Home / Browse projects / Bengaluru Urban, Karnataka / Estella Maple square Block A
Estella Maple square Block A
By Estella Projects Private Limited
RG-KA-79020 · RERA PRM/KA/RERA/1251/308/PR/180524/001815
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
Estella Maple square Block A is a Residential/Group Housing project by Estella Projects Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180524/001815 on 24 May 2018. Possession is promised by 30 Jun 2021. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameEstella Maple square Block A
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/180524/001815
- ReraGenie IDRG-KA-79020
Builder
- NameEstella Projects Private Limited
- Entity typeCompany
- Authorized SignatorySUDHAKAR AGANI
- Directorsvenkat reddy agani, vijayamm, MOHAN REDDY AGANI, sai kiran hampapuram
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 May 2018
- Promised completion30 Jun 2021
- Revised completionRevised to 30 Jun 2021 (originally 30 Jun 2020)
- Buildings1 building record
- Documents filed84 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLOCK A | - | - | - | 57 | 0 | 57 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Poornakriti |
| Engineer | Munish Sharma |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterApplied for modification
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01712/2023 | - | Estella Projects Private Limited | 16/11/2023 |
Documents filed84
As listed on the registration, under the names the promoter filed them with; the newest 80 of 84 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180524/001815 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: 5A.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: CERTIFICATE FOR WORK COMPL.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Estella A Block Extention.pdf | - |
| CA Certificate for Funds UtilizationFile: funds utilization certificate-project extension.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: CERTIFICATE FOR PENDING WORK.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending- for Extension of project .pdf | - |
| CA Certificate for Funds required for Project CompletionFile: funds required certificate-project extension.pdf | - |
| AffidavitFile: Affidavit for Extension of Estella Maple Square A Block.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails-Tower A.xlsx | - |
| Commencement | - |
| Site Plan | - |
| ESTELLA MAPLE SQUARE-Marked approved plan | - |
| RERA - Sale deed declaration | - |
| RERA - Sale deed declaration | - |
| Sale deed & RTC | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| RERA - Sale deed declaration | - |
| Marketing-ilovepdf-compressed | - |
| Marketing-ilovepdf-compressed | - |
| EC | - |
| Katha Maple square-SLN-22 | - |
| Binder1 Sca | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| SKM_C224e17053014450-KSPCBNOC-31-ilovepdf-compressed | - |
| certifi- incor | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| SKM_C224e17053014472-AIRPORT Authority of India NOC-28 | - |
| SKM_C224e17053014460- BESCOM NOC-29 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| SKM_C224e17053014470-BSNL NOC-33 | - |
| AVR -page-001 | - |
| Unnamed document | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| AVR -page-001 | - |
| Balance Sheet 2016 - 2017File: Balance sheet 2017.pdf | - |
| Balance Sheet 2015 - 2016File: Balance sheet 2016.pdf | - |
| Balance Sheet 2014 - 2015File: Balance sheet 2015.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Proit and loss 2017.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Profit and loss 2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Profit and loss 2015.pdf | - |
| Director's Report 2016 - 2017File: Director rept-17.pdf | - |
| Director's Report 2015 - 2016File: Director report 16.pdf | - |
| Director's Report 2014 - 2015File: Directors Report-15.pdf | - |
| Cash Flow Statement 2016 - 2017File: cash flow 2016 2017.pdf | - |
| Cash Flow Statement 2015 - 2016File: cash flow 2016 2017.pdf | - |
| Auditor's Report 2016 - 2017File: Auditor 2017.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor-16.pdf | - |
| Auditor's Report 2014 - 2015File: Auditor 2015.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITRV-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR -15.pdf | - |
| 20180521070800 | - |
| Prospectus/Brochure | - |
| Advertisement Copy 1 | - |
| Tower Excel SheetFile: PRMKARERA1251308PR180524001815.xlsx | - |
| Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: BESCOM 16-2-16.pdf | - |
| Occupancy CertificateFile: Occupancy Certificate.PDF | - |
| Consent for operation issued by KSPCBFile: KSPCB 21-4-16.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM 16-2-16.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM 16-2-16.pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: KSPCB 21-4-16.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form 5 Architect.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CA CC.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Completion Affidavit.PDF | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Estella Maple square Block A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 44 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Estella Projects Private Limited
Estella Projects Private Limited has 1 registration on RERA Karnataka, including Estella Maple square Block A. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Estella Maple square Block A is delayed beyond 30 Jun 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Estella Maple square Block A?
The registered promoter entity is Estella Projects Private Limited, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Estella Maple square Block A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Estella Maple square Block A?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Estella Maple square Block A?
The professionals named in the filing: Architect: Poornakriti; Engineer: Munish Sharma. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Estella Maple square Block A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback