Red flags
- 6 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EMPIRE INDUSTRIAL CENTRUM PHASE - I is a Others project by EMPIRE INDUSTRIES LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700006096 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2024. 6 complaints are on record with the regulator.
At a glance
Project
- NameEMPIRE INDUSTRIAL CENTRUM PHASE - I
- TypeOthers
- Location
- Ambarnath(M Cl)
- Ambarnath
- Thane
- 421505
- Pincode421505
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700006096
- ReraGenie IDRG-MH-12003
Builder
- NameEMPIRE INDUSTRIES LIMITED
- Entity typeCompany
- Other registrations4 more →
- Completed3 of 5
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on14 Aug 2017
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings5 building records
- Documents filed29 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DWARKA E1 | NA | 15 | 0 | 0 | 0 | 0 |
| UJJAIN E2 | NA | 15 | 0 | 0 | 0 | 0 |
| TAKSHASHILA F1 | NA | 15 | 0 | 0 | 0 | 0 |
| GUPTA A2 | NA | 4 | 0 | 0 | 0 | 0 |
| PALA A3 | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
55 of 55 construction stages are filed complete across 5 buildings.
DWARKA E1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
UJJAIN E2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
TAKSHASHILA F1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GUPTA A2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
PALA A3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | Yes | 15% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 5% |
| Electrical meter room, sub-station, receiving station | Yes | 5% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed225
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| DWARKA E1 | 11 | 25 | 36 |
| UJJAIN E2 | 11 | 25 | 36 |
| TAKSHASHILA F1 | 11 | 25 | 36 |
| GUPTA A2 | 0 | 53 | 53 |
| PALA A3 | 0 | 64 | 64 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prajacta Kambli |
| Engineer | Epicon Consultants Pvt Ltd |
| Partner | Role in project |
|---|---|
| EMPIRE INDUSTRIES LIMITED | - |
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000023871 | Ronald J Cardoza | Empire Industrial Centrum | 10/04/2018 |
| CC006000000057265 | Sunita Sanjeev Thorat | Empire Industries Limited | 11/12/2018 |
| CC006000000057785 | Gopalrao Pandharinath Yewale | Satish Chandra Malhotra | 21/02/2019 |
| CC006000000079115 | ROHINI ABHANG | Empire Industries LTD | 02/05/2019 |
| CC006000000194136 | Pranali Chohan | Empire Industries Limited | 22/09/2020 |
| CC006000000195785 | VISHAL AUTI | EMPIRE INDUSTRIES LIMITED | 31/01/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 May 2021
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: FORM-4 PHASE-1 A2 BUILDING.pdf | 24 Jan 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Pala certificate.pdf | 31 Oct 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Dwarka -certificate.pdf | 31 Oct 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Gupta- Certificate.pdf | 31 Oct 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Takshahsila- CErtificate.pdf | 31 Oct 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Ujjain- certificate.pdf | 31 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A2 2A-compressed.pdf | 4 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A3 2A_compressed.pdf | 4 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: E1 2A_compressed.pdf | 4 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: E2 FORM 2A_compressed.pdf | 4 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F1 FORM 2A_compressed.pdf | 4 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-Ph 1.pdf | 30 Sep 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: E1 Dwarka - F1 Takshashila - OC.pdf | 7 May 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A2 Gupta - A3 Pala OC.pdf | 7 May 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: E2 Ujjain - OC.pdf | 7 May 2021 |
| Certificates of CA (Form 5)File: Fom 5.pdf | 21 Dec 2018 |
| Declaration in FORM BFile: Form B - Notarised.pdf | 10 Aug 2017 |
| Certificates of CA (Form 3)File: Scan CA Certificate.pdf | 9 Aug 2017 |
| Proforma of Allotment letterFile: Draft Copy Allotment letter.pdf | 9 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 28 Jul 2017 |
| Building plan approvalFile: Approval for Bldg uc.pdf | 26 Jul 2017 |
| Layout approvalFile: Layout Plan.pdf | 26 Jul 2017 |
| PAN CardFile: Pan Card.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: Title Certificate.pdf | 26 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Plan.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Approval for Bldg uc.pdf | 26 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: MIDC-RO-2-Thane - AMB-1630001.pdf | 26 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 29 filed documents as one ZIP, foldered, with a manifest
Keep EMPIRE INDUSTRIAL CENTRUM PHASE - I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambarnath(M Cl)7,600+ in Thane
Filed coordinates, straight-line distance. 149 registered projects within 2 km.
MATOSHREE NAGAR EXCELLENCY BLDG SAPPHIRE A AND
MATOSHREE SHELTERS (INDIA) PRIVATE LIMITED
NIDHI RESIDENCY
ADITYA YASH BUILDERS
MIDTOWN B AND C WING
SIDDHIVINAYAK GROUP NX
PATELS LEGACY
RAPID CORPORATION
PATELS ETERNITY
OMKAR INFRASTRUCTURE
Harishree Celestial-1
HARISHREE CREATIONS
See every Thane project, with the district possession charts
Builder: EMPIRE INDUSTRIES LIMITED
EMPIRE INDUSTRIES LIMITED has 5 registrations on MahaRERA, including EMPIRE INDUSTRIAL CENTRUM PHASE - I and Empire Industrial Centrum - Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if EMPIRE INDUSTRIAL CENTRUM PHASE - I is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EMPIRE INDUSTRIAL CENTRUM PHASE - I?
The registered promoter entity is EMPIRE INDUSTRIES LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EMPIRE INDUSTRIAL CENTRUM PHASE - I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EMPIRE INDUSTRIAL CENTRUM PHASE - I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EMPIRE INDUSTRIAL CENTRUM PHASE - I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EMPIRE INDUSTRIAL CENTRUM PHASE - I?
The professionals named in the filing: Architect: Prajacta Kambli; Engineer: Epicon Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EMPIRE INDUSTRIAL CENTRUM PHASE - I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback