Home / Browse projects / Bengaluru Urban, Karnataka / Flowing Tree

Registration approved Residential/Group Housing project

Flowing Tree

By Axis Concepts Capstone Pvt. ltd.

RG-KA-76720 · RERA PRM/KA/RERA/1251/472/PR/181122/002177 · Last updated on RERA Karnataka portal: 28 Nov 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Jan 2025Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 149 documents Report an error

Flowing Tree is a Residential/Group Housing project by Axis Concepts Capstone Pvt. ltd. in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/181122/002177 on 22 Nov 2018. Possession is promised by 3 Jan 2025. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameFlowing Tree
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/181122/002177
  • ReraGenie IDRG-KA-76720

Builder

  • NameAxis Concepts Capstone Pvt. ltd.
  • Entity typeCompany
  • CINU45205KA2012PTC066826
  • Authorized SignatorySK Prasanna
  • OthersHarish Babu
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2018First promiseApr 2023Revised toJan 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Nov 2018
  • Promised completion3 Jan 2025
  • Revised completionRevised to 3 Jan 2025 (originally 3 Apr 2023)
  • Buildings1 building record
  • Documents filed149 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Flowing Tree---1420142

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 28 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,905 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 74.67 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJayant Vaitha
EngineerBellad Dinesh Kumar

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApr 2023 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/472/PR/240205/002177not stated → Jan 2025

