Registration approved Residential/Group Housing project

Evershine Greenwood

By EVERSHINE DWELLINGS PVT LTD

RG-KA-09944 · RERA PRM/KA/RERA/1251/308/PR/180120/002409

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Oct 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 58 documents Report an error

Evershine Greenwood is a Residential/Group Housing project by EVERSHINE DWELLINGS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180120/002409 on 20 Jan 2018. Possession is promised by 1 Oct 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameEvershine Greenwood
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/180120/002409
  • ReraGenie IDRG-KA-09944

Builder

  • NameEVERSHINE DWELLINGS PVT LTD
  • Entity typeCompany
  • CINU45202KA2013PTC072430
  • Authorized SignatoryBhaskaran.K
  • DirectorManoj Kumar.B
  • Other registrations2 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2018First promiseJan 2022Revised toOct 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2018
  • Promised completion1 Oct 2022
  • Revised completionRevised to 1 Oct 2022 (originally 1 Jan 2022)
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GREENWOOD---1200120

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Ground Floor Slab Completion-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,856 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 18.50 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJan 2022 → Oct 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed58

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180120/002409 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: company registration form.pdf-
commencement certificate-
Building Plans-
single site approval-
Sale Deed - Evershine Greenwood-
Sale Agreement -Evershine Greenwood-
Sharing Ag GPA JDA-
cross section plan -
sarjapura cdp plan -
allotment proforma-
Evershine Greenwood-
Specifications-
EC-
Katha-
Sharing Ag GPA JDA-
Conversion-
FIRE noc sarjapura-
Bescom Noc-
PCB letter sarjapura -
single site approval-
cross section plan -
Rtc 569-3 & 569-2A -
Balance Sheet 2016 - 2017File: Balance sheet 2017.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 2016.pdf-
Balance Sheet 2014 - 2015File: Balance sheet 2015.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & loss 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Balance Sheet & Profit and Loss.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Balance Sheet & Profit and Loss.pdf-
Director's Report 2016 - 2017File: Directors Report 2017.pdf-
Director's Report 2015 - 2016File: Directors Report 2016.pdf-
Director's Report 2014 - 2015File: Directors Report 2015.pdf-
Cash Flow Statement 2016 - 2017File: CASH FLOW STATEMENT 2017.pdf-
Cash Flow Statement 2015 - 2016File: CASH FLOW STATEMENT 2016.pdf-
Auditor's Report 2016 - 2017File: 2017 Auditor Report.pdf-
Auditor's Report 2015 - 2016File: 2016 Auditor Report.pdf-
Auditor's Report 2014 - 2015File: 2015 Auditor Report.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: It Returns 2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: It Returns 2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: It Returns 2015.pdf-
Declaration Form-B-
Prospectus/BrochureFile: Evershine Greenwood (1).pdf-
Advertisement Copy 1File: Evershine Greenwood Broucher.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_180120_002409.xlsx-
Stability CertificateFile: Structural Stabilty Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Road cutting permission letter .pdf-
NOC issued by the Fire Force department after completion of workFile: Fire CC Greenwood.pdf-
Occupancy CertificateFile: Occupancy Certificate.pdf-
Consent for operation issued by KSPCBFile: KSPCB CC Grrenwood.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift Chief Electrical Inspector certificate.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Bescom Final Approval.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB NOC.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Details of external infrastructure.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Common Area and other amenities.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Evershine Greenwood UDS.pdf-
Architect certificate for having completed the work(in format no 5)File: Form-5, Architect Completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Auditor Form 4 CC Certificate.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit cum Declaration of Promoter.pdf-
completion certificateFile: Completion certificate .pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Evershine Greenwood on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmEvershine GreenwoodOther 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: EVERSHINE DWELLINGS PVT LTD

EVERSHINE DWELLINGS PVT LTD has 3 registrations on RERA Karnataka, including Evershine Greenwood and Evershine StonePark. Its filings declare 3 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Evershine Greenwood is delayed beyond 1 Oct 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Evershine Greenwood?

The registered promoter entity is EVERSHINE DWELLINGS PVT LTD, a company as per the filing. Its CIN U45202KA2013PTC072430 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Evershine Greenwood?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Evershine Greenwood?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Evershine Greenwood. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Evershine Greenwood to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.