%100 of 203 units booked
120.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Fourwalls Avenue---2030203

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 19 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja work100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes100%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,823 sq m
Named landowners4
LandownerVillageDistrict
Muniraju--
T.M Narayan Swamy--
R raghuramaiah--
Srinivas--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.00 cr
Cost incurredRs 36.02 cr
Spent of the estimate120.07%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 30.00 crRs 36.02 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHarinisree Associates
EngineerVaibhav

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/260305/004703Dec 2025 → Dec 2026

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/220214/004703 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Q1 2627.pdf15 Oct 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form - 5 - Architect Certificate Fourwalls Q1- 26-27.pdf15 Oct 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 - Engineering Certficate Fourwalls - Q1- 26-27.pdf15 Oct 2026
Q1 2026-27 Water supply and sewage board15 Oct 2026
Q1 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Q2 26 27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form - 5 - Architect Certificate Fourwalls Q2- 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 - Engineering Certficate Fourwalls - Q2- 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Q4 25 26.pdf13 Oct 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 6 Fw.pdf13 Oct 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 5 (1).pdf13 Oct 2026
Q4 2025-26 Water supply and sewage board13 Oct 2026
Q4 2025-26 KPTCL- BESCOM13 Oct 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4, CA Fourwalls Q3 2526.pdf9 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form - 5 - Architect Certificate Fourwalls Q3- 25-26.pdf9 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 - Engineering Certficate Fourwalls - Q3- 25-26.pdf9 Jan 2026
Q3 2025-26 Water supply and sewage board9 Jan 2026
Q3 2025-26 KPTCL- BESCOM9 Jan 2026
Proforma of AOS in accordance with the notified by GOKFile: FWA - AGREEMENT FOR SALE.pdf4 Feb 2022
Proforma of sale deed having required detailsFile: THIS DEED OF SALE.pdf4 Feb 2022
certified copy by the concerned Sub-registrar office regarding value of the property on theFile: Sub registrar certificate.pdf4 Feb 2022
Development DetailsFile: FWA - Apartment Details.pdf4 Feb 2022
Rera Account detailsFile: RERA ACCOUNT FOURWALLS.pdf13 Jan 2022
remaining fee receiptFile: Khajane payment - Fourwalls Avenue.pdf12 Nov 2021
Bank account as per reraFile: RERA ACCOUNT FOURWALLS.pdf12 Nov 2021
Drawing sheet 1File: Sanction sheet 1-optimized.pdf12 Nov 2021
Drawing sheet 2File: Sanction sheet 2-optimized.pdf12 Nov 2021
BSNL NOCFile: BSNL NOC.pdf12 Nov 2021
Partition deed 94/1File: Partition 94-1.PDF19 Oct 2021
Partition deed 94/3File: Partition 94-3.PDF19 Oct 2021
Form B with completetion date in mm/yy formatFile: Form B (1).pdf19 Oct 2021
EC Upto date 94/1File: EC sy no 94-1 (1).pdf19 Oct 2021
EC Upto date 94/3File: EC sy no 94-3 (1).pdf19 Oct 2021
Approved drawing sheet 1- Site plan,Basement planFile: Sanction sheet 1_compressed.pdf19 Oct 2021
Approved drawing sheet 2 - GF plan, upper floor typical plan, elevation,sectionFile: Sanction sheet 2.pdf19 Oct 2021
RElinquish DEEDFile: Relenquish Deed.PDF19 Oct 2021
NOC KSPCBFile: Pollution NOC.pdf19 Oct 2021
SEIAA NOCFile: SEIAA NOC.pdf19 Oct 2021
BSNL NOCFile: BSNL NOC.pdf19 Oct 2021
Project SpeceficationFile: Specification.pdf19 Oct 2021
Latitude and LongitudeFile: lati&longi.JPG19 Oct 2021
STP Document & drawingFile: Fourwalls STP.pdf19 Oct 2021
CertificateFile: Partnership Deed- Four walls Avenue.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1 Architect Certificate FW.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5 Engineers Certificate.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex3 CA Certificate sign.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex1 Architect Certificate FW.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6 Engineers Certificate.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4 CA Certificate sign (2)_11zon.pdf-
AffidavitFile: Form ex7.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Consent letter from 2/3rd of AllotteesFile: FWA Consent.pdf-
Details Of Sold/ Un-sold UnitsFile: FWA SoldUnsoldDetails.xlsx-
CC -Fourwalls Avenue-compressed-
Sanction plan Sheet 1-compressed_1-
Single Site Plan-
THIS DEED OF SALE-
Sale Agreement-
RTC-
Sanction plan Sheet 2-compressed-
Sanction plan Sheet 1-compressed_1-
ALLOTMENT LETTER-
Fourwalls - Brochure-compressed-
Specification-
EC-
Declaration-Affidavit-
Affidavit cum declaration LL&builder-
E khata -Fourwalls Avenue-
JDA - Four walls Avenue-
Unnamed document-
Conversion order-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Four Wall Fire Noc-compressed-

How this compares with Bengaluru Urban

49%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep fourwalls avenue on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmfourwalls avenueOther 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: Fourwalls Avenue

Fourwalls Avenue has 1 registration on RERA Karnataka, including fourwalls avenue. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if fourwalls avenue is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of fourwalls avenue?

The registered promoter entity is Fourwalls Avenue, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in fourwalls avenue?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at fourwalls avenue?

The professionals named in the filing: Architect: Harinisree Associates; Engineer: Vaibhav. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in fourwalls avenue?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About fourwalls avenue. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save fourwalls avenue to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.