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed149

As listed on the registration, under the names the promoter filed them with; the newest 80 of 149 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/181122/002177 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Advisory for extention of validity and time limitFile: Advisory for extention of validity and time limit.pdf28 Nov 2022
BESCOM NOC - Allasandra ProjectFile: BESCOM NOC - Allasandra Project.pdf28 Nov 2022
Aditya Barjatya - FT 1303File: Aditya Barjatya - FT 1303.pdf28 Nov 2022
Anand Hiremath - FT 209File: Anand Hiremath - FT 209.pdf28 Nov 2022
Anurag Singh - FT 904File: Anurag Singh - FT 904.pdf28 Nov 2022
Balaji Kandaswamy -407File: Balaji Kandaswamy -407.pdf28 Nov 2022
Bhaskar Anand Rao - FT 303File: Bhaskar Anand Rao - FT 303.pdf28 Nov 2022
Girish Suresh Belagali - FT 606File: Girish Suresh Belagali - FT 606.pdf28 Nov 2022
Gowtham Lakshmi Venkateshwara - FT 603File: Gowtham Lakshmi Venkateshwara - FT 603.pdf28 Nov 2022
Harish P Ravi - FT 202File: Harish P Ravi - FT 202.pdf28 Nov 2022
Harish P Ravi - FT 1510File: Harish P Ravi - FT 1510.pdf28 Nov 2022
Kala Anand - FT 1101File: Kala Anand - FT 1101.pdf28 Nov 2022
Kala Anand - FT 1110File: Kala Anand - FT 1110.pdf28 Nov 2022
Keshavulu Naidu - FT 310File: Keshavulu Naidu - FT 310.pdf28 Nov 2022
Kiran Kumar - 506File: Kiran Kumar - 506.pdf28 Nov 2022
Kumarswamy - FT 1109File: Kumarswamy - FT 1109.pdf28 Nov 2022
Kumarswamy - FT 1509File: Kumarswamy - FT 1509.pdf28 Nov 2022
Mahendra - FT 508File: Mahendra - FT 508.pdf28 Nov 2022
Manish Patodi - FT 1409File: Manish Patodi - FT 1409.pdf28 Nov 2022
Natarajan Manthiramoorthy - FT 805File: Natarajan Manthiramoorthy - FT 805.pdf28 Nov 2022
Pooja Mishra - FT 308File: Pooja Mishra - FT 308.pdf28 Nov 2022
Prabhakaran Raghavan - FT 1304File: Prabhakaran Raghavan - FT 1304.pdf28 Nov 2022
Praghathi Hathwar - FT 1103File: Praghathi Hathwar - FT 1103.pdf28 Nov 2022
Praveen Rao -1504File: Praveen Rao -1504.pdf28 Nov 2022
Raaja Ganapathy - FT 206File: Raaja Ganapathy - FT 206.pdf28 Nov 2022
Rajendra Kumar Bandi - FT 803File: Rajendra Kumar Bandi - FT 803.pdf28 Nov 2022
Ramanath Ramakrishnan - FT 404File: Ramanath Ramakrishnan - FT 404.pdf28 Nov 2022
Ravi Sandesh - FT 808File: Ravi Sandesh - FT 808.pdf28 Nov 2022
Rejat U P - FT 109File: Rejat U P - FT 109.pdf28 Nov 2022
Sapna S Garampalli - FT 604File: Sapna S Garampalli - FT 604.pdf28 Nov 2022
Shankar B and Lucia P D - FT 1303File: Shankar B and Lucia P D - FT 1303.pdf28 Nov 2022
Shashidhar S Sangurmath - FT 403File: Shashidhar S Sangurmath - FT 403.pdf28 Nov 2022
Shashidhar S Sangurmath - FT 404File: Shashidhar S Sangurmath - FT 404.pdf28 Nov 2022
Sudipto Adhikari - FT 1001File: Sudipto Adhikari - FT 1001.pdf28 Nov 2022
Sudipto Adhikari - FT 1010File: Sudipto Adhikari - FT 1010.pdf28 Nov 2022
Sumit Bhosale - FT 101File: Sumit Bhosale - FT 101.pdf28 Nov 2022
Suresh Kumar P - FT 909File: Suresh Kumar P - FT 909.pdf28 Nov 2022
Tridiv Ojha - FT 806File: Tridiv Ojha - FT 806.pdf28 Nov 2022
Veera - FT 1202File: Veera - FT 1202.pdf28 Nov 2022
Vinod Kumar B - FT 105File: Vinod Kumar B - FT 105.pdf28 Nov 2022
Apply For Bank Account Change - Change of Bank applied on 12/05/2022File: 1 CHANGE OF BANK AC.pdf30 May 2022
THE NOC ISSUED BY SEIAA. - UPLOADEDFile: 2 AAI NOC.pdf30 May 2022
THE RELINQUISHMENT DEED - UPLOADEDFile: 3 Relinquishmnet Deed.pdf30 May 2022
Abstract of Sold and unsold details - UPLOADEDFile: 5 List of Allottes - Unit Sold - Unsold - FT - Copy.XLSX30 May 2022
List of Allottees - UPLOADEDFile: 6 List of Allottes.XLSX30 May 2022
the written consent letters of 2/3rd Allottees as per prescribed format available in RERA portal.File: 7 2 3rd Alotte.pdf30 May 2022
NOC issued by Airport visible copy - UPLOADEDFile: 2 AAI NOC.pdf30 May 2022
THE RENEWED NOC ISSUED BY BWSSB - UPLOADEDFile: 9 BWSSB.pdf30 May 2022
THE RENEWED NOC ISSUED BY BESCOM - UPLOADEDFile: 10 BESCOM.pdf30 May 2022
CertificateFile: Axis Concepts Capstone Pvt Ltd - COI.pdf-
Already registered project ongoing detailsFile: PRMKARERA1251472PR181122002177- FT.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: MODIFIED PLAN.pdf-
Elevation, Sections, Specifications ( If changes are there )File: MODIFIED PLAN.pdf-
List Of AllotteesFile: sold n unsold statement.pdf-
Consent LetterFile: 2 3rd Alotte.pdf-
Chartered Accountant CertificateFile: CA CERT Form 4.pdf-
Notarized AffidavitFile: Modification Affidavit axis.pdf-
Engineer CertificateFile: ENG CERT Form -6.pdf-
Architect CertificateFile: ARCH CERT Form-5.pdf-
Structural Engineer Certificate for stability of structureFile: STABILITY CERTIFICATE FLOWING TREE.pdf-
Modification of Plan DetailsFile: Site Plan.PDF-
Modification of Plan DetailsFile: MODIFIED PLAN.pdf-
Modification of Plan DetailsFile: Commenment Certificate.pdf-
Modification of Plan DetailsFile: Commenment Certificate.pdf-
Modification of Plan DetailsFile: sold n unsold statement.pdf-
Modification of Plan DetailsFile: sold n unsold statement.pdf-
Document 1File: Fire.pdf-
Document 2File: 2 AAI NOC.pdf-
Document 3File: 10 BESCOM.pdf-
Document 4File: 9 BWSSB.pdf-
Document 5File: KSPCBoard.pdf-
Document 6File: BSNL.pdf-
Application to submit Modified PlanFile: Application to submit Modified Plan.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate for Work Completion Schedule till Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate for Work Completion Schedule till Date.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate for Funds Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate for Pending Work Completion Schedule.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for Pending Work Completion Schedule.PDF-
CA Certificate for Funds required for Project CompletionFile: CA Certificate for Funds required for Project Completion.pdf-
AffidavitFile: Extension Affidavit.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Flowing Tree on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmFlowing TreeOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: Axis Concepts Capstone Pvt. ltd.

Axis Concepts Capstone Pvt ltd has 2 registrations on RERA Karnataka, including Experia and Flowing Tree. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Flowing Tree is delayed beyond 3 Jan 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Flowing Tree?

The registered promoter entity is Axis Concepts Capstone Pvt. ltd., a company as per the filing. Its CIN U45205KA2012PTC066826 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Flowing Tree?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Flowing Tree?

The professionals named in the filing: Architect: Jayant Vaitha; Engineer: Bellad Dinesh Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Flowing Tree?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Flowing Tree. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Flowing Tree to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.