Home / Browse projects / Bengaluru Urban, Karnataka / Elysium at Brigade Cornerstone Utopia

Registration approved Litigation declared Commercial project

Elysium at Brigade Cornerstone Utopia

By Mysore Projects Private Limited

RG-KA-66149 · RERA PRM/KA/RERA/1251/446/PR/040924/006987 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
19 of 19Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 130 documents Report an error

Elysium at Brigade Cornerstone Utopia is a Commercial project by Mysore Projects Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/040924/006987 on 4 Sep 2024. Possession is promised by 30 Jun 2026. 0 of the 19 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameElysium at Brigade Cornerstone Utopia
  • TypeCommercial
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/040924/006987
  • ReraGenie IDRG-KA-66149

Builder

  • NameMysore Projects Private Limited
  • Entity typeCompany
  • CINU70102KA2010PTC054771
  • GSTIN29AAGCM7611Q1ZS
  • Authorized SignatoryA Arvind Rao
  • DirectorsPavitra Shankar, Pavitra Shankar, Roshin Mathew, Manjunatha Prasad
  • Project HeadManjunath Prasad
  • Other registrations6 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredSep 2024PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Sep 2024
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed130 files

Current status

0%0 of 19 units booked
0.0%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Elysium at Brigade Cornerstone Utopia---01919

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners3
LandownerVillageDistrict
Cornerstone Bay East Developers Private Limited--
G. Narayanappa--
M. Prasad--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 178.77 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 138.07 cr-
Payment of taxesRs 24.93 cr-
On-site expenditure-Site OverheadRs 9.10 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 6.10 cr-
On-site expenditure-Salaries of workersRs 39.41 lakh-
On-site expenditure-Consultants FeesRs 15.81 lakh-
Payment of PremiumsRs 68,447-
Payment of cessRs 60,312-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC B Vivek Uthaiah
EngineerPrasad Consultants
Chartered AccountantR. Srinivasan

Litigation declared1

CaseCourtStatus
51Civil Judge-K R Puram-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed130

As listed on the registration, under the names the promoter filed them with; the newest 80 of 130 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/040924/006987 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 MPPL (Elysium at Brigade Cornerstone Utopia).pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Elysium - Form 5 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Elysium - Form 6 - Q1.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Elysium at Brigade Cornerstone Utopia - Form 4 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Elysium - Form 5 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Elysium - Form 6 - Q4.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Elysium - Form 4 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Elysium - Form 5 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Elysium - Form 6 - Q3.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
Elsyium - Form 1 - CA CertificateFile: Elysium - Form 1 - CA Certificate.pdf17 Jul 2024
Encumbrance Certificate - Sy No. 183/3File: EC - Sy No 183-3.pdf17 Jul 2024
Litigation AffidavitFile: Elysium - Affidavit - Litigation.pdf17 Jul 2024
Blownup Plan with Area DetailsFile: Blownup Plan.PDF17 Jul 2024
CDP MapFile: Brigade Cornerstone Utopia - CDP and Village Map Extracts.pdf17 Jul 2024
Structral Stability CertificateFile: Elysium - Strl Stability Certificate.pdf17 Jul 2024
Elysium Carpet Area DetailsFile: Elysium - Carpet Area Details.pdf17 Jul 2024
Guideline Value detailsFile: Elysium - Guideline Value.pdf17 Jul 2024
Allotment LetterFile: Elysium - Allotment Letter.pdf17 Jul 2024
NOC LetterFile: NOC Letter.pdf17 Jul 2024
Reply LetterFile: Reply Letter.pdf17 Jul 2024
Sanction Plan - Blown UpFile: Site Plan and Blownup Plan.pdf17 Jul 2024
RTC, survey 183/3-
Mutation, survey 183/3-
Encumbrance Certificate, survey 183/3-
Conversion/Alienation Order, survey 183/3-
Sale/Title/Gift Deed, survey 183/3-
JDA, survey 183/3-
Khatha, survey 183/3-
Registration CertificateFile: MPPL Certificate of Incorporation (1).pdf-
Memorandum of AssociationFile: MOA & AOA - MPPL - Updated.pdf-
Article of AssociationFile: MOA & AOA - MPPL - Updated.pdf-
Organization StructureFile: Organogram.xls-
Certificate issued by CA Form 1File: Elysium - Form 1 - CA Certificate.pdf-
Certificate issued by Architect Form 2File: Elysium - Form 2.pdf-
Certificate issued by Engineer Form 3File: Elysium - Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
Land Litigation Details-
Land Litigation Details-
Certificate from Chartered AccountFile: Elysium - Approval Certificate.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet - 2023-2024.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet - 2022-2023.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet - 2021-2022.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss - 2023-2024.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss - 2022-2023.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss - 2021-2022.pdf-
Director's Report 2022 - 2023File: Directors Report - 2022-2023_compressed.pdf-
Director's Report 2021 - 2022File: Directors Report - 2022-2023_compressed.pdf-
Director's Report 2020 - 2021File: Directors Report - 2021-2022_compressed_compressed.pdf-
Cash Flow Statement 2022 - 2023File: Cash Flow - 2023-2024.pdf-
Cash Flow Statement 2021 - 2022File: Cash Flow - 2022-2023.pdf-
Auditor's Report 2022 - 2023File: Auditor Report - 2023-2024_compressed_compressed.pdf-
Auditor's Report 2021 - 2022File: Auditor Report - 2022-2023_compressed.pdf-
Auditor's Report 2020 - 2021File: Auditor Report - 2021-2022_compressed.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITRV - 2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITRV - 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITRV - 2020-21.pdf-
Brigade Cornerstone Utopia - Commencement Certificate - Building 1-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Elysium at Brigade Cornerstone Utopia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Mysore Projects Private Limited

Mysore Projects Private Limited has 7 registrations on RERA Karnataka, including Elysium at Brigade Cornerstone Utopia and Serene at Brigade Cornerstone Utopia. Its filings declare 4 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Elysium at Brigade Cornerstone Utopia is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Elysium at Brigade Cornerstone Utopia?

The registered promoter entity is Mysore Projects Private Limited, a company as per the filing. Its CIN U70102KA2010PTC054771 and GSTIN 29AAGCM7611Q1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Elysium at Brigade Cornerstone Utopia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Elysium at Brigade Cornerstone Utopia?

The professionals named in the filing: Architect: C B Vivek Uthaiah; Engineer: Prasad Consultants; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Elysium at Brigade Cornerstone Utopia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Elysium at Brigade Cornerstone Utopia. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Elysium at Brigade Cornerstone Utopia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.